Extended 33 mo6 floorsRERA P51700023483

Main building, Regency Plaza

Deedo IDDP-THN-T23K-RP

MahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.

All of Regency Plaza
Median saleNot on recordneeds 3 or more sales
Booked65%35 of 54 · MahaRERA
Completion31 Dec 202630 Mar 2024 · revised
Units & parking in Main building
TypeCarpet areaUnitsBooked
1 BHK26.3 m² (283 sq.ft)32
1 BHK26.4 m² (284 sq.ft)30
1 BHK28.1 m² (302 sq.ft)32
1 BHK28.6 m² (308 sq.ft)33
1 BHK29 m² (312 sq.ft)65
1 BHK29.8 m² (321 sq.ft)66
2 BHK39.9 m² (429 sq.ft)33
OFFICE10.4 m² (112 sq.ft)31
OFFICE10.6 m² (114 sq.ft)20
OFFICE11.1 m² (119 sq.ft)10
OFFICE12.7 m² (136 sq.ft)63
OFFICE14.7 m² (158 sq.ft)11
OFFICE85 m² (915 sq.ft)11
OFFICE140.2 m² (1,509 sq.ft)10
Shop14.8 m² (159 sq.ft)10
Shop151 m² (1,625 sq.ft)10
SHOP9.3 m² (100 sq.ft)11
SHOP9.4 m² (101 sq.ft)11
SHOP11.3 m² (121 sq.ft)11
SHOP12.9 m² (138 sq.ft)11
SHOP13 m² (140 sq.ft)11
SHOP13.7 m² (148 sq.ft)10
SHOP14.7 m² (158 sq.ft)10
SHOP15.7 m² (169 sq.ft)33
As registered with MahaRERA
RERA registration
P51700023483 · registered 18 Dec 2019
Promised completion
30 Mar 2024
Revised completion
31 Dec 2026
Sanctioned habitable floors
6
Building
REGENCY PLAZA
Sanctioned floors (incl. basement, stilt, podium)
6
Units declared
0
Homes
0
Shops and offices
0
MahaRERA status
Certificate Signed
Deedo ID
DP-THN-T23K-RP
Questions about Main building

When is Main building due for completion?

The MahaRERA registration promises 30 Mar 2024, revised to 31 Dec 2026.

How many floors does Main building have?

6 sanctioned habitable floors, as registered with MahaRERA.

Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology