Residential / Group Housing · 2 buildings · 40 unitsRERA P51700053444

Saraswati Devi Krupa

Deedo IDDP-THN-SF8E

Completion was pushed back 4 months, to Nov 2026; no MahaRERA orders on record; 45% of its units are booked.

Dombivli, Thane 421202 · by Yogiraj Heritage

DeliveryExtended 4 moPromised Jul 2026 · now due Nov 2026RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales45% booked18 of 40 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Nov 2026

  • This projectRegistered 1 Nov 2023, completion promised 31 Jul 2026, revised to 30 Nov 2026.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700053444
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P517000534441 Nov 202331 Jul 202630 Nov 2026Yogiraj HeritageProject page
Documents89

1 document held by Deedo, 88 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardYogiraj PAN Card.pdf · uploaded 21 Aug 2023Source

Legal

  • Legal Title reportLegal Title Report.pdf · uploaded 21 Aug 2023Source
  • Legal Title reportSearch REPORT Mayur N Surte.pdf · uploaded 21 Aug 2023Source
  • Declaration Form BBalachandra Wani.pdf · uploaded 21 Aug 2023Source
  • Declaration Form BAshok Shah.pdf · uploaded 30 Oct 2023Source
  • Declaration Form BAshok-Prabhakar Khatti.pdf · uploaded 30 Oct 2023Source

Migrated

  • 1 PAN CardYogiraj PAN Card.pdf · uploaded 21 Aug 2023Source
Show all 89 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reportLegal Title Report.pdf · uploaded 21 Aug 2023Source
  • 2 Copy of the legal title reportSearch REPORT Mayur N Surte.pdf · uploaded 21 Aug 2023Source
  • 1 a Details of encumbrances concerned to FinanceFinance Encumbrance Declaration 002.pdf · uploaded 21 Aug 2023Source
  • 2 a Details of encumbrances concerned to FinanceLegal enclumbrance declaration 001.pdf · uploaded 21 Aug 2023Source
  • 1 b Details of encumbrances concerned to LegalFinance Encumbrance Declaration 002.pdf · uploaded 21 Aug 2023Source
  • 2 b Details of encumbrances concerned to LegalLegal enclumbrance declaration 001.pdf · uploaded 21 Aug 2023Source
  • 1 Copy of Layout Approval (in case of layout)Plan Layout 1.pdf · uploaded 21 Aug 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentPlan Layout 2.pdf · uploaded 21 Aug 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentPrabhakar khatti Commencement Certificate.pdf · uploaded 21 Aug 2023Source
  • 1 Declaration about Commencement CertificateDeckaration_Commencement Certificate.pdf · uploaded 21 Aug 2023Source
  • 2 Declaration about Commencement CertificateAfiidavit Form B Prabhakar Khati_11zon.pdf · uploaded 21 Aug 2023Source
  • 1 Declaration in FORM BBalachandra Wani.pdf · uploaded 21 Aug 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architects Certificate.pdf · uploaded 21 Aug 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engg Certificate.pdf · uploaded 21 Aug 2023Source
  • 1 CERSAI detailsCersai Report.pdf · uploaded 21 Aug 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAshok Shah_Annexure A.pdf · uploaded 21 Aug 2023Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A_Rasiklal Shah.pdf · uploaded 21 Aug 2023Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsHarshad Patil_Annexure A.pdf · uploaded 21 Aug 2023Source
  • 4 Disclosure of Interest in Other Real Estate OrganizationsTrupri Patil_Annexure A.pdf · uploaded 21 Aug 2023Source
  • 1 Proforma of Agreement for saleModel Form Agreement_11zon.pdf · uploaded 21 Aug 2023Source
  • 1 Proforma of Allotment letterAnn1_Model Form Of Allotment Letter_11zon.pdf · uploaded 21 Aug 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank detail -Rera 001.pdf · uploaded 21 Aug 2023Source
  • 1 Deviation Report with respect to Allotment letterDeviation Allotment.pdf · uploaded 21 Aug 2023Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation AFS.pdf · uploaded 21 Aug 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA certificate_11zon.pdf · uploaded 22 Aug 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentCC Confirmation Mail SS.pdf · uploaded 30 Oct 2023Source
  • 2 Declaration in FORM BAshok Shah.pdf · uploaded 30 Oct 2023Source
  • 3 Declaration in FORM BAshok-Prabhakar Khatti.pdf · uploaded 30 Oct 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate_Saraswati Devi Krupa_QPR3.pdf · uploaded 30 Jan 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engg Certificate_Saraswati Devi Krupa_QPR3.pdf · uploaded 30 Jan 2024Source
  • 1 Disclosure of sold/ booked inventorySold Unsold Disclosure.pdf · uploaded 30 Jan 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA Certificate Saraswati Devi Krupa_QPR3_11zon.pdf · uploaded 30 Jan 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 QPR4 Saraswati Devi Krupa.pdf · uploaded 22 Apr 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 QPR4 Saraswati Devi Krupa.pdf · uploaded 22 Apr 2024Source
  • 2 Disclosure of sold/ booked inventoryInventory Disclosure QPR4.pdf · uploaded 22 Apr 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 QPR4 Saraswati Devi Krupa.pdf · uploaded 22 Apr 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Arch Certificate_Yogiraj heritage_QPR1_2024-25.pdf · uploaded 22 Jul 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engg Certificate_Yogiraj heritage_QPR1_2024-25.pdf · uploaded 22 Jul 2024Source
  • 3 Disclosure of sold/ booked inventorySold Unsold_Yogiraj Heritage_QPR1_2024-25.pdf · uploaded 22 Jul 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 QPR1_24-25_Saraswati Devikrupa.pdf · uploaded 22 Jul 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Yogiraj Heriatge.pdf · uploaded 7 Nov 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 QPR2 Yogiraj heritage CA certificate_11zon.pdf · uploaded 7 Nov 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)heritage Engineer Certificate.pdf · uploaded 7 Nov 2024Source
  • 1 Disclosure of sold/ booked inventoryyogiraj heritage sold unsold data.pdf · uploaded 7 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate.pdf · uploaded 28 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA Certificate.pdf · uploaded 28 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate.pdf · uploaded 28 Mar 2025Source
  • 1 Disclosure of sold/ booked inventoryHeritage Sold unsold flat.pdf · uploaded 28 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form -1 Yogiraj Heritage Architect's Certificate.pdf · uploaded 8 May 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form -3 Yogiraj Heritage C A Certificate_compressed.pdf · uploaded 8 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form -2 Yogiraj Heritage Engineer's Certificate.pdf · uploaded 8 May 2025Source
  • 1 Disclosure of sold/ booked inventoryHeritage Sold Unsold Disclosure .pdf · uploaded 8 May 2025Source
  • Form 1Form 1 Architect Cetificate.pdf · uploaded 8 Aug 2025Source
  • Form 2Form 2 Engineer Certificate.pdf · uploaded 8 Aug 2025Source
  • Form 3Form 3 CA Certificate.pdf · uploaded 8 Aug 2025Source
  • Disclosure of Sold and Booked InventoryDisclosure of Sold Unsold.pdf · uploaded 8 Aug 2025Source
  • Form 5 (FY 2024-2025)Yogiraj Heritage Form-5.pdf · uploaded 17 Dec 2025Source
  • Form 1Form -1 Architect Certificate Heritage.pdf · uploaded 24 Dec 2025Source
  • Form 2Form -1 Architect Certificate Heritage.pdf · uploaded 24 Dec 2025Source
  • Form 3Form-3 Yogiraj Heritage.pdf · uploaded 24 Dec 2025Source
  • Disclosure of Sold and Booked InventoryDisclosure of sold unsold.pdf · uploaded 24 Dec 2025Source
  • Form 1Architect Certificate - yogiraj heritage.pdf · uploaded 4 Mar 2026Source
  • Form 2Engineers Certificate yogiraj Heritage.pdf · uploaded 4 Mar 2026Source
  • Form 3Form -3 yogiraj heritage.pdf · uploaded 4 Mar 2026Source
  • Disclosure of Sold and Booked Inventoryyogiraj Heritage Rera Q3 sold unsold disclosure.pdf · uploaded 4 Mar 2026Source
  • Withdrawal Update Form 1Form 1 Arch Certificate_Yogiraj heritage_QPR1_2024-25.pdf · uploaded 26 Jun 2026Source
  • Withdrawal Update Form 2Form 2 Engineering certificate.pdf · uploaded 26 Jun 2026Source
  • Withdrawal Update Form 3Form 3 Shivleela.pdf · uploaded 26 Jun 2026Source
  • Withdrawal Update Form 1Form 1 Arch Certificate_Yogiraj heritage_QPR1_2024-25.pdf · uploaded 30 Sep 2026Source
  • Withdrawal Update Form 2Form 2 Engineering certificate.pdf · uploaded 30 Sep 2026Source
  • Withdrawal Update Form 3Form -3.pdf · uploaded 30 Sep 2026Source

Technical

  • DocumentPlan Layout 1.pdf · uploaded 21 Aug 2023Source
  • DocumentPlan Layout 2.pdf · uploaded 21 Aug 2023Source

Technical (Architect)

  • DocumentForm 1 Arch Certificate_Yogiraj heritage_QPR1_2024-25.pdf · uploaded 22 Jul 2024Source
  • DocumentArchitect Certificate Yogiraj Heriatge.pdf · uploaded 7 Nov 2024Source
  • DocumentForm 1 Architect Certificate.pdf · uploaded 28 Mar 2025Source
  • DocumentForm -1 Yogiraj Heritage Architect's Certificate.pdf · uploaded 8 May 2025Source

Technical (Engineer)

  • Documentheritage Engineer Certificate.pdf · uploaded 7 Nov 2024Source
  • DocumentForm 2 Engineer Certificate.pdf · uploaded 28 Mar 2025Source
  • DocumentForm -2 Yogiraj Heritage Engineer's Certificate.pdf · uploaded 8 May 2025Source
  • DocumentForm 2 Engineering certificate.pdf · uploaded 30 Sep 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 2977, 2978

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, 3BHK, 1RK40 units in all
Address
2977, 2978, 2979, Ram Mandir Road, Ram Mandir Road No 5PIN 421202
Village
Dombivli, Kalyan taluka
Land area for this project
753 sq m (8,100 sq ft)
Permissible built-up area
2,608 sq m (28,077 sq ft)
Sanctioned built-up area
2,608 sq m (28,077 sq ft)
Designated bank account
200
Developed in phases
Yes

Survey, CTS, gat or plot numbers

297729782979

Land as published on MahaRERA's project page

2977,2978,2979

Boundaries

North
Pushkaraj Bunglow And Ushakal Bunglow
South
12mtr Wide Road
East
9mtr Wide Road
West
Dwarka Sadan Bunglow

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking40 units

18 of 40 units booked (45%), as the promoter reported to MahaRERA

1BHK · 17 units2BHK · 18 units3BHK · 4 units1RK · 1 unit
BuildingTypeCarpet areaUnitsBooked
DEVI KRUPA-BUILDING No 21BHK47.67 sq m · 513 sq ft53
DEVI KRUPA-BUILDING No 22BHK62.14 sq m · 669 sq ft50
DEVI KRUPA-BUILDING No 22BHK66.26 sq m · 713 sq ft54
DEVI KRUPA-BUILDING No 23BHK81.15 sq m · 873 sq ft20
DEVI KRUPA-BUILDING No 23BHK94.34 sq m · 1,015 sq ft20
SARASWATI KRUPA-BUILDING No 11BHK49.06 sq m · 528 sq ft64
SARASWATI KRUPA-BUILDING No 11BHK54 sq m · 581 sq ft64
SARASWATI KRUPA-BUILDING No 11RK36.8 sq m · 396 sq ft10
SARASWATI KRUPA-BUILDING No 12BHK66.37 sq m · 714 sq ft10
SARASWATI KRUPA-BUILDING No 12BHK68.87 sq m · 741 sq ft73

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectA One Architects—
Chartered accountantA V Khatu & Co—
EngineerRajesh Thakare And Asscoiates—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Dombivli

All 445 projects in Dombivli · Compare Saraswati Devi Krupa with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology