Skip to content
Promised date passed6 floors · 36 flatsRERA P51700049706

Main building, Ram Rivera

Deedo IDDP-THN-GBGP-RR

34 of 36 flats are unsold and 2 are booked; no sale deed is on record yet.

All of Ram Rivera
Median saleNot on recordneeds 3 or more sales
Booked6%2 of 36
Completion30 Sep 2025as registered

Every flat, floor by floor

Tap a flat to see its record.

  • Booked, no deed yet
  • Unsold
0102030405
Fl 6
Fl 5
Fl 4
Fl 3
Fl 2
Fl 1
Fl G
2 BHK1 BHK1 BHK2 BHK

Other units on these floors (no stack in the number):

Fl 4
Fl 1
Fl G

Flat number not read (7): no floor on record and the number doesn't say one.

Sale status from MahaRERA's disclosure; deeds from IGR Index II, placed on a flat only when the deed names this tower and flat. “Listed by developer” comes from the developer and is labelled as such.

SelectedBooked

Flat 604

2 BHK · 528 sq ft · floor 6

Deeds
0
Last activity
None on record
Last sale
None registered
Units & parking in Main building
TypeCarpet areaUnitsBooked
1BHK25.1 m² (270 sq.ft)10
1BHK35.7 m² (384 sq.ft)51
1BHK36 m² (387 sq.ft)40
1BHK37.3 m² (401 sq.ft)40
2BHK45.9 m² (494 sq.ft)50
2BHK49 m² (528 sq.ft)11
2BHK49.1 m² (528 sq.ft)40
Office space22.4 m² (242 sq.ft)10
Office space24.2 m² (260 sq.ft)10
Office space24.3 m² (262 sq.ft)10
Office space35.8 m² (386 sq.ft)10
Office space36 m² (388 sq.ft)10
Office space46.1 m² (496 sq.ft)10
Office space49.1 m² (528 sq.ft)10
Office space49.8 m² (536 sq.ft)10
Shop10.3 m² (111 sq.ft)10
Shop10.3 m² (111 sq.ft)10
Shop11.5 m² (124 sq.ft)20
Shop18.6 m² (200 sq.ft)10
Shop43.7 m² (470 sq.ft)10
As registered with MahaRERA
RERA registration
P51700049706 · registered 22 Feb 2023
Promised completion
30 Sep 2025
Revised completion
30 Sep 2025
Sanctioned habitable floors
6
Building
RAM RIVERA
Sanctioned floors (incl. basement, stilt, podium)
6
Units declared
0
Homes
0
Shops and offices
0
MahaRERA status
Certificate Signed
Deedo ID
DP-THN-GBGP-RR
Questions about Main building

How many flats in Main building are sold?

0 flats have a sale on record, 2 are booked without a sale deed yet and 34 are unsold.

When is Main building due for completion?

The MahaRERA registration promises 30 Sep 2025.

How many floors does Main building have?

6 sanctioned habitable floors, as registered with MahaRERA.

Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology