Completion was pushed back 4 months to Jul 2026, and that date has passed too; no MahaRERA orders on record; 0% of its units are booked.

Dombivli, Thane 421201 · by Parisparsh

Delivery8 mo latePromised Mar 2026 · revised Jul 2026 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 22 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months to Jul 2026, and that date has passed too

  • This projectRegistered 10 May 2019, completion promised 30 Mar 2026, revised to 30 Jul 2026, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700020807
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170002080710 May 201930 Mar 202630 Jul 2026ParisparshProject page
Documents173

1 document held by Deedo, 172 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardParisparsh Pan Card.pdf · uploaded 24 Apr 2019Source
  • DocumentAvenue conveyance Index 2.pdf · uploaded 31 Jul 2026Source
  • DocumentAvenue Society regn certificate.pdf · uploaded 31 Jul 2026Source

Legal

  • Legal Title reporttitle certificate.pdf · uploaded 24 Apr 2019Source
  • Declaration Form BForm B.pdf · uploaded 24 Apr 2019Source

Migrated

  • 1 PAN CardParisparsh Pan Card.pdf · uploaded 24 Apr 2019Source
  • 1 Copy of the legal title reporttitle certificate.pdf · uploaded 24 Apr 2019Source
Show all 173 documentsShow fewer documents

Migrated

  • 1 Details of encumbrancesencumberances_letter.pdf · uploaded 24 Apr 2019Source
  • 1 Copy of Layout Approval (in case of layout)Plan Copy-min.pdf · uploaded 24 Apr 2019Source
  • 1 Building Plan Approval (IOD)Plan Copy-min.pdf · uploaded 24 Apr 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommecement Certificate.pdf · uploaded 24 Apr 2019Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 24 Apr 2019Source
  • 1 Proforma of Allotment letterFinal rera_allotment___agreement_sale.pdf · uploaded 27 Apr 2019Source
  • 1 Certificates of CA (Form 3)Form 3.pdf · uploaded 29 Apr 2019Source
  • 2 Details of encumbrancesno_encumberance letter.pdf · uploaded 23 Aug 2019Source
  • 2 Commencement Certificates / NA Order for plotted developmentLatest Revised Sanction - 30-03-2022_compressed.pdf · uploaded 4 Apr 2022Source
  • 2 Proforma of Allotment letterAGREEMENT FOR SALE - DRAFT.pdf · uploaded 4 Apr 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)1) Architect Certificate - 09-09-2019.pdf · uploaded 24 Sep 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)2) Architect Certificate - 09-12-2019.pdf · uploaded 24 Sep 2022Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)3) Architect Certificate - 09-03-2020.pdf · uploaded 24 Sep 2022Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)4) Architect Certificate - 15-10-2020.pdf · uploaded 24 Sep 2022Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)5) Architect Certificate - 13-02-2021.pdf · uploaded 24 Sep 2022Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)6) Architect Certificate - 17-06-2021.pdf · uploaded 24 Sep 2022Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)7) Architect Certificate - 15-09-2021.pdf · uploaded 24 Sep 2022Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)8) Architect Certificate - 02-01-2022.pdf · uploaded 24 Sep 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)11) 09092019 Parisparsh Avenue.pdf · uploaded 24 Sep 2022Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)12) 09122019 Parisparsh Avenue.pdf · uploaded 24 Sep 2022Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)13) 09032020 Parisparsh Avenue.pdf · uploaded 24 Sep 2022Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)14) 15102020 Parisparsh Avenue.pdf · uploaded 24 Sep 2022Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)15) 13022021 Parisparsh Avenue.pdf · uploaded 24 Sep 2022Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)16) 17062021 Parisparsh Avenue.pdf · uploaded 24 Sep 2022Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)17) 15092021 Parisparsh Avenue.pdf · uploaded 24 Sep 2022Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)18) 02012022 Parisparsh Avenue.pdf · uploaded 24 Sep 2022Source
  • 1 Disclosure of sold/ booked inventoryScan 1.pdf · uploaded 24 Sep 2022Source
  • 2 Disclosure of sold/ booked inventoryRera Uploaded File - Table C.pdf · uploaded 25 Nov 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Annual Report Rera March 2020.pdf · uploaded 20 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Annual Report Rera March 2021.pdf · uploaded 20 Feb 2023Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Annual Report Rera March 2022.pdf · uploaded 20 Feb 2023Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)01-04-2019 To 31-03-2020.pdf · uploaded 23 Mar 2023Source
  • 3 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)01-04-2020 To 31-03-2021.pdf · uploaded 23 Mar 2023Source
  • 4 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)01-04-2021 To 31-03-2022.pdf · uploaded 23 Mar 2023Source
  • 1 Declaration about Commencement CertificateThe 23' Avenue OC wing B 21-02-2023.pdf · uploaded 19 May 2023Source
  • 3 Disclosure of sold/ booked inventoryDisclosure of Sold - Booked Inventory.pdf · uploaded 6 Jul 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)GetUserDocumentFileContent.pdf · uploaded 7 Oct 2023Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)9) Architect Certificate - 25-04-2022.pdf · uploaded 18 Oct 2023Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)25042022 Parisparsh Avenue.pdf · uploaded 18 Oct 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 FY 22-23.pdf · uploaded 2 Apr 2024Source
  • 1 Certificates of CA (Form 3)Form- 3 CA Cert 18-2-2025.pdf · uploaded 18 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 28 Feb 2025Source
  • Form 1Form 1 Jun 24.pdf · uploaded 9 Sep 2026Source
  • Form 2Form 2 Jun 24.pdf · uploaded 9 Sep 2026Source
  • Form 3Form 3 Jun 24.pdf · uploaded 9 Sep 2026Source
  • Disclosure of Sold and Booked InventoryForm 3 Jun 24.pdf · uploaded 9 Sep 2026Source
  • Form 1Form 1 05 oct 2023 aug to sep23.pdf · uploaded 9 Sep 2026Source
  • Form 2Form 2 Sep 19.pdf · uploaded 9 Sep 2026Source
  • Form 3form 3 2025.pdf · uploaded 9 Sep 2026Source
  • Disclosure of Sold and Booked Inventoryform 3 2025.pdf · uploaded 9 Sep 2026Source
  • Form 1form 1 06 01 25 oct to dec24.pdf · uploaded 9 Sep 2026Source
  • Form 2Form 2 Mar 22.pdf · uploaded 9 Sep 2026Source
  • Form 3form 3 2025.pdf · uploaded 9 Sep 2026Source
  • Disclosure of Sold and Booked Inventoryform 3 2025.pdf · uploaded 9 Sep 2026Source
  • Form 1form 1 06 01 2024 oct to dec23.pdf · uploaded 9 Sep 2026Source
  • Form 2Form 2 Mar 22.pdf · uploaded 9 Sep 2026Source
  • Form 3form 3 2025.pdf · uploaded 9 Sep 2026Source
  • Disclosure of Sold and Booked Inventoryform 3 2025.pdf · uploaded 9 Sep 2026Source
  • Form 1Form 1 07 10 24 jul to sep24.pdf · uploaded 9 Sep 2026Source
  • Form 2Form 2 Mar 22.pdf · uploaded 9 Sep 2026Source
  • Form 3form 3 2025.pdf · uploaded 9 Sep 2026Source
  • Disclosure of Sold and Booked Inventoryform 3 2025.pdf · uploaded 9 Sep 2026Source
  • Form 1form 1 10 04 2024 jan to mar24.pdf · uploaded 9 Sep 2026Source
  • Form 2Form 2 Mar 22.pdf · uploaded 9 Sep 2026Source
  • Form 3form 3 2025.pdf · uploaded 9 Sep 2026Source
  • Disclosure of Sold and Booked Inventoryform 3 2025.pdf · uploaded 9 Sep 2026Source
  • Form 1form 1 15 04 2025 jan to mar25.pdf · uploaded 9 Sep 2026Source
  • Form 2Form 2 Mar 22.pdf · uploaded 9 Sep 2026Source
  • Form 3form 3 2025.pdf · uploaded 9 Sep 2026Source
  • Disclosure of Sold and Booked Inventoryform 3 2025.pdf · uploaded 9 Sep 2026Source
  • Withdrawal Update Form 1form 1 08 10 25 jul to sep25.pdf · uploaded 9 Sep 2026Source
  • Withdrawal Update Form 2Form 2 Mar 22.pdf · uploaded 9 Sep 2026Source
  • Withdrawal Update Form 3form 3 2025.pdf · uploaded 9 Sep 2026Source
  • Form 1Form 1 05 oct 2023 aug to sep23.pdf · uploaded 10 Sep 2026Source
  • Form 2Form 2 Sep 19.pdf · uploaded 10 Sep 2026Source
  • Form 3form 3 2025.pdf · uploaded 10 Sep 2026Source
  • Disclosure of Sold and Booked InventoryFORM 5 2023-2024.pdf · uploaded 10 Sep 2026Source
  • Form 1Form 1 05 oct 2023 aug to sep23.pdf · uploaded 10 Sep 2026Source
  • Form 2Form 2 Dec 19.pdf · uploaded 10 Sep 2026Source
  • Form 3form 3 2025.pdf · uploaded 10 Sep 2026Source
  • Disclosure of Sold and Booked InventoryFORM 5 2023-2024.pdf · uploaded 10 Sep 2026Source
  • Form 1Form 1 05 oct 2023 aug to sep23.pdf · uploaded 10 Sep 2026Source
  • Form 2Form 2 Dec 19.pdf · uploaded 10 Sep 2026Source
  • Form 3form 3 2025.pdf · uploaded 10 Sep 2026Source
  • Disclosure of Sold and Booked Inventoryform 3 2025.pdf · uploaded 10 Sep 2026Source
  • Form 1Form 1 05 oct 2023 aug to sep23.pdf · uploaded 10 Sep 2026Source
  • Form 2Form 2 Dec 19.pdf · uploaded 10 Sep 2026Source
  • Form 3form 3 2025.pdf · uploaded 10 Sep 2026Source
  • Disclosure of Sold and Booked Inventoryform 3 2025.pdf · uploaded 10 Sep 2026Source
  • Form 1Form 1 05 oct 2023 aug to sep23.pdf · uploaded 10 Sep 2026Source
  • Form 2Form 2 Mar 22.pdf · uploaded 10 Sep 2026Source
  • Form 3form 3 2025.pdf · uploaded 10 Sep 2026Source
  • Disclosure of Sold and Booked Inventoryform 3 2025.pdf · uploaded 10 Sep 2026Source
  • Form 1Form 1 05 oct 2023 aug to sep23.pdf · uploaded 10 Sep 2026Source
  • Form 2Form 2 Dec 19.pdf · uploaded 10 Sep 2026Source
  • Form 3form 3 2025.pdf · uploaded 10 Sep 2026Source
  • Disclosure of Sold and Booked Inventoryform 3 2025.pdf · uploaded 10 Sep 2026Source
  • Form 1Form 1 05 oct 2023 aug to sep23.pdf · uploaded 10 Sep 2026Source
  • Form 2Form 2 Sep 20.pdf · uploaded 10 Sep 2026Source
  • Form 3form 3 2025.pdf · uploaded 10 Sep 2026Source
  • Disclosure of Sold and Booked Inventoryform 3 2025.pdf · uploaded 10 Sep 2026Source
  • Form 1Form 1 05 oct 2023 aug to sep23.pdf · uploaded 10 Sep 2026Source
  • Form 2Form 2 Dec 20.pdf · uploaded 10 Sep 2026Source
  • Form 3form 3 2025.pdf · uploaded 10 Sep 2026Source
  • Disclosure of Sold and Booked Inventoryform 3 2025.pdf · uploaded 10 Sep 2026Source
  • Form 1Form 1 05 oct 2023 aug to sep23.pdf · uploaded 10 Sep 2026Source
  • Form 2Form 2 Mar 21.pdf · uploaded 10 Sep 2026Source
  • Form 3form 3 2025.pdf · uploaded 10 Sep 2026Source
  • Disclosure of Sold and Booked Inventoryform 3 2025.pdf · uploaded 10 Sep 2026Source
  • Form 1Form 1 05 oct 2023 aug to sep23.pdf · uploaded 10 Sep 2026Source
  • Form 2Form 2 Jun 21.pdf · uploaded 10 Sep 2026Source
  • Form 3form 3 2025.pdf · uploaded 10 Sep 2026Source
  • Disclosure of Sold and Booked Inventoryform 3 2025.pdf · uploaded 10 Sep 2026Source
  • Form 1Form 1 05 oct 2023 aug to sep23.pdf · uploaded 10 Sep 2026Source
  • Form 2Form 2 Jun 21.pdf · uploaded 10 Sep 2026Source
  • Form 3form 3 2025.pdf · uploaded 10 Sep 2026Source
  • Disclosure of Sold and Booked Inventoryform 3 2025.pdf · uploaded 10 Sep 2026Source
  • Form 1Form 1 05 oct 2023 aug to sep23.pdf · uploaded 10 Sep 2026Source
  • Form 2Form 2 Dec 21.pdf · uploaded 10 Sep 2026Source
  • Form 3form 3 2025.pdf · uploaded 10 Sep 2026Source
  • Disclosure of Sold and Booked Inventoryform 3 2025.pdf · uploaded 10 Sep 2026Source
  • Form 1Form 1 05 oct 2023 aug to sep23.pdf · uploaded 10 Sep 2026Source
  • Form 2Form 2 Mar 22.pdf · uploaded 10 Sep 2026Source
  • Form 3form 3 2025.pdf · uploaded 10 Sep 2026Source
  • Disclosure of Sold and Booked Inventoryform 3 2025.pdf · uploaded 10 Sep 2026Source
  • Form 1Form 1 05 oct 2023 aug to sep23.pdf · uploaded 10 Sep 2026Source
  • Form 2Form 2 Mar 22.pdf · uploaded 10 Sep 2026Source
  • Form 3form 3 2025.pdf · uploaded 10 Sep 2026Source
  • Disclosure of Sold and Booked Inventoryform 3 2025.pdf · uploaded 10 Sep 2026Source
  • Form 1Form 1 05 oct 2023 aug to sep23.pdf · uploaded 10 Sep 2026Source
  • Form 2Form 2 Mar 22.pdf · uploaded 10 Sep 2026Source
  • Form 3form 3 2025.pdf · uploaded 10 Sep 2026Source
  • Disclosure of Sold and Booked Inventoryform 3 2025.pdf · uploaded 10 Sep 2026Source
  • Form 1Form 1 05 oct 2023 aug to sep23.pdf · uploaded 10 Sep 2026Source
  • Form 2Form 2 Mar 22.pdf · uploaded 10 Sep 2026Source
  • Form 3form 3 2025.pdf · uploaded 10 Sep 2026Source
  • Disclosure of Sold and Booked Inventoryform 3 2025.pdf · uploaded 10 Sep 2026Source
  • Form 1Form 1 05 oct 2023 aug to sep23.pdf · uploaded 10 Sep 2026Source
  • Form 2Form 2 Mar 22.pdf · uploaded 10 Sep 2026Source
  • Form 3form 3 2025.pdf · uploaded 10 Sep 2026Source
  • Disclosure of Sold and Booked Inventoryform 3 2025.pdf · uploaded 10 Sep 2026Source
  • Withdrawal Update Form 1form 1 08 10 25 jul to sep25.pdf · uploaded 10 Sep 2026Source
  • Withdrawal Update Form 1form 1 08 10 25 jul to sep25.pdf · uploaded 10 Sep 2026Source
  • Withdrawal Update Form 1form 1 08 10 25 jul to sep25.pdf · uploaded 10 Sep 2026Source
  • Withdrawal Update Form 1form 1 08 10 25 jul to sep25.pdf · uploaded 10 Sep 2026Source
  • Withdrawal Update Form 2Form 2 Mar 22.pdf · uploaded 10 Sep 2026Source
  • Withdrawal Update Form 2Form 2 Mar 22.pdf · uploaded 10 Sep 2026Source
  • Withdrawal Update Form 2Form 2 Mar 22.pdf · uploaded 10 Sep 2026Source
  • Withdrawal Update Form 2Form 2 Mar 22.pdf · uploaded 10 Sep 2026Source
  • Withdrawal Update Form 3form 3 2025.pdf · uploaded 10 Sep 2026Source
  • Withdrawal Update Form 3form 3 2025.pdf · uploaded 10 Sep 2026Source
  • Withdrawal Update Form 3form 3 2025.pdf · uploaded 10 Sep 2026Source
  • Withdrawal Update Form 3form 3 2025.pdf · uploaded 10 Sep 2026Source
  • Form 5 (FY 2019-2020)FORM 5 2023-2024.pdf · uploaded 10 Sep 2026Source
  • Form 5 (FY 2020-2021)FORM 5 2023-2024.pdf · uploaded 10 Sep 2026Source
  • Form 5 (FY 2021-2022)FORM 5 2023-2024.pdf · uploaded 10 Sep 2026Source
  • Form 5 (FY 2022-2023)FORM 5 2023-2024.pdf · uploaded 10 Sep 2026Source
  • Form 5 (FY 2023-2024)FORM 5 2023-2024.pdf · uploaded 10 Sep 2026Source
  • Form 5 (FY 2024-2025)FORM 5 2024-2025.pdf · uploaded 10 Sep 2026Source
  • Form 5 (FY 2025-2026)FORM 5 2025-2026.pdf · uploaded 10 Sep 2026Source

Technical

  • DocumentPlan Copy-min.pdf · uploaded 24 Apr 2019Source
  • DocumentPlan Copy-min.pdf · uploaded 24 Apr 2019Source

Technical (Architect)

  • DocumentForm 1.pdf · uploaded 28 Feb 2025Source
  • Documentform 1 08 10 25 jul to sep25.pdf · uploaded 10 Sep 2026Source

Technical (Engineer)

  • DocumentForm 2 Mar 22.pdf · uploaded 9 Sep 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 12132 A, 12132B

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
Type 1, Type 2, Type 3, Commercial Type 1, Office Type 1, Office Type 2, Office Type 3, Office Type 4, Office Type 5, Office Type 6, Shop Type 1, Shop Type 2, Shop Type 3, Shop TYpe 422 units in all
Address
12132 A, 12132B, 4th Cross Lane, Rajaji Path, RamnagarPIN 421201
Village
Dombivli, Kalyan taluka
Land area for this project
1,802 sq m (19,394 sq ft)
Permissible built-up area
2,090 sq m (22,500 sq ft)
Sanctioned built-up area
976 sq m (10,501 sq ft)
Designated bank account
82
Developed in phases
Yes

Survey, CTS, gat or plot numbers

12132 A12132B

Land as published on MahaRERA's project page

12132 A, 12132B

Boundaries

North
Kdmc Road
South
Jagdamba Society
East
Suraj Chs
West
Navkrishana Dham Chs

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking22 units

0 of 22 units booked (0%), as the promoter reported to MahaRERA

Type 1 · 1 unitType 2 · 1 unitType 3 · 1 unitCommercial Type 1 · 2 unitsOffice Type 1 · 2 unitsOffice Type 2 · 2 unitsOffice Type 3 · 2 unitsOffice Type 4 · 2 unitsOffice Type 5 · 2 unitsOffice Type 6 · 2 unitsShop Type 1 · 1 unitShop Type 2 · 1 unitShop Type 3 · 1 unitShop TYpe 4 · 2 units
BuildingTypeCarpet areaUnitsBooked
DiamondType 152.14 sq m · 561 sq ft10
DiamondType 275.43 sq m · 812 sq ft10
DiamondType 349.41 sq m · 532 sq ft10
PearlCommercial Type 1243.5 sq m · 2,621 sq ft20
PearlOffice Type 131.6 sq m · 340 sq ft20
PearlOffice Type 232.9 sq m · 354 sq ft20
PearlOffice Type 330.1 sq m · 324 sq ft20
PearlOffice Type 425.79 sq m · 278 sq ft20
Show all 14 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
PearlOffice Type 524.21 sq m · 261 sq ft20
PearlOffice Type 623.14 sq m · 249 sq ft20
PearlShop Type 122.97 sq m · 247 sq ft10
PearlShop Type 231.37 sq m · 338 sq ft10
PearlShop Type 326.39 sq m · 284 sq ft10
PearlShop TYpe 432.21 sq m · 347 sq ft20

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDhanashri Rajesh Bhosale—
Chartered accountantAnand Chandak—
Chartered accountantA T Upadhye and Co—
EngineerManohar Patil—

Source: MahaRERA project page. Contact details are not shown.