Regency Plaza
Deedo IDDP-THN-T23KMahaRERA shows it completed, after its date was pushed back 2 years and 9 months; no MahaRERA orders on record; 65% of its units are booked.
Badlapur, Thane 421503 · by Shree Sai Ventures
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed, after its date was pushed back 2 years and 9 months
- This projectRegistered 18 Dec 2019, completion promised 30 Mar 2024, revised to 31 Dec 2026.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700023483
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700023483 | 18 Dec 2019 | 30 Mar 2024 | 31 Dec 2026 | Shree Sai Ventures | Project page |
Documents62
3 documents held by Deedo, 59 filings listed on MahaRERA's project page
Other
- OtherDate not statedView
Finance
- PAN CardFirm Pan Card_compressed.pdf · uploaded 30 May 2019Source
Legal
- Legal Title reportTitle Certificate_compressed.pdf · uploaded 30 May 2019Source
- Declaration Form BDeveloper Form B_compressed.pdf · uploaded 3 Aug 2019Source
- Declaration Form BForm B Builder .pdf · uploaded 3 Apr 2024Source
- Declaration Form BAffidavit (vishwambhar shelke).pdf · uploaded 13 May 2024Source
Show all 62 documentsShow fewer documents
Migrated
- 1 PAN CardFirm Pan Card_compressed.pdf · uploaded 30 May 2019Source
- 1 Copy of the legal title reportTitle Certificate_compressed.pdf · uploaded 30 May 2019Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect's Certificate_compressed.pdf · uploaded 30 May 2019Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate_compressed.pdf · uploaded 30 May 2019Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement_compressed.pdf · uploaded 31 May 2019Source
- 1 Proforma of Allotment letterAllotment Letter_compressed.pdf · uploaded 31 May 2019Source
- 2 Proforma of Allotment letterDraft_Agreement_compressed.pdf · uploaded 31 May 2019Source
- 1 Details of encumbrancesNon encumbrance.pdf · uploaded 3 Aug 2019Source
- 1 Declaration in FORM BDeveloper Form B_compressed.pdf · uploaded 3 Aug 2019Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)REGENCY PLAZA768.pdf · uploaded 14 Sep 2019Source
- 1 Copy of Layout Approval (in case of layout)MYSCAN_20191010_0002.PDF · uploaded 22 Oct 2019Source
- 1 Building Plan Approval / NA Order for plotted developmentN A Order sai ventures_compressed.pdf · uploaded 21 Nov 2019Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 30 Jun 2021Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 30 Jun 2021Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 30 Jun 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 Shri Sai Ventures.pdf · uploaded 30 Jun 2021Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)JUNE20 - SSV.pdf · uploaded 15 Aug 2021Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)SEPT20 - SSV.pdf · uploaded 15 Aug 2021Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)DEC20 - SSV.pdf · uploaded 15 Aug 2021Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)MARCH21 - SSV.pdf · uploaded 15 Aug 2021Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)JUNE21-SSV.pdf · uploaded 15 Aug 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Shree Sai Ven Form 5 FY 20-21.pdf · uploaded 11 Jun 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Shree Sai Ven Form 5 2021-22.pdf · uploaded 15 Feb 2023Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Sep 21_compressed.pdf · uploaded 14 Dec 2023Source
- 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)Forn 3 Dec 21_compressed.pdf · uploaded 14 Dec 2023Source
- 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Mar 22_compressed.pdf · uploaded 14 Dec 2023Source
- 13 CA Certificate on Project Cost & Fund withdrawal (Form 3)Shree sai ventures form 3 June 22_compressed.pdf · uploaded 14 Dec 2023Source
- 14 CA Certificate on Project Cost & Fund withdrawal (Form 3)Shree sai ventures form 3 sep 22.pdf · uploaded 14 Dec 2023Source
- 15 CA Certificate on Project Cost & Fund withdrawal (Form 3)shree sai vent form 3 Dec 22.pdf · uploaded 14 Dec 2023Source
- 16 CA Certificate on Project Cost & Fund withdrawal (Form 3)shree sai vent form 3 Mar 23.pdf · uploaded 14 Dec 2023Source
- 17 CA Certificate on Project Cost & Fund withdrawal (Form 3)shree sai vent form 3 June 23.pdf · uploaded 14 Dec 2023Source
- 18 CA Certificate on Project Cost & Fund withdrawal (Form 3)shree sai ven form 3 sep 23.pdf · uploaded 14 Dec 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 2022-23.pdf · uploaded 14 Dec 2023Source
- 2 Declaration in FORM BForm B Builder .pdf · uploaded 3 Apr 2024Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect certificate .pdf · uploaded 3 Apr 2024Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers certificate .pdf · uploaded 3 Apr 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A.pdf · uploaded 19 Apr 2024Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 Mar 24_compressed.pdf · uploaded 7 May 2024Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Mar 24.pdf · uploaded 7 May 2024Source
- 19 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Mar 24_compressed.pdf · uploaded 7 May 2024Source
- 3 Declaration in FORM BAffidavit (vishwambhar shelke).pdf · uploaded 13 May 2024Source
- 1 Disclosure of sold/ booked inventoryDisclosure of Sold inventory.pdf · uploaded 13 May 2024View
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 June 24_compressed.pdf · uploaded 30 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)shree sai ven form 3 June 24_compressed.pdf · uploaded 30 Oct 2024Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 June 24_compressed.pdf · uploaded 30 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)shree sai ven form 5 23-24 .pdf · uploaded 30 Oct 2024Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC Shree Sai Ven.pdf · uploaded 8 Nov 2024Source
- 1 Architect’s Certificate on Completion of Project (Form 4)Form 4 Regency Plaza.pdf · uploaded 7 Feb 2025Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel S no 81 Hissa No 3
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1 BHK, 2 BHK, Office, Shop54 units in all
- Address
- S no 81 Hissa No 3, Belavali, BadlapurPIN 421503
- Village
- Badlapur (M Cl), Ambarnath taluka
- Location
- 20.21520, 73.79860
- Land area for this project
- 1,110 sq m (11,948 sq ft)
- Permissible built-up area
- 1,639 sq m (17,647 sq ft)
- Sanctioned built-up area
- 1,639 sq m (17,647 sq ft)
- Recreational open space
- 118 sq m (1,265 sq ft)
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
S no 81 Hissa No 3
Boundaries
- North
- Land Bearing 18 M wide D P Road
- South
- Land Bearing S No 81 P
- East
- Land Bearing S No 83 P
- West
- Land Bearing S No 80 P
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking54 units
35 of 54 units booked (65%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK | 26.28 sq m · 283 sq ft | 3 | 2 |
| 1 BHK | 26.37 sq m · 284 sq ft | 3 | 0 |
| 1 BHK | 28.08 sq m · 302 sq ft | 3 | 2 |
| 1 BHK | 28.61 sq m · 308 sq ft | 3 | 3 |
| 1 BHK | 29.03 sq m · 312 sq ft | 6 | 5 |
| 1 BHK | 29.79 sq m · 321 sq ft | 6 | 6 |
| 2 BHK | 39.9 sq m · 429 sq ft | 3 | 3 |
| Office | 10.42 sq m · 112 sq ft | 3 | 1 |
Show all 24 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Office | 10.55 sq m · 114 sq ft | 2 | 0 |
| Office | 11.1 sq m · 119 sq ft | 1 | 0 |
| Office | 12.66 sq m · 136 sq ft | 6 | 3 |
| Office | 14.66 sq m · 158 sq ft | 1 | 1 |
| Office | 84.98 sq m · 915 sq ft | 1 | 1 |
| Office | 140.2 sq m · 1,509 sq ft | 1 | 0 |
| Shop | 14.78 sq m · 159 sq ft | 1 | 0 |
| Shop | 150.95 sq m · 1,625 sq ft | 1 | 0 |
| Shop | 9.27 sq m · 100 sq ft | 1 | 1 |
| Shop | 9.35 sq m · 101 sq ft | 1 | 1 |
| Shop | 11.27 sq m · 121 sq ft | 1 | 1 |
| Shop | 12.85 sq m · 138 sq ft | 1 | 1 |
| Shop | 12.97 sq m · 140 sq ft | 1 | 1 |
| Shop | 13.71 sq m · 148 sq ft | 1 | 0 |
| Shop | 14.7 sq m · 158 sq ft | 1 | 0 |
| Shop | 15.66 sq m · 169 sq ft | 3 | 3 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Space Designers | — |
| Chartered accountant | Ashwini Prabhu | — |
| Engineer | Darshan Kasture | — |
| Other | Ashok Rameshwar Choudhari | — |
Source: MahaRERA project page. Contact details are not shown.