Tulsi Aananta
Deedo IDDP-THN-DJC9Completion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 12% of its units are booked.
Badlapur, Thane 421503 · by Shree Developers
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2029
- This projectRegistered 24 Jan 2023, completion promised 31 Dec 2028, revised to 30 Apr 2029.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700048896
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700048896 | 24 Jan 2023 | 31 Dec 2028 | 30 Apr 2029 | Shree Developers | Project page |
Documents103
1 document held by Deedo, 102 filings listed on MahaRERA's project page
Finance
- PAN CardPAN-Shree Developers.pdf · uploaded 15 Nov 2022Source
Legal
- Legal Title reportRera Titile PH-8_compressed.pdf · uploaded 15 Nov 2022Source
- Legal Title reportSearch Report_merged_compressed.pdf · uploaded 15 Nov 2022Source
- Declaration Form BForm B-Revised.pdf · uploaded 15 Nov 2022Source
- Other – LegalSHREE RERA LETTER.pdf · uploaded 9 Dec 2022Source
- Legal Title reportTitile Report Tulsi Aananta_compressed.pdf · uploaded 9 Dec 2022Source
Migrated
- 1 PAN CardPAN-Shree Developers.pdf · uploaded 15 Nov 2022Source
Show all 103 documentsShow fewer documents
Migrated
- 1 Copy of the legal title reportRera Titile PH-8_compressed.pdf · uploaded 15 Nov 2022Source
- 2 Copy of the legal title reportSearch Report_merged_compressed.pdf · uploaded 15 Nov 2022Source
- 1 a Details of encumbrances concerned to FinanceEncumbrance Certificate.pdf · uploaded 15 Nov 2022Source
- 1 b Details of encumbrances concerned to LegalEncumbrance Certificate.pdf · uploaded 15 Nov 2022Source
- 1 Copy of Layout Approval (in case of layout)Layout Plan_compressed.pdf · uploaded 15 Nov 2022Source
- 1 Building Plan Approval / NA Order for plotted developmentLayout Plan_compressed.pdf · uploaded 15 Nov 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement certificate.pdf · uploaded 15 Nov 2022Source
- 2 Commencement Certificates / NA Order for plotted developmentRevised CC.pdf · uploaded 15 Nov 2022Source
- 1 Declaration about Commencement CertificateForm D.pdf · uploaded 15 Nov 2022Source
- 1 Declaration in FORM BForm B-Revised.pdf · uploaded 15 Nov 2022Source
- 1 CERSAI detailsCERSAI_Search_Report_200254362123_For_Asset_Based_Search_09_12_2022_11_32_20_779.pdf · uploaded 15 Nov 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3-Rera.pdf · uploaded 15 Nov 2022Source
- 1 Proforma of Agreement for saleRera Sale Agreement.pdf · uploaded 15 Nov 2022Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSHREE RERA BANK AC DECLERATION.pdf · uploaded 15 Nov 2022Source
- 1 Deviation Report with respect to Allotment letterDeviation allotment letter.pdf · uploaded 15 Nov 2022Source
- 1 Deviation Report with respect to model copy of AgreementDevaition Model Sale Agreement.pdf · uploaded 15 Nov 2022Source
- 3 Copy of the legal title reportTitile Report Tulsi Aananta_compressed.pdf · uploaded 9 Dec 2022Source
- 2 a Details of encumbrances concerned to FinanceSHREE RERA CERTIFICATE.pdf · uploaded 9 Dec 2022Source
- 2 b Details of encumbrances concerned to LegalSHREE RERA CERTIFICATE.pdf · uploaded 9 Dec 2022Source
- 1 Proforma of Allotment letterAFS.pdf · uploaded 9 Dec 2022Source
- 1 Other – LegalSHREE RERA LETTER.pdf · uploaded 9 Dec 2022Source
- 2 Building Plan Approval / NA Order for plotted developmentB-wing PLAN COPY.pdf · uploaded 21 Dec 2022Source
- 3 Building Plan Approval / NA Order for plotted developmentA-wing PLAN COPY.pdf · uploaded 21 Dec 2022Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsInterest Letter_compressed (1).pdf · uploaded 17 Jan 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 DATED 31-03-2023.pdf · uploaded 3 Aug 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 Tulsi Aananta 31-03-2023.pdf · uploaded 3 Aug 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A.pdf · uploaded 3 Aug 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3_compressed.pdf · uploaded 4 Aug 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 JUN-2023 (Aananta)_compressed.pdf · uploaded 16 Aug 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 JUN-2023 (Tulsi Aananta).pdf · uploaded 16 Aug 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 30092023 Aananta.pdf · uploaded 1 Nov 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Tulsi Aananta - Form 2.pdf · uploaded 1 Nov 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Form-Tulsi Aananta PH 8_Apr23 To Jun23_compressed.pdf · uploaded 15 Jan 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Form-Tulsi Aanata PH 8_Jul23 To Sep23_Compressed.pdf · uploaded 15 Jan 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 Q1-Aananta.pdf · uploaded 3 Feb 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 Q2-Aananta.pdf · uploaded 3 Feb 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3-Shree Developers-Q3_compressed.pdf · uploaded 3 Feb 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM-5-31MARCH2023 Aananta.pdf · uploaded 3 Feb 2024Source
- 1 Disclosure of sold/ booked inventoryDisclosure of Sold_Unsold Inventory Tulsi Aanantha PH 8_compressed.pdf · uploaded 18 May 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Signed Form 3 Q4 Shree Developers_compressed.pdf · uploaded 18 May 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 Aananta.pdf · uploaded 23 May 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 Aananta.pdf · uploaded 23 May 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 30062024 Aananta.pdf · uploaded 14 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2- 30062024 Aananta.pdf · uploaded 14 Oct 2024Source
- 1 Disclosure of sold/ booked inventoryDisclosure of sold -unsold inventory 30062024 (Aananta).pdf · uploaded 14 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-3 30062024 (Aananta)_compressed.pdf · uploaded 14 Oct 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 30062024 Aananta.pdf · uploaded 14 Oct 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-3 30062024 (Aananta)_compressed.pdf · uploaded 14 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2- 30062024 Aananta.pdf · uploaded 14 Oct 2024Source
- 2 Disclosure of sold/ booked inventoryDisclosure of sold -unsold inventory 30062024 (Aananta).pdf · uploaded 14 Oct 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1.pdf · uploaded 22 Nov 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-3.pdf · uploaded 22 Nov 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2.pdf · uploaded 22 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 - Tulsi Aanantha.pdf · uploaded 9 Dec 2024Source
- 3 Disclosure of sold/ booked inventoryDisclosure of sold and unsold inventory Aananta_11zon.pdf · uploaded 24 Dec 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM-2A Aananta.pdf · uploaded 26 Dec 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 Q3 Aananta.pdf · uploaded 31 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Q3 Aananta.pdf · uploaded 7 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 Q3 Aananta.pdf · uploaded 7 Feb 2025Source
- 1 Disclosure of sold/ booked inventoryDisclosure of sold unsold inventory Q3 Aananta.pdf · uploaded 7 Feb 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 31_03_2025 Tulsi Aananta.pdf · uploaded 2 May 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Aananta 31_03_2025.pdf · uploaded 2 May 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-3 31_03_2025 Aananta_11zon.pdf · uploaded 5 May 2025Source
- 1 Disclosure of sold/ booked inventoryDisclosure of sold unsold inventory 31_03_2025.pdf · uploaded 6 May 2025Source
- Withdrawal Update Form 1FORM-1 Q1 Aananta.pdf · uploaded 16 Jan 2026Source
- Withdrawal Update Form 1Form-1 Tulsi Aananta Q2.pdf · uploaded 16 Jan 2026Source
- Withdrawal Update Form 2FORM 2 Aananta.pdf · uploaded 16 Jan 2026Source
- Withdrawal Update Form 2FORM 2 Aananta.pdf · uploaded 16 Jan 2026Source
- Withdrawal Update Form 3Signed Form 3 Q4 Shree Developers_compressed.pdf · uploaded 16 Jan 2026Source
- Withdrawal Update Form 3Form 3 - Tulasi aananta Q2_compressed.pdf · uploaded 16 Jan 2026Source
- Withdrawal Update Form 1FORM 1 Aananta 31_12_2025.pdf · uploaded 27 Mar 2026Source
- Withdrawal Update Form 2FORM 2 Aananta.pdf · uploaded 27 Mar 2026Source
- Withdrawal Update Form 3Form 3 _SRD_compressed.pdf · uploaded 27 Mar 2026Source
- Withdrawal Update Form 1FORM_1 31-03-2026 Aananta.pdf · uploaded 5 May 2026Source
- Withdrawal Update Form 2FORM-2 31-03-2026 Aananta.pdf · uploaded 5 May 2026Source
- Withdrawal Update Form 3Form 3 Shree Developers Tulsi Anantha Q4_compressed (1).pdf · uploaded 5 May 2026Source
- Withdrawal Update Form 1FORM -Tulsi Aananta .pdf · uploaded 12 Aug 2026Source
- Withdrawal Update Form 2FORM -2 Tulsi Aananta .pdf · uploaded 12 Aug 2026Source
- Withdrawal Update Form 3Form 3_compressed.pdf · uploaded 12 Aug 2026Source
Technical
Technical (Architect)
- DocumentFORM-1 30062024 Aananta.pdf · uploaded 14 Oct 2024Source
- DocumentFORM-1 30062024 Aananta.pdf · uploaded 14 Oct 2024Source
- DocumentFORM-1.pdf · uploaded 22 Nov 2024Source
- DocumentFORM 1 Q3 Aananta.pdf · uploaded 31 Jan 2025Source
- DocumentFORM 1 31_03_2025 Tulsi Aananta.pdf · uploaded 2 May 2025Source
- DocumentFORM -Tulsi Aananta .pdf · uploaded 12 Aug 2026Source
Technical (Engineer)
- DocumentFORM-2- 30062024 Aananta.pdf · uploaded 14 Oct 2024Source
- DocumentFORM-2- 30062024 Aananta.pdf · uploaded 14 Oct 2024Source
- DocumentFORM-2.pdf · uploaded 22 Nov 2024Source
- DocumentFORM 2 Q3 Aananta.pdf · uploaded 7 Feb 2025Source
- DocumentForm 2 Aananta 31_03_2025.pdf · uploaded 2 May 2025Source
- DocumentFORM -2 Tulsi Aananta .pdf · uploaded 12 Aug 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel S No.41 H No2/2, S No.41 H No3 S No41 H No4
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK277 units in all
- Address
- S No.41 H No-2/2, S No.41 H No-3 S No-41 H No-4, Kharvai, BadlapurPIN 421503
- Village
- Badlapur (M Cl), Ambarnath taluka
- Location
- 19.15091, 73.24825
- Land area for this project
- 6,030 sq m (64,906 sq ft)
- Permissible built-up area
- 16,119 sq m (1,73,508 sq ft)
- Sanctioned built-up area
- 16,119 sq m (1,73,508 sq ft)
- Designated bank account
- 21
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
S No.41 H No-2/2, S No.41 H No-3 S No-41 H No-4
Boundaries
- North
- S No-45
- South
- S No-42-P and 44-C
- East
- S No-44-A
- West
- S No-40-2
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking277 units
32 of 277 units booked (12%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Wing A | 1BHK | 39.17 sq m · 422 sq ft | 21 | 0 |
| Wing A | 1BHK | 39.44 sq m · 425 sq ft | 20 | 0 |
| Wing A | 1BHK | 40.1 sq m · 432 sq ft | 22 | 0 |
| Wing A | 1BHK | 40.23 sq m · 433 sq ft | 20 | 0 |
| Wing A | 2BHK | 51.58 sq m · 555 sq ft | 11 | 0 |
| Wing A | 2BHK | 54.12 sq m · 583 sq ft | 22 | 0 |
| Wing A | 2BHK | 55.7 sq m · 600 sq ft | 9 | 0 |
| Wing B | 1BHK | 37.1 sq m · 399 sq ft | 14 | 2 |
Show all 17 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Wing B | 1BHK | 39.05 sq m · 420 sq ft | 14 | 0 |
| Wing B | 1BHK | 39.14 sq m · 421 sq ft | 14 | 3 |
| Wing B | 1BHK | 39.56 sq m · 426 sq ft | 14 | 6 |
| Wing B | 1BHK | 39.72 sq m · 428 sq ft | 12 | 0 |
| Wing B | 1BHK | 39.77 sq m · 428 sq ft | 14 | 0 |
| Wing B | 1BHK | 40.2 sq m · 433 sq ft | 14 | 1 |
| Wing B | 1BHK | 40.95 sq m · 441 sq ft | 28 | 10 |
| Wing B | 2BHK | 56.31 sq m · 606 sq ft | 14 | 3 |
| Wing B | 2BHK | 59.36 sq m · 639 sq ft | 14 | 7 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Raj Associates (Ar. S R Khambayat) | — |
| Chartered accountant | CA Ganapath jain | — |
| Chartered accountant | CA Rajendra Chaplot | — |
| Engineer | ER. Kamlesh R Patel | — |
Source: MahaRERA project page. Contact details are not shown.