Shree Astaganesh Chs
Deedo IDDP-THN-8V9YCompletion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 0% of its units are booked.
Dombivli, Thane 421201 · by Shree Laxmi Realty
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2027
- This projectRegistered 22 Mar 2024, completion promised 31 Dec 2026, revised to 30 Apr 2027.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
- Building (P51700055452)Size not on record0% booked
- Shree Asta Ganesh Chs Ltd8 floors · 33 units0% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700055452
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700055452 | 22 Mar 2024 | 31 Dec 2026 | 30 Apr 2027 | Shree Laxmi Realty | Project page |
Documents63
2 documents held by Deedo, 61 filings listed on MahaRERA's project page
Show all 63 documentsShow fewer documents
Migrated
- 1 Commencement Certificates / NA Order for plotted developmentCopy of CC.pdf · uploaded 26 Dec 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE FORM 1.pdf · uploaded 26 Dec 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)RERA ENGINEER CERTIFICATE FORM 2.pdf · uploaded 26 Dec 2023Source
- 1 Declaration about Commencement CertificateDECLARATION COMMENCEMENT .pdf · uploaded 27 Dec 2023Source
- 1 Proforma of Allotment letterALLOTMENT DRAFT.pdf · uploaded 27 Dec 2023Source
- 1 Proforma of Agreement for saleAGREEMENT FOR SALE.pdf · uploaded 27 Dec 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentblue print_compressed (1).pdf · uploaded 15 Feb 2024Source
- 1 Copy of the legal title reportTitle Report-MahaRERA Format.pdf · uploaded 1 Mar 2024Source
- 2 Copy of the legal title reportCopy of the legal title report-Search report.pdf · uploaded 1 Mar 2024Source
- 1 a Details of encumbrances concerned to FinanceEC-Finance.pdf · uploaded 1 Mar 2024Source
- 2 a Details of encumbrances concerned to FinanceEC-Legal.pdf · uploaded 1 Mar 2024Source
- 1 b Details of encumbrances concerned to LegalEC-Finance.pdf · uploaded 1 Mar 2024Source
- 2 b Details of encumbrances concerned to LegalEC-Legal.pdf · uploaded 1 Mar 2024Source
- 1 CERSAI details1 CERSAI details.pdf · uploaded 1 Mar 2024Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest.pdf · uploaded 1 Mar 2024Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest-2.pdf · uploaded 1 Mar 2024Source
- 3 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest-3.pdf · uploaded 1 Mar 2024Source
- 4 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest-4.pdf · uploaded 1 Mar 2024Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A-Bank Declaration.pdf · uploaded 1 Mar 2024Source
- 1 Deviation Report with respect to Allotment letterDevation Report-Allotment Letter.pdf · uploaded 1 Mar 2024Source
- 1 Deviation Report with respect to model copy of AgreementDevation Report-AFS.pdf · uploaded 1 Mar 2024Source
- 1 Other – TechnicalFormat - D.pdf · uploaded 1 Mar 2024Source
- 2 Other – TechnicalAnnexure-A.pdf · uploaded 1 Mar 2024Source
- 1 Declaration in FORM BFrom-B-Developers.pdf · uploaded 13 Mar 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate-Final-140324.pdf · uploaded 14 Mar 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_March 24.pdf · uploaded 19 Feb 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_June 24.pdf · uploaded 19 Feb 2025Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_Sep 24.pdf · uploaded 19 Feb 2025Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_Dec 24.pdf · uploaded 19 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_March 24.pdf · uploaded 19 Feb 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_June 24.pdf · uploaded 19 Feb 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_Sep 24.pdf · uploaded 19 Feb 2025Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_Dec 24.pdf · uploaded 19 Feb 2025Source
- 1 Disclosure of sold/ booked inventoryDisclosure of Sold Booked Inventory - March 24.pdf · uploaded 19 Feb 2025Source
- 2 Disclosure of sold/ booked inventoryDisclosure of Sold Booked Inventory - June 24.pdf · uploaded 19 Feb 2025Source
- 3 Disclosure of sold/ booked inventoryDisclosure of Sold Booked Inventory - Sep 24.pdf · uploaded 19 Feb 2025Source
- 4 Disclosure of sold/ booked inventoryDisclosure of Sold Booked Inventory - Dec 24.pdf · uploaded 19 Feb 2025View
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_Mar.pdf · uploaded 20 Feb 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_Jun-24.pdf · uploaded 20 Feb 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_Sep-24-Signed Copy.pdf · uploaded 20 Feb 2025Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_Dec-24.pdf · uploaded 20 Feb 2025Source
Technical
Technical (Architect)
Technical (Engineer)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 4772. Mouje Ayre, CTS No. 4771
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK33 units in all
- Address
- Survey No. 65 H. No. 2 (Pt), Plot No. 7, CTS No. 4771 & 4772. Mouje Ayre, Sai Nagar, Sunil Nagar, Dombivli, Kalyan, Thane-421 201., SAI NAGAR, SUNIL NAGARPIN 421201
- Village
- Dombivli, Kalyan taluka
- Land area for this project
- 588 sq m (6,324 sq ft)
- Permissible built-up area
- 2,235 sq m (24,059 sq ft)
- Sanctioned built-up area
- 2,235 sq m (24,059 sq ft)
- Designated bank account
- 82
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Survey No. 65 H. No. 2 (Pt), Plot No. 7, CTS No. 4771 & 4772. Mouje Ayre, Sai Nagar, Sunil Nagar, Dombivli, Kalyan, Thane-421 201.
Boundaries
- North
- Shiv Parvati CHS
- South
- Kamdhenu CHS
- East
- Vanvasi Kalyan Ashram and Shivraj CHS Ltd
- West
- Society Road and Aditya Mhatre Chawal
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking33 units
0 of 33 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 29.98 sq m · 323 sq ft | 1 | 0 |
| 1BHK | 30.29 sq m · 326 sq ft | 1 | 0 |
| 1BHK | 32.95 sq m · 355 sq ft | 5 | 0 |
| 1BHK | 34.79 sq m · 374 sq ft | 7 | 0 |
| 2BHK | 41.68 sq m · 449 sq ft | 6 | 0 |
| 2BHK | 43.27 sq m · 466 sq ft | 7 | 0 |
| 2BHK | 43.43 sq m · 467 sq ft | 6 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Ninad Vaidya | — |
| Chartered accountant | Abhilash Gupta | — |
| Engineer | Omkar V Joshi | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Dombivli
- Mali ShivalayaRERA PM1330002602683
- Shiv SadanRERA PR1330002602567
- Bhargav Co-Op Housing Society LimitedRERA PM1330002602519
- The MeadowsRERA PR1330002601825
- Om Ganesh PujaRERA PR1330002601796
- Payal Business ParkRERA PC1330002600694
- VedvikaRERA PR1330002600676
- YashrajRERA PM1330002600521
All 445 projects in Dombivli · Compare Shree Astaganesh Chs with another project