Precious Avenue
Deedo IDDP-THN-EM68Completion was pushed back 1 year to Dec 2025, and that date has passed too; no MahaRERA orders on record; 74% of its units are booked.
Belavli, Thane 421503 · by Metro Shivshakti Developers
Buying a flat here?
See every deed registered on it.
Completion was pushed back 1 year to Dec 2025, and that date has passed too
- This projectRegistered 24 Feb 2020, completion promised 30 Dec 2024, revised to 30 Dec 2025, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700024621
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700024621 | 24 Feb 2020 | 30 Dec 2024 | 30 Dec 2025 | Metro Shivshakti Developers | Project page |
Documents55
2 documents held by Deedo, 53 filings listed on MahaRERA's project page
Finance
- PAN CardPAN.pdf · uploaded 14 Feb 2020Source
Legal
- Declaration Form Baffidavit-metro shiv shakti compressed.pdf · uploaded 14 Feb 2020Source
- Legal Title reportTitle1compressed.pdf · uploaded 14 Feb 2020Source
- Legal Title reportTitle Report compressed 2.pdf · uploaded 14 Feb 2020Source
- Declaration Form BMSD Form B Affidavit notry.pdf · uploaded 3 Oct 2023Source
Migrated
- 1 PAN CardPAN.pdf · uploaded 14 Feb 2020Source
Show all 55 documentsShow fewer documents
Migrated
- 1 Copy of the legal title reportTitle1compressed.pdf · uploaded 14 Feb 2020Source
- 2 Copy of the legal title reportTitle Report compressed 2.pdf · uploaded 14 Feb 2020Source
- 1 Details of encumbrances03_No Encumbrances.pdf · uploaded 14 Feb 2020Source
- 1 Copy of Layout Approval (in case of layout)Senction Block Plan compressed.pdf · uploaded 14 Feb 2020Source
- 1 Building Plan Approval / NA Order for plotted developmentSenction Floor Plan compressed.pdf · uploaded 14 Feb 2020Source
- 1 Commencement Certificates / NA Order for plotted developmentC C Copy compressed.pdf · uploaded 14 Feb 2020Source
- 1 Declaration in FORM Baffidavit-metro shiv shakti compressed.pdf · uploaded 14 Feb 2020Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Scan Architect Certificate compressed.pdf · uploaded 14 Feb 2020Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)5 Engineers cert.pdf · uploaded 14 Feb 2020Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)metro shivshakti form 3.pdf · uploaded 14 Feb 2020Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)metro shivshakti form 3.pdf · uploaded 14 Feb 2020Source
- 1 Proforma of Allotment letterAllotment letter.pdf · uploaded 14 Feb 2020Source
- 2 Proforma of Allotment letterAgreement for Sale Draft.pdf · uploaded 14 Feb 2020Source
- 1 Declaration about Commencement CertificateForm D.pdf · uploaded 23 Jun 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)MSD QUALITY CERT 19-20.pdf · uploaded 23 Jun 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)MSD QUALITY CERT 20-21.pdf · uploaded 23 Jun 2022Source
- 1 CERSAI detailsCERSAI_Search_Report_200240513319_For_Asset_Based_Search_23_06_202.pdf · uploaded 23 Jun 2022Source
- 1 Disclosure of sold/ booked inventoryDisclosure of Sold and Unsold Units.pdf · uploaded 23 Jun 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)MSD Form 5 19-20.pdf · uploaded 23 Jun 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)MSD Form 5 20-21.pdf · uploaded 23 Jun 2022Source
- 2 Copy of Layout Approval (in case of layout)Revised Plan.pdf · uploaded 9 Jul 2022Source
- 2 Commencement Certificates / NA Order for plotted developmentRevised Commencement Certificate.pdf · uploaded 9 Jul 2022Source
- 2 Building Plan Approval / NA Order for plotted developmentRevised Plan.pdf · uploaded 2 Aug 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)MSD Form 5.pdf · uploaded 23 Jan 2023Source
- 1 Proforma of Agreement for saleDraft AFS.pdf · uploaded 1 Feb 2023Source
- 3 Proforma of Allotment letterDraft Allotment Letter.pdf · uploaded 1 Feb 2023Source
- 2 Declaration in FORM BMSD Form B Affidavit notry.pdf · uploaded 3 Oct 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)MSD Form 01_Arch Certificate.pdf · uploaded 3 Oct 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)MSD Form 02_Engg Certificate.pdf · uploaded 3 Oct 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 30-9-23 Arch.pdf · uploaded 20 Oct 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)MMBD FORM 5.pdf · uploaded 18 Dec 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)MSD Form 01_Q4.pdf · uploaded 20 Apr 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)MSD Form 02_Q4.pdf · uploaded 20 Apr 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Metro Shiv Shakti 31-03-24.pdf · uploaded 10 May 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)MSD Form 01 Q1_2024-25.pdf · uploaded 20 Jul 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)MSD Form 02 Q1_2024-25.pdf · uploaded 20 Jul 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)MSD Arc F1 30092024.pdf · uploaded 19 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)MSD Eng F-2 30092024.pdf · uploaded 19 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)signedForm 5 Metro Shivshakti Developers.pdf · uploaded 2 Dec 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)MSD F-1 31 DEC.pdf · uploaded 20 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)MSD F-02 31 DEC.pdf · uploaded 20 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Signed Form 3_11zon.pdf · uploaded 13 Mar 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)MSD Form 01_ Q4.pdf · uploaded 19 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)MSD Form 002_ Q4.pdf · uploaded 19 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final form 3_11zon.pdf · uploaded 23 Apr 2025Source
- Form 5 (FY 2024-2025)Signed Metro Shivsakhti Developers form 5 scanned.pdf · uploaded 29 Sep 2025Source
- Form 5 (FY 2025-2026)1 Final Metro 4621 - Copy.pdf · uploaded 27 Sep 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 92/2B, 92/7
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- —172 units in all
- Address
- Survey No 90/1, 92/2b, 92/7, Ambernath Road, BelavaliPIN 421503
- Village
- Badlapur (M Cl), Ambarnath taluka
- Location
- 19.17994, 73.22398
- Designated bank account
- 76
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Boundaries
- North
- S No 90 Hissa No 6
- South
- S No 92 Hissa No 8
- East
- 18 Meters Dp Road
- West
- S No 90 Hissa 2a
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking172 units
172 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 172 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals2
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Raj Associates Architec and Engineers | — |
| Chartered accountant | Mukesh Gurnani | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Belavli
- Sai Sonali GrandRERA PR1330002602653
- Shree Ambika ResidencyRERA PR1330002602289
- Infinity MeadowsRERA PR1330002601926
- Hari Shrushti Wing A Phase IIRERA PM1330002601855
- Raj CornerstoneRERA PR1330002601601
- R1 And R2 Panvelkar Palash ChsRERA PR1330002600912
- Datar Height D And E WingRERA PM1331012503007
- Amber SolitaireRERA PC1330002502746
All 32 projects in Belavli · Compare Precious Avenue with another project