Balaji Vishant
Deedo IDDP-THN-2Q12It is due for completion in Dec 2026, with no extension on record; no MahaRERA orders on record; 89% of its units are booked.
Dombivli, Thane 421201 · by Sairaj Builders
Buying a flat here?
See every deed registered on it.
It is due for completion in Dec 2026, with no extension on record
- This projectRegistered 28 Nov 2022, completion promised 31 Dec 2026.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
4 buildings
Open a building to see every flat, floor by floor.
- B3Size not on record100% booked
- B6Size not on record100% booked
- BalaiiVishantSize not on record86% booked
- Main building20 floors · 92 units89% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700047811
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700047811 | 28 Nov 2022 | 31 Dec 2026 | 31 Dec 2026 | Sairaj Builders | Project page |
Documents90
2 documents held by Deedo, 88 filings listed on MahaRERA's project page
Show all 90 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)Plan 1.pdf · uploaded 23 Sep 2022Source
- 2 Copy of Layout Approval (in case of layout)Plan 2.pdf · uploaded 23 Sep 2022Source
- 1 Building Plan Approval / NA Order for plotted developmentPlan 1.pdf · uploaded 23 Sep 2022Source
- 2 Building Plan Approval / NA Order for plotted developmentPlan 2.pdf · uploaded 23 Sep 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentCC- Sairaj Builders.pdf · uploaded 23 Sep 2022Source
- 1 Declaration about Commencement CertificateDeclaration about commencent certificate.pdf · uploaded 23 Sep 2022Source
- 1 Declaration in FORM BSanjay Singh - Form -B.pdf · uploaded 23 Sep 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form- 1.pdf · uploaded 23 Sep 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form - 2.pdf · uploaded 23 Sep 2022Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration for Seprate bank account.pdf · uploaded 23 Sep 2022Source
- 1 Deviation Report with respect to Allotment letterDeviation report of allotment letter.pdf · uploaded 24 Sep 2022Source
- 1 Deviation Report with respect to model copy of AgreementDeviataion report of ATS.pdf · uploaded 24 Sep 2022Source
- 1 CERSAI detailsCERSAI.pdf · uploaded 26 Sep 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3-1.pdf · uploaded 29 Sep 2022Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3-2.pdf · uploaded 29 Sep 2022Source
- 1 Proforma of Allotment letterAllotment letter-BALAJI VISHANT-RERA.pdf · uploaded 17 Oct 2022Source
- 1 Proforma of Agreement for saleAllotment letter-BALAJI VISHANT-RERA.pdf · uploaded 17 Oct 2022Source
- 1 Copy of the legal title reportTitle report.pdf · uploaded 18 Oct 2022Source
- 2 Proforma of Agreement for saleAgreement for Sale-BALAJI VISHANT-RERA.pdf · uploaded 18 Oct 2022Source
- 2 Proforma of Allotment letterAgreement for Sale-BALAJI VISHANT-RERA.pdf · uploaded 18 Oct 2022Source
- 3 Copy of Layout Approval (in case of layout)Plan 1.pdf · uploaded 28 Feb 2023Source
- 4 Copy of Layout Approval (in case of layout)Plan 2.pdf · uploaded 28 Feb 2023Source
- 2 Commencement Certificates / NA Order for plotted developmentCC_compressed.pdf · uploaded 28 Feb 2023Source
- 2 Declaration about Commencement CertificateRara Format- D - SRD.pdf · uploaded 28 Feb 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Balaji Vishant - Form - 1 - Dt - 01012023.pdf · uploaded 23 Sep 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Balaji Vishant - Form - 1 - Dt - 01042023.pdf · uploaded 23 Sep 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Balaji Vishant - Form - 1 - Dt - 01072023.pdf · uploaded 27 Sep 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Balaji Vishant - Form 2 - 02012023.pdf · uploaded 27 Sep 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Balaji Vishant - Form 2 - 03042023_compressed.pdf · uploaded 27 Sep 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Balaji Vishant 31122022-1-5_compressed.pdf · uploaded 27 Sep 2023Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Balaji Vishant 31122022-6-10_compressed.pdf · uploaded 27 Sep 2023Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Balaji Vishant 31032023-1-5_compressed.pdf · uploaded 27 Sep 2023Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Balaji Vishant 31032023-6-10_compressed.pdf · uploaded 27 Sep 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)SRB BALAJI VISHANT FORM 2A MAR 23.pdf · uploaded 3 Oct 2023Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)From 3- Balaji Vishant June 2023-1-4_compressed.pdf · uploaded 23 Oct 2023Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)From 3- Balaji Vishant June 2023-5-9_compressed.pdf · uploaded 23 Oct 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Balaji Vishant June 2023_compressed.pdf · uploaded 3 Nov 2023Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 of Balaji Vishant Sept 2023_compressed.pdf · uploaded 18 Nov 2023Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 of Balaji Vishant Sept 2023Compress.pdf · uploaded 18 Nov 2023Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Balaji Vishant - Form 1 - 01102023.pdf · uploaded 30 Nov 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 Vishant 2022 23.pdf · uploaded 28 Dec 2023Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)SAIRAJ- FORM 3_compressed.pdf · uploaded 22 Jan 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2_compressed.pdf · uploaded 30 Jan 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Balaji Vishant - Form 1 - Dt - 01012024.pdf · uploaded 12 Mar 2024Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Balaji Vishant - Form 1 - Dt 01-04-2024.pdf · uploaded 22 May 2024Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 of Balaji Vishant March 2024.pdf · uploaded 6 Jun 2024Source
- 1 Disclosure of sold/ booked inventoryDisclosure -Sairaj.pdf · uploaded 6 Jun 2024View
- 2 Disclosure of sold/ booked inventoryInventory Disclosure Balaji Vishant.pdf · uploaded 6 Jun 2024Source
- 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Balaji Vishant March 2024.pdf · uploaded 6 Jun 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Balaji Vishant - March 2024.pdf · uploaded 18 Jun 2024Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Balaji Vishant - Form 1 - Dt 01-07-2024.pdf · uploaded 30 Jul 2024Source
- 3 Disclosure of sold/ booked inventoryInventory Balaji Vishant Jun 24.pdf · uploaded 30 Jul 2024Source
- 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)Balaji Vishant - Form 3 - Dt - 30-06-2024_compressed.pdf · uploaded 30 Jul 2024Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Balaji Vishant June 2024.pdf · uploaded 13 Aug 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 balaji vishant 24.pdf · uploaded 29 Oct 2024Source
- 2 Disclosure of sold/ booked inventoryBalaji Vishant - Sold Inventory .pdf · uploaded 29 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)SRB BALAJI VISHANT FORM 2A SEP 2024.pdf · uploaded 20 Nov 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Balaji Vishant Form 1.pdf · uploaded 27 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 Balaji Vishant 23 24.pdf · uploaded 25 Dec 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Balaji Vishant - Form 1 - Dt 01-01-2025 .pdf · uploaded 29 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Vishant Dec 2024.pdf · uploaded 29 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Vishant Dec 2024.pdf · uploaded 29 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryDisclosure Vishant Dec 24.pdf · uploaded 29 Jan 2025View
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Balaji Vishant - Date 01-04-2025.pdf · uploaded 30 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Signed Form 3 Balaji Vishant March 2025_compressed.pdf · uploaded 30 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 of Balaji vishant March 2025.pdf · uploaded 30 Apr 2025Source
- 1 Disclosure of sold/ booked inventoryInventory disclosure Balaji Vishant March 2025.pdf · uploaded 30 Apr 2025View
- Form 2A (FY 2024-2025)Balaji Vishant - Form 2A - March 25.pdf · uploaded 4 Apr 2026Source
Technical
Technical (Architect)
- DocumentBalaji Vishant - Form 1 - Dt 01-07-2024.pdf · uploaded 30 Jul 2024Source
- DocumentBalaji Vishant Form 1.pdf · uploaded 27 Nov 2024Source
- DocumentBalaji Vishant - Form 1 - Dt 01-01-2025 .pdf · uploaded 29 Jan 2025Source
- DocumentForm 1 - Balaji Vishant - Date 01-04-2025.pdf · uploaded 30 Apr 2025Source
Technical (Engineer)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 100 (new), 9B
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, Office space, Shop92 units in all
- Address
- Survey No. 88 (old), 100 (new), Hissa No 9A and 9B, Kanchangaon, Dombivli EastPIN 421201
- Village
- Dombivli, Kalyan taluka
- Land area for this project
- 1,600 sq m (17,222 sq ft)
- Permissible built-up area
- 6,238 sq m (67,142 sq ft)
- Sanctioned built-up area
- 6,064 sq m (65,267 sq ft)
- Designated bank account
- 220
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Survey No. 88 (old), 100 (new), Hissa No 9A and 9B
Boundaries
- North
- open plot S No 100 hissa no 1
- South
- KMC Skyline UC Building
- East
- 24 meter DP Road
- West
- open plot S No 100 hissa no 7
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking92 units
82 of 92 units booked (89%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 39.23 sq m · 422 sq ft | 18 | 18 |
| 1BHK | 39.65 sq m · 427 sq ft | 18 | 18 |
| 1BHK | 39.67 sq m · 427 sq ft | 18 | 16 |
| 2BHK | 56.86 sq m · 612 sq ft | 16 | 9 |
| 2BHK | 57.8 sq m · 622 sq ft | 1 | 1 |
| 2BHK | 59.45 sq m · 640 sq ft | 16 | 15 |
| 2BHK | 60.7 sq m · 653 sq ft | 1 | 1 |
| Office space | 142.41 sq m · 1,533 sq ft | 1 | 1 |
Show all 11 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Shop | 10.12 sq m · 109 sq ft | 1 | 1 |
| Shop | 13.75 sq m · 148 sq ft | 1 | 1 |
| Shop | 15.6 sq m · 168 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Sthapatya Nirmaan | — |
| Chartered accountant | Kapure and Kapure Chartered accountants | — |
| Engineer | S V Patel and associates | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Dombivli
- Mali ShivalayaRERA PM1330002602683
- Shiv SadanRERA PR1330002602567
- Bhargav Co-Op Housing Society LimitedRERA PM1330002602519
- The MeadowsRERA PR1330002601825
- Om Ganesh PujaRERA PR1330002601796
- Payal Business ParkRERA PC1330002600694
- VedvikaRERA PR1330002600676
- YashrajRERA PM1330002600521
All 445 projects in Dombivli · Compare Balaji Vishant with another project