Deedo IDDP-THN-3FKNCompletion was pushed back 4 months, to Jan 2029; no MahaRERA orders on record; 11% of its units are booked.
Badlapur (M Cl), Thane 421503 · by Shree Samarth Enterprises
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Jan 2029
- This projectRegistered 4 Mar 2024, completion promised 30 Sep 2028, revised to 30 Jan 2029.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700055115
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700055115 | 4 Mar 2024 | 30 Sep 2028 | 30 Jan 2029 | Shree Samarth Enterprises | Project page |
Documents89
1 document held by Deedo, 88 filings listed on MahaRERA's project page
Finance
- PAN CardPAN_samarth.pdf · uploaded 13 Sep 2023Source
Legal
Migrated
- 1 Commencement Certificates / NA Order for plotted developmentcc shree samartha enterprises.pdf · uploaded 10 Aug 2023Source
- 1 PAN CardPAN_samarth.pdf · uploaded 13 Sep 2023Source
- 1 a Details of encumbrances concerned to FinanceEncumbrances of partner.pdf · uploaded 13 Sep 2023Source
- 1 b Details of encumbrances concerned to LegalEncumbrances of partner.pdf · uploaded 13 Sep 2023Source
Show all 89 documentsShow fewer documents
Migrated
- 1 Building Plan Approval / NA Order for plotted developmentBLUE PRINT PLAN COPY 1 2compressed.pdf · uploaded 13 Sep 2023Source
- 2 Building Plan Approval / NA Order for plotted developmentBLUE PRINT PLAN COPY 22compressed.pdf · uploaded 13 Sep 2023Source
- 1 Declaration about Commencement CertificateCommencement Certificate declaration.pdf · uploaded 13 Sep 2023Source
- 1 Declaration in FORM BPramotor Anil Jaju.pdf · uploaded 13 Sep 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsAnil Jajau.pdf · uploaded 13 Sep 2023Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsNishant Dargar.pdf · uploaded 13 Sep 2023Source
- 3 Disclosure of Interest in Other Real Estate OrganizationsRavi Jaju.pdf · uploaded 13 Sep 2023Source
- 4 Disclosure of Interest in Other Real Estate OrganizationsSanjay Dargar.pdf · uploaded 13 Sep 2023Source
- 1 Proforma of Agreement for saleAGREEMENT FOR SALE.pdf · uploaded 13 Sep 2023Source
- 1 Copy of Layout Approval (in case of layout)LAYOUT PLAN SHEET.pdf · uploaded 3 Oct 2023Source
- 3 Building Plan Approval / NA Order for plotted developmentLAYOUT PLAN SHEET.pdf · uploaded 3 Oct 2023Source
- 1 CERSAI detailsCERSAI_Search_Report_.pdf · uploaded 23 Nov 2023Source
- 1 Other – Technical6_Mail copy.pdf · uploaded 23 Nov 2023Source
- 2 Other – Technical05_01_Letter No 064 Shree Samarth Ent Plinth Completion.pdf · uploaded 23 Nov 2023Source
- 2 CERSAI details02_Undertaking Cersai.pdf · uploaded 28 Nov 2023Source
- 5 Disclosure of Interest in Other Real Estate Organizations08_DoI_Rathi Developers LLP.pdf · uploaded 28 Nov 2023Source
- 1 Proforma of Allotment letter09_Allotment letter.pdf · uploaded 28 Nov 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the same04_Bank Account declaration.pdf · uploaded 28 Nov 2023Source
- 1 Deviation Report with respect to Allotment letter09_Declaration of no deviation in Allotment letter.pdf · uploaded 28 Nov 2023Source
- 1 Deviation Report with respect to model copy of Agreement10_Declaration of Deviation in Agreement letter.pdf · uploaded 28 Nov 2023Source
- 3 Other – Technical06_UD Communication.pdf · uploaded 28 Nov 2023Source
- 4 Other – TechnicalReply to queries.pdf · uploaded 28 Nov 2023Source
- 2 a Details of encumbrances concerned to Finance01_Declaration of no encumberance.pdf · uploaded 29 Nov 2023Source
- 2 b Details of encumbrances concerned to Legal01_Declaration of no encumberance.pdf · uploaded 29 Nov 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)05_Form 1-Signed-compressed.pdf · uploaded 29 Nov 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)05_Form 2-signed-compressed.pdf · uploaded 29 Nov 2023Source
- 1 Disclosure of sold/ booked inventoryDisclosure Inventory-Signed-compressed.pdf · uploaded 29 Nov 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)03_Form 3-Signed-compressed-better.pdf · uploaded 29 Nov 2023Source
- 5 Other – Technical08_rathi developers llp-Authorisation.pdf · uploaded 29 Nov 2023Source
- 6 Disclosure of Interest in Other Real Estate OrganizationsPankaj Teli.pdf · uploaded 29 Dec 2023Source
- 7 Disclosure of Interest in Other Real Estate OrganizationsSachin Shanbhag.pdf · uploaded 29 Dec 2023Source
- 8 Disclosure of Interest in Other Real Estate OrganizationsDeepak Mahatre.pdf · uploaded 29 Dec 2023Source
- 9 Disclosure of Interest in Other Real Estate OrganizationsSangeeta Mahatre.pdf · uploaded 29 Dec 2023Source
- 10 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in other Real Estate-Tukaram Mahatre010.pdf · uploaded 3 Jan 2024Source
- 11 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in other Real Estate-Subhash Teli011.pdf · uploaded 3 Jan 2024Source
- 1 Copy of the legal title reportnull_compressed.pdf · uploaded 17 Feb 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certifiacte.pdf · uploaded 18 Feb 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 18 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 18 Feb 2025Source
- Form 1Architect Certifiacte.pdf · uploaded 18 Oct 2025Source
- Form 2Engineer Certificate.pdf · uploaded 18 Oct 2025Source
- Form 3Form 3.pdf · uploaded 18 Oct 2025Source
- Disclosure of Sold and Booked Inventory31122024.pdf · uploaded 18 Oct 2025Source
- Form 1Form 1March 24.pdf · uploaded 25 Jun 2026Source
- Form 2Engineer certificate mar 24.pdf · uploaded 25 Jun 2026Source
- Form 3Form 3 mar 24-compressed.pdf · uploaded 25 Jun 2026Source
- Disclosure of Sold and Booked InventorySold Unsold.pdf · uploaded 25 Jun 2026Source
- Form 1Form 1 June 24.pdf · uploaded 25 Jun 2026Source
- Form 2Engineer certificate june 24.pdf · uploaded 25 Jun 2026Source
- Form 3Form 3 June 24-compressed.pdf · uploaded 25 Jun 2026Source
- Disclosure of Sold and Booked InventorySold unsolld June 24.pdf · uploaded 25 Jun 2026Source
- Form 1Form 1 Sep 24.pdf · uploaded 25 Jun 2026Source
- Form 2Engineer certificate Sept 24.pdf · uploaded 25 Jun 2026Source
- Form 3Form 3 Sep 24-compressed.pdf · uploaded 25 Jun 2026Source
- Disclosure of Sold and Booked InventorySold Unsold sep24.pdf · uploaded 25 Jun 2026Source
- Form 1Form 1March 25.pdf · uploaded 25 Jun 2026Source
- Form 2Engineer Certificate Mar 25.pdf · uploaded 25 Jun 2026Source
- Form 3Form 3Mar 25-compressed.pdf · uploaded 25 Jun 2026Source
- Disclosure of Sold and Booked InventorySold Unsold Mar 25.pdf · uploaded 25 Jun 2026Source
- Withdrawal Update Form 1Form 1 June 25.pdf · uploaded 25 Jun 2026Source
- Withdrawal Update Form 1Architect Certificate Sep 25.pdf · uploaded 25 Jun 2026Source
- Withdrawal Update Form 2Engineer Certificate June 25.pdf · uploaded 25 Jun 2026Source
- Withdrawal Update Form 2Engineer Certificate Sep 25.pdf · uploaded 25 Jun 2026Source
- Withdrawal Update Form 3Form 3 June 25-compressed.pdf · uploaded 25 Jun 2026Source
- Withdrawal Update Form 3UDIN Form 3 Sept 25.pdf · uploaded 25 Jun 2026Source
- Withdrawal Update Form 1Architect Cerificate Dec 25.pdf · uploaded 26 Jun 2026Source
- Withdrawal Update Form 2Engineer certificate Dec 25.pdf · uploaded 26 Jun 2026Source
- Withdrawal Update Form 3Final Form 3_Dec 25.pdf · uploaded 26 Jun 2026Source
Technical
- DocumentBLUE PRINT PLAN COPY 1 2compressed.pdf · uploaded 13 Sep 2023Source
- DocumentBLUE PRINT PLAN COPY 22compressed.pdf · uploaded 13 Sep 2023Source
- DocumentLAYOUT PLAN SHEET.pdf · uploaded 3 Oct 2023Source
- DocumentLAYOUT PLAN SHEET.pdf · uploaded 3 Oct 2023Source
- Other – Technical6_Mail copy.pdf · uploaded 23 Nov 2023Source
- Other – Technical05_01_Letter No 064 Shree Samarth Ent Plinth Completion.pdf · uploaded 23 Nov 2023Source
- Other – Technical06_UD Communication.pdf · uploaded 28 Nov 2023Source
- Other – TechnicalReply to queries.pdf · uploaded 28 Nov 2023Source
- Other – Technical08_rathi developers llp-Authorisation.pdf · uploaded 29 Nov 2023Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 2, 3
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- —180 units in all
- Address
- Survey No 79, Hissa No. 1, 2 & 3, BelavliPIN 421503
- Village
- Badlapur (M Cl), Ambarnath taluka
- Location
- 19.17968, 73.22345
- Designated bank account
- 66
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking180 units
180 units registered
| Building | Type | Carpet area | Units |
|---|---|---|---|
| Building A | — | — | 157 |
| Building B | — | — | 23 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Rahul Shrikhande & Associates | — |
| Chartered accountant | A Y Kale and Associates | — |
| Engineer | M Nandwani Structural Consultants | — |
Source: MahaRERA project page. Contact details are not shown.