Deedo IDDP-THN-WNPDCompletion was pushed back 4 months, to Jul 2027; no MahaRERA orders on record; 9% of its units are booked.
Cherpoli, Thane 421601 · by J D Housing LLP
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Jul 2027
- This projectRegistered 2 Mar 2026, completion promised 31 Mar 2027, revised to 31 Jul 2027.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationPM1330002502557
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| PM1330002502557 | 2 Mar 2026 | 31 Mar 2027 | 31 Jul 2027 | J D Housing LLP | Project page |
Documents31
1 document held by Deedo, 30 filings listed on MahaRERA's project page
Finance
- PAN Cardpan card.pdf · uploaded 21 Nov 2025Source
Legal
Show all 31 documentsShow fewer documents
Migrated
- Withdrawal Update Form 3FORM - 3 - 31-03-2026.pdf · uploaded 2 May 2026Source
- Withdrawal Update Form 1FORM - 1 - 31-03-2026.pdf · uploaded 18 May 2026Source
- Withdrawal Update Form 2FORM - 2 - 31-03-2026.pdf · uploaded 18 May 2026Source
- Withdrawal Update Form 3FORM - 3 - 31-03-2026.pdf · uploaded 18 May 2026Source
- Withdrawal Update Form 1FORM - 1 - 31-03-2026.pdf · uploaded 11 Jun 2026Source
- Withdrawal Update Form 2FORM - 2 - 31-03-2026.pdf · uploaded 11 Jun 2026Source
- Withdrawal Update Form 3FORM - 3 - 31-03-2026.pdf · uploaded 11 Jun 2026Source
- Withdrawal Update Form 1FORM 1 - 30-06-2026.pdf · uploaded 12 Aug 2026Source
- Withdrawal Update Form 2FORM 2 - 30-06-2026.pdf · uploaded 12 Aug 2026Source
- Withdrawal Update Form 3FORM 3 - 30-06-2026.pdf · uploaded 12 Aug 2026Source
Technical
- Document1_compressed.pdf · uploaded 17 Oct 2025Source
- Document2_compressed.pdf · uploaded 17 Oct 2025Source
- Document3_compressed.pdf · uploaded 17 Oct 2025Source
- Document4_compressed.pdf · uploaded 17 Oct 2025Source
- DocumentOrder 50 Undertaking.pdf · uploaded 17 Oct 2025Source
- DocumentNA Order 10-10-24 PLot No-5.pdf · uploaded 2 Dec 2025Source
- OthersForm 1 Architech Certifiate.pdf · uploaded 22 Dec 2025Source
- OthersFORM 2 ENGINEER CERTIFICATE.pdf · uploaded 22 Dec 2025Source
- DocumentVERIFICATION OF CC.pdf · uploaded 26 Dec 2025Source
- OthersCC AND VERIFICATION OF CC.pdf · uploaded 26 Dec 2025Source
- OthersADTP Recommendation letter.pdf · uploaded 15 Jan 2026Source
Technical (Architect)
- DocumentFORM 1 - 30-06-2026.pdf · uploaded 12 Aug 2026Source
Technical (Engineer)
- DocumentFORM 2 - 30-06-2026.pdf · uploaded 10 Aug 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel Plot no-5 Survey No-138AB
As registered with MahaRERA and published on its project page
- Project type
- Mixed
- Status on MahaRERA
- Certificate Signed
- Unit types
- —87 units in all
- Address
- Off Nasik Highway NH-3, Near J D PARK SOCIETYPIN 421601
- Village
- Cherpoli, Shahapur taluka
- Location
- 19.46143, 73.33107
- Land area for this project
- 1,584 sq m (17,050 sq ft)
- Permissible built-up area
- 4,708 sq m (50,673 sq ft)
- Sanctioned built-up area
- 4,701 sq m (50,604 sq ft)
- Recreational open space
- 773 sq m (8,316 sq ft)
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Plot no-5 Survey No-138AB
Boundaries
- North
- RG Plot No-II of Survey no 138A
- South
- Amenity Plot No-II of Sub Gat no 138A
- East
- 9mtr Internal Roadof Sub Gat 138A abutting S.no 137 Part
- West
- Survey no 134 Part & 135 Part
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking87 units
87 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 87 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Vijay Dattatray Bahulekar | — |
| Chartered accountant | Kishor P Pabari | — |
| Engineer | Kirtikumar Himatlal Shah | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Cherpoli
- Sai Anand ApartmentRERA PR1330002601798
- Skyline PrimeRERA PR1330002600362
- Om Imperial Tower - 4RERA PR1330002600179
- Shilpa ApartmentRERA PR1330002502194
- Chintamani HeightzRERA PR1330002501955
- Om Sai Imperial Tower 3RERA PR1330002501669
- Atlas Sky ViewRERA P51700081005
- Niharika HeightsRERA P51700079641
All 16 projects in Cherpoli · Compare J D Palms with another project