Skip to content
Deedo home
Menu

Shree Samarth Enterprises

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date—no proposed date has passed yet
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Om Dutta Deep Co. Op HSGP51700054486Badlapur (M Cl)2024Not reported31 Dec 2026—On date
Swaraswati HeightsP51700055115Badlapur (M Cl)2024Not reported30 Sep 2028—On date
Deepsamay ChsP51700080595Badlapur (M Cl)2025Not reported30 Jun 2028—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Om Dutta Deep Co. Op HSGOn date
  • Swaraswati HeightsOn date
  • Deepsamay ChsOn date

Track record notes

  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology