Extended 4 mo8 floorsRERA P51700079659
Main building, Jay Pooja Darshan
Deedo IDDP-THN-RHQ3-JPDMahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked0%0 of 18 · MahaRERA
Completion31 Jul 202731 Mar 2027 · revised
Units & parking in Main building
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 44.9 m² (484 sq.ft) | 1 | 0 |
| 2BHK Land Owner Flat | 56.3 m² (606 sq.ft) | 1 | 0 |
| 2BHK land Owners Fla | 62 m² (667 sq.ft) | 1 | 0 |
| 2BHK Land Owners Fla | 56.4 m² (607 sq.ft) | 4 | 0 |
| 2BHK Land Owners Fla | 58.2 m² (626 sq.ft) | 2 | 0 |
| 2BHK Land Owners Fla | 60.1 m² (647 sq.ft) | 3 | 0 |
| 3BHK | 77.3 m² (832 sq.ft) | 3 | 0 |
| 3 BHK Land Owners Fl | 91.8 m² (988 sq.ft) | 1 | 0 |
| Office space | 199.3 m² (2,145 sq.ft) | 1 | 0 |
| Office space | 253.8 m² (2,732 sq.ft) | 1 | 0 |
As registered with MahaRERA
- RERA registration
- P51700079659 · registered 18 Mar 2025
- Promised completion
- 31 Mar 2027
- Revised completion
- 31 Jul 2027
- Sanctioned habitable floors
- 8
- Building
- Jay Pooja Darshan
- Sanctioned floors (incl. basement, stilt, podium)
- 8
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-THN-RHQ3-JPD
Questions about Main building
When is Main building due for completion?
The MahaRERA registration promises 31 Mar 2027, revised to 31 Jul 2027.
How many floors does Main building have?
8 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology