Skip to content

Skyline Prime

Certificate Signed

Cherpoli, Thane 421601 |Promoter: Tilak Construction Co , Sunil Govindlal Kabra

7 May 2026Registered with MahaRERA
31 Dec 2030Promised completion
30 Apr 2031Revised completionPushed back 4 months
1Building
74Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
—74 units in all
Address
Cherpoli, ShahapurPIN 421601
Designated bank account
66
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.45977, 73.33334
Skyline Prime is at latitude 19.45977, longitude 73.33334.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
7 May 2026
Promised
31 Dec 2030
Revised
30 Apr 2031

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PR13300026003627 May 202631 Dec 203030 Apr 2031Tilak Construction Co , Sunil Govindlal KabraProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsFloors with CCUnits
Skyline Prime91074

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

74 units registered

— · 74 units
TypeCarpet areaUnits
——74

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 31 filings listed on MahaRERA's project page

Registration certificate

Finance

  • GSTIN DocumentGST Certificate.pdf · uploaded 17 Feb 2026Source
  • OthersDecoration regarding Financial Viability of the project.pdf · uploaded 18 Feb 2026Source
  • PAN CardPancard Tilak Construction and Sunil Kabra.pdf · uploaded 24 Apr 2026Source
  • OthersJoint Declaration skyline Prime.pdf · uploaded 4 May 2026Source

Legal

  • OthersPartnership Deed - Retirement Deed.pdf · uploaded 17 Feb 2026Source
  • Declaration Form BForm B Skyline -Promoter.pdf · uploaded 17 Feb 2026Source
  • Declaration Form BSale Deed - 1583-2026 _ Sunil kabra_.pdf · uploaded 17 Feb 2026Source
Show all 32 documentsShow fewer documents

Legal

  • OthersMOU -Skyline Prime_.pdf · uploaded 18 Feb 2026Source
  • OthersAnnexure_A -Disclosure of Intrest - and Partners.pdf · uploaded 20 Feb 2026Source
  • Declaration Form BLegal Title _Certificate_Skyline Prime_18022026.pdf · uploaded 18 Apr 2026Source
  • Declaration Form BForm B_Tilak Constructions and Sunil Kabra _Notarized.pdf · uploaded 22 Apr 2026Source
  • OthersJoint Declaration skyline -Tilak Const and Sunil Kabra.pdf · uploaded 25 Apr 2026Source

Migrated

  • Withdrawal Update Form 1Form 1 - Skyline Prime as on June 2026.pdf · uploaded 20 Aug 2026Source
  • Withdrawal Update Form 2Form 2 - Skyline Prime as on June 2026.pdf · uploaded 20 Aug 2026Source
  • Withdrawal Update Form 3Form 3 - Skyline Prime as on June 2026.pdf · uploaded 20 Aug 2026Source
  • Withdrawal Update Form 1Form 1 - Skyline Prime as on June 2026.pdf · uploaded 4 Sep 2026Source
  • Withdrawal Update Form 2Form 2 - Skyline Prime as on June 2026.pdf · uploaded 4 Sep 2026Source
  • Withdrawal Update Form 3Form 3 - Skyline Prime as on June 2026.pdf · uploaded 4 Sep 2026Source

Technical

  • DocumentApproval Plan Page -2.pdf · uploaded 17 Feb 2026Source
  • DocumentApproval Plan Page -3.pdf · uploaded 17 Feb 2026Source
  • DocumentApproval Plan Page - 4.pdf · uploaded 17 Feb 2026Source
  • DocumentApproval Plan Page -5.pdf · uploaded 17 Feb 2026Source
  • DocumentApproval Plan Page -6.pdf · uploaded 17 Feb 2026Source
  • DocumentApproval Plan Page 7.pdf · uploaded 17 Feb 2026Source
  • DocumentApproval Plan Page -8.pdf · uploaded 17 Feb 2026Source
  • DocumentApproval Plan Page 9.pdf · uploaded 17 Feb 2026Source
  • DocumentLayout Plan Page 1.pdf · uploaded 18 Feb 2026Source
  • OthersCC Verification Mail -Skyline Prime.pdf · uploaded 18 Feb 2026Source
  • DocumentAnnexure A - order No_ 50.pdf · uploaded 20 Feb 2026Source

Technical (Architect)

  • DocumentForm 1 - Skyline Prime as on June 2026.pdf · uploaded 20 Aug 2026Source

Technical (Engineer)

  • DocumentForm 2 - Skyline Prime as on June 2026.pdf · uploaded 20 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Cherpoli, Shahapur taluka

Survey, CTS, gat or plot numbers

Gut No 410Gut No -72/A

Boundaries

North
Property of Gut No 72
South
Property of Gut No 78
East
Property of Gut No 78
West
Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
EngineerAjay Mahale—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology