Deedo IDDP-THN-75KCCompletion was pushed back 4 months, to May 2028; no MahaRERA orders on record; 0% of its units are booked.
Gandhare, Thane 421301 · by Nivara Constructions
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to May 2028
- This projectRegistered 17 Feb 2026, completion promised 1 Jan 2028, revised to 1 May 2028.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationPM1330002502382
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| PM1330002502382 | 17 Feb 2026 | 1 Jan 2028 | 1 May 2028 | Nivara Constructions | Project page |
Documents47
1 document held by Deedo, 46 filings listed on MahaRERA's project page
Finance
Show all 47 documentsShow fewer documents
Legal
- OthersNivara Constructions Partnership deed (Address change).pdf · uploaded 9 Jan 2026Source
- Declaration Form BPRCard.pdf · uploaded 9 Jan 2026Source
- Declaration Form BLegal Title Report.pdf · uploaded 10 Jan 2026Source
- OthersClarification Letter for past experience.pdf · uploaded 3 Feb 2026Source
- OthersDeviations with respect to the proforma of the agreement for sale.pdf · uploaded 12 Feb 2026Source
Migrated
- Withdrawal Update Form 1Form 1 Mar-26.pdf · uploaded 26 May 2026Source
- Withdrawal Update Form 1Form 1 Mar-26.pdf · uploaded 26 May 2026Source
- Withdrawal Update Form 1Form 1 Mar-26.pdf · uploaded 26 May 2026Source
- Withdrawal Update Form 1Form 1 Mar-26.pdf · uploaded 26 May 2026Source
- Withdrawal Update Form 2Form-2 Mar 26.pdf · uploaded 26 May 2026Source
- Withdrawal Update Form 2Form-2 Mar 26.pdf · uploaded 26 May 2026Source
- Withdrawal Update Form 2Form-2 Mar 26.pdf · uploaded 26 May 2026Source
- Withdrawal Update Form 2Form-2 Mar 26.pdf · uploaded 26 May 2026Source
- Withdrawal Update Form 3CA Certificate_Mar 26.pdf · uploaded 26 May 2026Source
- Withdrawal Update Form 3CA Certificate_Mar 26.pdf · uploaded 26 May 2026Source
- Withdrawal Update Form 3CA Certificate_Mar 26.pdf · uploaded 26 May 2026Source
- Withdrawal Update Form 3CA Certificate_Mar 26.pdf · uploaded 26 May 2026Source
- Withdrawal Update Form 1Form 1_Jun 26.pdf · uploaded 20 Aug 2026Source
- Withdrawal Update Form 1Form 1_Jun 26 (1).pdf · uploaded 20 Aug 2026Source
- Withdrawal Update Form 2Form 2_Jun 26.pdf · uploaded 20 Aug 2026Source
- Withdrawal Update Form 2Form 2_Jun 26.pdf · uploaded 20 Aug 2026Source
- Withdrawal Update Form 3Form 3_Jun 26.pdf · uploaded 20 Aug 2026Source
- Withdrawal Update Form 3Form 3_Jun 26.pdf · uploaded 20 Aug 2026Source
Planning Authority
- Document1730718608_KDMCC-24-19273_R0.html · uploaded 9 Jan 2026Source
- Document1730718608_KDMCC-24-19273_R0.pdf_2_60DSE_Sign.pdfSign.pdf · uploaded 9 Jan 2026Source
- DocumentyUxIRidhpx7-12_(4).pdf · uploaded 9 Jan 2026Source
- DocumentCert_B_429660_446EbUBxSign.pdf · uploaded 9 Jan 2026Source
- DocumentyUxIRidhpxDevelopment_agreement.pdf · uploaded 9 Jan 2026Source
Technical
- DocumentLayout Approval Plan.pdf · uploaded 29 Dec 2025Source
- DocumentSanctioned Plan.pdf · uploaded 29 Dec 2025Source
- DocumentDeclaration- One Plot One Registration 01.pdf · uploaded 10 Jan 2026Source
- OthersFormat D.pdf · uploaded 10 Jan 2026Source
- OthersForm 1 Kanchanjunga Nivara RERA.pdf · uploaded 10 Jan 2026Source
- OthersForm 2 Kanchanjunga Nivara RERA.pdf · uploaded 10 Jan 2026Source
- OthersNotarised Copy of Clarification Letter.pdf · uploaded 10 Jan 2026Source
- OthersClarification Letter for Tenant units.pdf · uploaded 3 Feb 2026Source
- OthersClarification Letter for land details as per CC.pdf · uploaded 5 Feb 2026Source
Technical (Architect)
- DocumentForm 1_Jun 26 (1).pdf · uploaded 20 Aug 2026Source
Technical (Engineer)
- DocumentForm 2_Jun 26.pdf · uploaded 20 Aug 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 43, 43/S.No. 29
As registered with MahaRERA and published on its project page
- Project type
- Mixed
- Status on MahaRERA
- Certificate Signed
- Unit types
- —34 units in all
- Address
- Amrut Park Road, Sector 3, GandharePIN 421301
- Village
- Gandhare, Kalyan taluka
- Location
- 19.24033, 73.13054
- Land area for this project
- 670 sq m (7,212 sq ft)
- Permissible built-up area
- 2,176 sq m (23,423 sq ft)
- Sanctioned built-up area
- 2,158 sq m (23,230 sq ft)
- Recreational open space
- 0 sq m (0 sq ft)
- Designated bank account
- 51
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
S.No. 29, H.No. 8 and 9, PLOT No. 42 and 43/S.No. 29, H.no. 8 and 9, Plot no.42 and 43
Boundaries
- North
- Property of S. No 20
- South
- Dayal Apartment
- East
- 9 Mtr. Road
- West
- Plot No. 44
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking34 units
34 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 34 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals1
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Engineer | Ram Vitthal Marathe | — |