Amber One
Deedo IDDP-THN-K6GBCompletion was pushed back 4 months, to Oct 2028; no MahaRERA orders on record; 30% of its units are booked.
Dombivli, Thane 421201 · by Amber Buildcon
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Oct 2028
- This projectRegistered 26 Nov 2020, completion promised 30 Jun 2028, revised to 30 Oct 2028.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700027251
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700027251 | 26 Nov 2020 | 30 Jun 2028 | 30 Oct 2028 | Amber Buildcon | Project page |
Documents165
1 document held by Deedo, 164 filings listed on MahaRERA's project page
Finance
Legal
Show all 165 documentsShow fewer documents
Migrated
- 1 Details of encumbrancesEncumbrances Letter.pdf · uploaded 21 Nov 2020Source
- 1 Copy of Layout Approval (in case of layout)LAYOUT PLAN-min.pdf · uploaded 21 Nov 2020Source
- 1 Building Plan Approval / NA Order for plotted developmentBASEMENT GROUND AND FIRST.pdf · uploaded 21 Nov 2020Source
- 2 Building Plan Approval / NA Order for plotted development2ND AND 3RD.pdf · uploaded 21 Nov 2020Source
- 3 Building Plan Approval / NA Order for plotted development4TH TO 28TH.pdf · uploaded 21 Nov 2020Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 21 Nov 2020Source
- 1 Declaration in FORM BFORM B -AMBER BUILDCON-.pdf · uploaded 21 Nov 2020Source
- 1 Proforma of Allotment letterDEAFT AGREEMENT And ALLOTMENT LETTER.pdf · uploaded 21 Nov 2020Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)RCC CERTIFICATE.pdf · uploaded 23 Nov 2020Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 Chartered Accountants.pdf · uploaded 24 Nov 2020Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICAT FORM 2 MARCH-21.pdf · uploaded 19 May 2021Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CARTERED ACCOUNTANT CERTIFICAT-FORM 3 MARCH-21.pdf · uploaded 19 May 2021Source
- 1 Disclosure of sold/ booked inventorySOLD INVENTORY.pdf · uploaded 20 May 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Form-1.pdf · uploaded 28 May 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)QUALITY CERTIFICATE 2020-2021.pdf · uploaded 3 Jun 2021Source
- 1 Declaration about Commencement CertificatePROMOTER - DECLARATION ABOUT COMMENCEMNT CERTIFICATE.pdf · uploaded 16 Sep 2021Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE FORM 1 June-21.pdf · uploaded 16 Sep 2021Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE FORM 2 June-21.pdf · uploaded 16 Sep 2021Source
- 2 Disclosure of sold/ booked inventorySOLD AND UNSOLD INVENTORY June-21.pdf · uploaded 16 Sep 2021Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A CERTIFICATE FORM 3 June-21.pdf · uploaded 16 Sep 2021Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)QUALITY CERTIFICATE JUNE 2021.pdf · uploaded 18 Sep 2021Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE Fome-3 Sept-21.pdf · uploaded 7 Oct 2021Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE-FORM 1 Sept-21.pdf · uploaded 8 Oct 2021Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE-FORM 2 Sep-21.pdf · uploaded 8 Oct 2021Source
- 3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)QUALITY CERTIFICATE Sept-21.pdf · uploaded 8 Oct 2021Source
- 3 Disclosure of sold/ booked inventoryPROMOTER SOLD UNSOLD AMBER ONE Sept-21.pdf · uploaded 8 Oct 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 Rera CA Certificat 2020-21.pdf · uploaded 16 Oct 2021Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 ARCHITECT CERTIFICATE For Dec-21.pdf · uploaded 20 Jan 2022Source
- 4 Disclosure of sold/ booked inventoryPROMOTER SOLD UNSOLD AMBER ONE Dec-21.pdf · uploaded 20 Jan 2022Source
- 1 CERSAI detailsCERSAI_Search_Report Dec-21.pdf · uploaded 20 Jan 2022Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 Chartered Certificat for Dec-21.pdf · uploaded 20 Jan 2022Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Fome -2 Engineer Certificate Dec-21.pdf · uploaded 27 Jan 2022Source
- 4 Building Plan Approval / NA Order for plotted developmentRewise PLAN 25-02-2022.PDF · uploaded 23 Apr 2022Source
- 2 Commencement Certificates / NA Order for plotted developmentRewise Commence Certificat 25-02-2022.pdf · uploaded 23 Apr 2022Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER rewise form-2 Certificate.pdf · uploaded 23 Apr 2022Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA rewise form-3 CERTIFICATE.pdf · uploaded 23 Apr 2022Source
- 2 Proforma of Allotment letterRera Flat Sale-Amber One-DRAFT.pdf · uploaded 23 Apr 2022Source
- 2 Declaration about Commencement CertificatePROMOTER - DECLARATION ABOUT COMMENCEMNT CERTIFICATE.pdf · uploaded 4 May 2022Source
- 1 OtherRESOLUTION CONSENT FOR CORRECTION US 14(2).pdf · uploaded 4 May 2022Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE FORM 1.pdf · uploaded 5 May 2022Source
- 5 Disclosure of sold/ booked inventorySOLD UNSOLD INVENTORY - PROMOTER.pdf · uploaded 5 May 2022Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Form 1.pdf · uploaded 23 Jul 2022Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Form 2.pdf · uploaded 23 Jul 2022Source
- 6 Disclosure of sold/ booked inventoryPromoter sold unsold inventory.pdf · uploaded 23 Jul 2022Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Form 3.pdf · uploaded 23 Jul 2022Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Form 1.pdf · uploaded 4 Oct 2022Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Form 2.pdf · uploaded 4 Oct 2022Source
- 7 Disclosure of sold/ booked inventoryPromoter sold unsold inventory.pdf · uploaded 4 Oct 2022Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Form 3.pdf · uploaded 18 Oct 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form-5 Amber Buidcon 2021-22.pdf · uploaded 18 Oct 2022Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)A-ONE Engineer Certificate Form 2.pdf · uploaded 18 Jan 2023Source
- 8 Disclosure of sold/ booked inventoryPromoter sold unsold inventory-31-12-22.pdf · uploaded 18 Jan 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameA ONE - DECLARATION ABOUT SEPARATE BANK ACCOUNT.pdf · uploaded 18 Jan 2023Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Form 1.pdf · uploaded 24 Jan 2023Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Form 3.pdf · uploaded 24 Jan 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Engineer Quality Assurance Certificate Fome 2A F A 2021-22.pdf · uploaded 31 Jan 2023Source
- 1 Proforma of Agreement for salePerfoma Of Agreement for Sale-Amber One.pdf · uploaded 31 Jan 2023Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer cost Incurred Cetificat Form-2 31-03-23.pdf · uploaded 14 Apr 2023Source
- 9 Disclosure of sold/ booked inventoryPromoter sold unsold inventory-31-03-2023.pdf · uploaded 14 Apr 2023Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect work Complition Certificate Form -1.pdf · uploaded 21 Apr 2023Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Form 3.pdf · uploaded 21 Apr 2023Source
- 1 Other – FinanceDevelopment Right Morge Deed Index2file.pdf · uploaded 29 May 2023Source
- 2 Details of encumbrancesDetails of Encumbrance concerned to finance.pdf · uploaded 2 Jun 2023Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)ONE ARCHITECT CERTIFICATE FORM 1.pdf · uploaded 8 Jul 2023Source
- 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)ONE ENGINEER CERTIFICATE FORM 2.pdf · uploaded 8 Jul 2023Source
- 10 Disclosure of sold/ booked inventoryPROMOTER SOLD UNSOLD INVENTORY.pdf · uploaded 8 Jul 2023Source
- 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)ONE CA CERTIFICATE FORM 3.pdf · uploaded 8 Jul 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Engineer QUALITY CERTIFICATE 2022-23.pdf · uploaded 11 Jul 2023Source
- 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE FORM 1 30-09-2023.pdf · uploaded 17 Oct 2023Source
- 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE FORM 2 30-09-2023.pdf · uploaded 17 Oct 2023Source
- 11 Disclosure of sold/ booked inventoryPROMOTER SOLD UNSOLD INVENTORY.pdf · uploaded 17 Oct 2023Source
- 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE FORM 3 Sept-23.pdf · uploaded 17 Oct 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)CA REPORT FORM 5 2022-23.pdf · uploaded 17 Oct 2023Source
- 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE FORM 1 DEC 23.pdf · uploaded 16 Jan 2024Source
- 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE FORM 2 DEC 23.pdf · uploaded 16 Jan 2024Source
- 12 Disclosure of sold/ booked inventoryPROMOTER SOLD UNSOLD INVENTORY DEC 23.pdf · uploaded 16 Jan 2024Source
- 13 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE FORM-3 DEC 23.pdf · uploaded 16 Jan 2024Source
- 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE FORM 1 MARCH 24.pdf · uploaded 13 Apr 2024Source
- 14 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE FORM 2 MARCH 24.pdf · uploaded 13 Apr 2024Source
- 13 Disclosure of sold/ booked inventoryPROMOTER SOLD UNSOLD MARCH 24 - MARCH 24.pdf · uploaded 13 Apr 2024Source
- 14 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE FORM-3 MARCH 24.pdf · uploaded 16 Apr 2024Source
- 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE FORM 1 JUNE 24.pdf · uploaded 15 Jul 2024Source
- 4 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)ENGINEER CERTIFICATE FORM 2 JUNE 24.pdf · uploaded 15 Jul 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A - QUALITY CERTIFICAATE.pdf · uploaded 15 Jul 2024Source
- 14 Disclosure of sold/ booked inventoryPROMOTER SOLD UNSOLD JUNE 24.pdf · uploaded 15 Jul 2024Source
- 15 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE FORM-3 JUNE 24.pdf · uploaded 15 Jul 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE FORM 1 SEPT 24.pdf · uploaded 26 Oct 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE FORM-3 SEPT 24.pdf · uploaded 26 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE FORM 2 SEPT 24.pdf · uploaded 26 Oct 2024Source
- 2 Disclosure of sold/ booked inventoryBUILDCON PROMOTER SOLD UNSOLD.pdf · uploaded 26 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)CA FORM 5 SEPT 24.pdf · uploaded 26 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE FORM 1 DEC 24.pdf · uploaded 23 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE FORM 3 DEC 2024.pdf · uploaded 23 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE FORM 2 DEC 24.pdf · uploaded 23 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryPROMOTER SOLD UNSOLD - ONE.pdf · uploaded 23 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE FORM 1 MARCH 2025.pdf · uploaded 14 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE FORM 3 MARCH 2025.pdf · uploaded 14 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE Form 2 MARCH 2025.pdf · uploaded 14 Apr 2025Source
- 1 Disclosure of sold/ booked inventoryPROMOTER SOLD UNSOLD - ELITE.pdf · uploaded 14 Apr 2025Source
- Form 1ARCHITECT CERTIFICATE FORM 1 MARCH 25.pdf · uploaded 21 Jul 2025Source
- Form 2ENGINEER CERTIFICATE FORM 2 MARCH 25.pdf · uploaded 21 Jul 2025Source
- Form 3CA CERTIFICATE FORM 3 MARCH 25.pdf · uploaded 21 Jul 2025Source
- Disclosure of Sold and Booked InventoryPROMOTER SOLD UNSOLD - ONE.pdf · uploaded 21 Jul 2025Source
- Withdrawal Update Form 1ARCHITECT CERTIFICATE FORM 1 SEPTEMBER 2025.pdf · uploaded 1 Nov 2025Source
- Withdrawal Update Form 1ARCHITECT CERTIFICATE FORM 1 SEPTEMBER 2025.pdf · uploaded 1 Nov 2025Source
- Withdrawal Update Form 2ENGINEER CERTIFICATE FORM 2 MARCH 24.pdf · uploaded 1 Nov 2025Source
- Withdrawal Update Form 2ENGINEER CERTIFICATE FORM 2 MARCH 24.pdf · uploaded 1 Nov 2025Source
- Withdrawal Update Form 3CA CERTIFICATE FORM 3 SEPTEMBER 2025.pdf · uploaded 1 Nov 2025Source
- Withdrawal Update Form 3CA CERTIFICATE FORM 3 SEPTEMBER 2025.pdf · uploaded 1 Nov 2025Source
- Form 2A (FY 2020-2021)QUALITY CERTIFICATE 2020-2021.pdf · uploaded 1 Nov 2025Source
- Form 2A (FY 2021-2022)QUALITY CERTIFICATE JUNE 2021.pdf · uploaded 1 Nov 2025Source
- Form 2A (FY 2022-2023)Quality Certificate.pdf · uploaded 1 Nov 2025Source
- Form 2A (FY 2023-2024)FORM 2A - QUALITY CERTIFICAATE.pdf · uploaded 1 Nov 2025Source
- Form 2A (FY 2024-2025)FORM 2A - QUALITY CERTIFICATE MARCH 25.pdf · uploaded 1 Nov 2025Source
- Form 5 (FY 2022-2023)CA REPORT FORM 5 2022-23.pdf · uploaded 1 Nov 2025Source
- Form 5 (FY 2023-2024)CA FORM 5 SEPT 24.pdf · uploaded 1 Nov 2025Source
- Form 5 (FY 2024-2025)FORM 5 - A ONE.pdf · uploaded 1 Nov 2025Source
- Form 1ARCHITECT CERTIFICATE FORM 1 SEPTEMBER 2025.pdf · uploaded 7 Nov 2025Source
- Form 2ENGINEER CERTIFICATE FORM 2 SEPTEMBER 2025.pdf · uploaded 7 Nov 2025Source
- Form 3CA CERTIFICATE FORM 3 SEPTEMBER 2025.pdf · uploaded 7 Nov 2025Source
- Disclosure of Sold and Booked InventoryONE - PROMOTER SOLD UNSOLD.pdf · uploaded 7 Nov 2025Source
- Form 1ARCHITECT CERTIFICATE FORM 1.pdf · uploaded 17 Jan 2026Source
- Form 2ENGINEER CERTIFICATE FORM 2_compressed.pdf · uploaded 17 Jan 2026Source
- Form 3CA CERTIFICATE FORM 3.pdf · uploaded 17 Jan 2026Source
- Disclosure of Sold and Booked InventoryPROMOTER Dicloser Sold UNsold FLAT.pdf · uploaded 17 Jan 2026Source
- Form 1ARCHITECT CERTIFICATE FORM 1.pdf · uploaded 18 Apr 2026Source
- Form 2ENGINEER CERTIFICATE FORM 2.pdf · uploaded 18 Apr 2026Source
- Form 3CA CERTIFICATE FORM 3.pdf · uploaded 18 Apr 2026Source
- Disclosure of Sold and Booked InventoryPROMOTER CERTIFICAT SOLD UNSOLD.pdf · uploaded 18 Apr 2026Source
- Withdrawal Update Form 1ARCHITECT CERTIFICATE FORM 1.pdf · uploaded 24 Apr 2026Source
- Withdrawal Update Form 2ENGINEER CERTIFICATE FORM 2.pdf · uploaded 24 Apr 2026Source
- Withdrawal Update Form 3CA CERTIFICATE FORM 3.pdf · uploaded 24 Apr 2026Source
- Withdrawal Update Form 1ARCHITECT CERTIFICATE FORM 1 June-26.pdf · uploaded 13 Jul 2026Source
- Withdrawal Update Form 2ENGINEER CERTIFICATE FORM 2 June-26.pdf · uploaded 13 Jul 2026Source
- Withdrawal Update Form 3CA CERTIFICATE FORM 3.pdf · uploaded 13 Jul 2026Source
- Withdrawal Update Form 1ARCHITECT CERTIFICATE FORM 1 SEPT 2026.pdf · uploaded 12 Oct 2026Source
- Withdrawal Update Form 1ARCHITECT CERTIFICATE FORM 1 SEPT 2026.pdf · uploaded 12 Oct 2026Source
- Withdrawal Update Form 1ARCHITECT CERTIFICATE FORM 1 SEPT 2026.pdf · uploaded 12 Oct 2026Source
- Withdrawal Update Form 2ENGINEER CERTIFICATE FORM 2 SEPT 2026.pdf · uploaded 12 Oct 2026Source
- Withdrawal Update Form 2ENGINEER CERTIFICATE FORM 2 SEPT 2026.pdf · uploaded 12 Oct 2026Source
- Withdrawal Update Form 2ENGINEER CERTIFICATE FORM 2 SEPT 2026.pdf · uploaded 12 Oct 2026Source
- Withdrawal Update Form 3CA CERTIFICATE FORM 3.pdf · uploaded 12 Oct 2026Source
- Withdrawal Update Form 3CA CERTIFICATE FORM 3.pdf · uploaded 12 Oct 2026Source
- Withdrawal Update Form 3CA CERTIFICATE FORM 3.pdf · uploaded 12 Oct 2026Source
Technical
Technical (Architect)
- DocumentARCHITECT CERTIFICATE FORM 1 SEPT 24.pdf · uploaded 26 Oct 2024Source
- DocumentARCHITECT CERTIFICATE FORM 1 DEC 24.pdf · uploaded 23 Jan 2025Source
- DocumentARCHITECT CERTIFICATE FORM 1 MARCH 2025.pdf · uploaded 14 Apr 2025Source
- DocumentARCHITECT CERTIFICATE FORM 1 SEPT 2026.pdf · uploaded 12 Oct 2026Source
Technical (Engineer)
- DocumentENGINEER CERTIFICATE FORM 2 SEPT 24.pdf · uploaded 26 Oct 2024Source
- DocumentENGINEER CERTIFICATE FORM 2 DEC 24.pdf · uploaded 23 Jan 2025Source
- DocumentENGINEER CERTIFICATE Form 2 MARCH 2025.pdf · uploaded 14 Apr 2025Source
- DocumentENGINEER CERTIFICATE FORM 2 SEPT 2026.pdf · uploaded 12 Oct 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel Old S No 74 New S No 102 Hissa no 1C 2A 2B 2C
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, Office space, Shop380 units in all
- Address
- Old S No 74 New S No 102 Hissa no 1C 2A 2B 2C, Thakurli Kalyan Road, kanchangoanPIN 421201
- Village
- Kalyan-Dombivali (M Corp.), Kalyan taluka
- Location
- 19.22684, 73.10234
- Land area for this project
- 3,629 sq m (39,057 sq ft)
- Permissible built-up area
- 22,900 sq m (2,46,488 sq ft)
- Sanctioned built-up area
- 22,900 sq m (2,46,488 sq ft)
- Recreational open space
- 237 sq m (2,555 sq ft)
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Old S No 74 New S No 102 Hissa no 1C 2A 2B 2C
Boundaries
- North
- 24 Meter Road
- South
- K D M C Reseve Garden plot
- East
- 18 Meter Road
- West
- Mahalaxmi Ashish Building
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking380 units
113 of 380 units booked (30%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 39.4 sq m · 424 sq ft | 1 | 0 |
| 1BHK | 39.78 sq m · 428 sq ft | 35 | 7 |
| 1BHK | 40.11 sq m · 432 sq ft | 34 | 5 |
| 1BHK | 40.43 sq m · 435 sq ft | 34 | 11 |
| 1BHK | 40.65 sq m · 438 sq ft | 1 | 1 |
| 1BHK | 40.66 sq m · 438 sq ft | 33 | 5 |
| 2BHK | 54.4 sq m · 586 sq ft | 2 | 0 |
| 2BHK | 54.85 sq m · 590 sq ft | 34 | 5 |
Show all 33 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 54.87 sq m · 591 sq ft | 34 | 3 |
| 2BHK | 56.14 sq m · 604 sq ft | 34 | 13 |
| 2BHK | 56.65 sq m · 610 sq ft | 25 | 7 |
| 2BHK | 57.52 sq m · 619 sq ft | 17 | 10 |
| 2BHK | 58.96 sq m · 635 sq ft | 17 | 5 |
| Office space | 14.3 sq m · 154 sq ft | 2 | 1 |
| Office space | 14.64 sq m · 158 sq ft | 3 | 1 |
| Office space | 15.78 sq m · 170 sq ft | 1 | 1 |
| Office space | 16.86 sq m · 181 sq ft | 2 | 0 |
| Office space | 20.83 sq m · 224 sq ft | 2 | 1 |
| Office space | 21.33 sq m · 230 sq ft | 32 | 22 |
| Office space | 22.26 sq m · 240 sq ft | 4 | 2 |
| Office space | 28.44 sq m · 306 sq ft | 2 | 0 |
| Office space | 29.37 sq m · 316 sq ft | 2 | 0 |
| Office space | 30.96 sq m · 333 sq ft | 2 | 2 |
| Office space | 32.15 sq m · 346 sq ft | 2 | 0 |
| Office space | 33.26 sq m · 358 sq ft | 2 | 0 |
| Shop | 18.89 sq m · 203 sq ft | 1 | 0 |
| Shop | 19.34 sq m · 208 sq ft | 1 | 0 |
| Shop | 27.7 sq m · 298 sq ft | 1 | 0 |
| Shop | 28.45 sq m · 306 sq ft | 16 | 10 |
| Shop | 34.19 sq m · 368 sq ft | 1 | 0 |
| Shop | 34.26 sq m · 369 sq ft | 1 | 0 |
| Shop | 39.23 sq m · 422 sq ft | 1 | 1 |
| Shop | 39.46 sq m · 425 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals6
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Shirish G Nachane | — |
| Chartered accountant | Dinesh Kanji Patel | — |
| Chartered accountant | Nilesh S Patil | — |
| Chartered accountant | Urvi Devansh Rangani | — |
| Engineer | Dinanath Balmkund Jha | — |
| Engineer | Techline Consulting Engineer | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Dombivli
- Mali ShivalayaRERA PM1330002602683
- Shiv SadanRERA PR1330002602567
- Bhargav Co-Op Housing Society LimitedRERA PM1330002602519
- The MeadowsRERA PR1330002601825
- Om Ganesh PujaRERA PR1330002601796
- Payal Business ParkRERA PC1330002600694
- VedvikaRERA PR1330002600676
- YashrajRERA PM1330002600521
All 445 projects in Dombivli · Compare Amber One with another project