Promised date passed7 floorsRERA P51700015392
R7, Panvelkar Optima
Deedo IDDP-THN-3GD3-R7MahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked59%10 of 17 · MahaRERA
Completion30 Sep 2020as registered
Units & parking in R7
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK | 25.2 m² (271 sq.ft) | 3 | 1 |
| 1 BHK | 27.9 m² (300 sq.ft) | 3 | 2 |
| 1 BHK | 28.4 m² (306 sq.ft) | 3 | 1 |
| OFFICE | 24.8 m² (267 sq.ft) | 1 | 0 |
| OFFICE | 60.1 m² (647 sq.ft) | 1 | 0 |
| SHOP | 6.8 m² (74 sq.ft) | 2 | 2 |
| SHOP | 8.2 m² (88 sq.ft) | 1 | 1 |
| SHOP | 9 m² (97 sq.ft) | 1 | 1 |
| SHOP | 12.7 m² (137 sq.ft) | 1 | 1 |
| SHOP | 16.5 m² (177 sq.ft) | 1 | 1 |
As registered with MahaRERA
- RERA registration
- P51700015392 · registered 21 Feb 2018
- Promised completion
- 30 Sep 2020
- Revised completion
- 30 Sep 2020
- Sanctioned habitable floors
- 7
- Sanctioned floors (incl. basement, stilt, podium)
- 7
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-THN-3GD3-R7
Questions about R7
When is R7 due for completion?
The MahaRERA registration promises 30 Sep 2020.
How many floors does R7 have?
7 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology