Residential / Group Housing · 2 buildings · 218 unitsRERA P51700028880

Nano City

Deedo IDDP-THN-WQ4H

Its promised completion date, Jun 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 64% of its units are booked.

Badlapur (M Cl), Thane 421503 · by Pinnacle Spm Group

Delivery1 yr 5 mo past duePromised Jun 2025 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales64% booked140 of 218 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Jun 2025, has passed and MahaRERA does not show it completed

  • This projectRegistered 5 Apr 2021, completion promised 30 Jun 2025, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700028880
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P517000288805 Apr 202130 Jun 202530 Jun 2025Pinnacle Spm GroupProject page
Documents44

1 document held by Deedo, 43 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPinnacle SPM Group PAN Card.pdf · uploaded 25 Mar 2021Source

Legal

  • Legal Title reportLegal Title Report Survey No 8-comp.pdf · uploaded 25 Mar 2021Source
  • Legal Title reportLegal Title Report Survey No 9-Comp.pdf · uploaded 25 Mar 2021Source
  • Declaration Form BAffidavit cum Declaration From Partners (1).pdf · uploaded 26 Mar 2021Source
  • Legal Title reportPSPMG DCB Bank Letter Encumbrance.pdf · uploaded 8 Jun 2022Source

Migrated

  • 1 PAN CardPinnacle SPM Group PAN Card.pdf · uploaded 25 Mar 2021Source
  • 1 Copy of the legal title reportLegal Title Report Survey No 8-comp.pdf · uploaded 25 Mar 2021Source
Show all 44 documentsShow fewer documents

Migrated

  • 2 Copy of the legal title reportLegal Title Report Survey No 9-Comp.pdf · uploaded 25 Mar 2021Source
  • 1 Details of encumbrancesLegal Title Report Survey No 8-comp.pdf · uploaded 25 Mar 2021Source
  • 2 Details of encumbrancesLegal Title Report Survey No 9-Comp.pdf · uploaded 25 Mar 2021Source
  • 1 Copy of Layout Approval (in case of layout)Layout Plan_ FINAL.pdf · uploaded 25 Mar 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentLayout Plan_ FINAL.pdf · uploaded 25 Mar 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC Copy comp.pdf · uploaded 25 Mar 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA certificate Pinnacle SPM signed comp.pdf · uploaded 25 Mar 2021Source
  • 1 Proforma of Allotment letterDraft Sale Agreement.pdf · uploaded 25 Mar 2021Source
  • 1 Declaration in FORM BAffidavit cum Declaration From Partners (1).pdf · uploaded 26 Mar 2021Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 as on 20 01 2022 Pinnacle Spm Group signed.pdf · uploaded 4 Mar 2022Source
  • 3 Copy of the legal title reportPSPMG DCB Bank Letter Encumbrance.pdf · uploaded 8 Jun 2022Source
  • 3 Details of encumbrancesPSPMG DCB Bank Letter Encumbrance.pdf · uploaded 8 Jun 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 13 Jul 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 13 Jul 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)form 5 Pinnacle SPM Group.pdf · uploaded 23 Jan 2023Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 signed.pdf · uploaded 3 May 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form1 Pinnacle SPM Group.pdf · uploaded 25 Jun 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Pinnacle SPM Group.pdf · uploaded 25 Jun 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1 Pinnacle SPM Group.pdf · uploaded 26 Jun 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form5- Signed.pdf · uploaded 28 Feb 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1 Pinnacle SPM Group.pdf · uploaded 14 Mar 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Pinnacle SPM Group.pdf · uploaded 14 Mar 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)2024-03-14 15-15 (1).pdf · uploaded 14 Mar 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1_compressed.pdf · uploaded 1 Jun 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 1 Jun 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1.pdf · uploaded 1 Jun 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 1 Jun 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 1 Jun 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form2_.pdf · uploaded 1 Jun 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 1 Jun 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 1 Jun 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 1 Jun 2024Source

Technical

  • DocumentLayout Plan_ FINAL.pdf · uploaded 25 Mar 2021Source
  • DocumentLayout Plan_ FINAL.pdf · uploaded 25 Mar 2021Source

Technical (Architect)

  • DocumentForm1.pdf · uploaded 1 Jun 2024Source

Technical (Engineer)

  • DocumentForm2_.pdf · uploaded 1 Jun 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel S NO 8/1A, S NO 8/2B

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1RK, 1.5BHK, 2BHK218 units in all
Address
S No 8/2b, S No 8/1a, S No 9/8, Joveli, JoveliPIN 421503
Village
Badlapur (M Cl), Ambarnath taluka
Land area for this project
7,430 sq m (79,976 sq ft)
Permissible built-up area
16,997 sq m (1,82,959 sq ft)
Sanctioned built-up area
10,721 sq m (1,15,402 sq ft)
Recreational open space
664 sq m (7,147 sq ft)
Designated bank account
51
Developed in phases
Yes

Survey, CTS, gat or plot numbers

S NO 8/1AS NO 8/2BS NO 9/8

Land as published on MahaRERA's project page

S NO 8/2B,S NO 8/1A, S NO 9/8

Boundaries

North
S No 7
South
H No 1 P 2 3
East
30 Mtr Wide Road
West
S No 7 H No 4 5

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking218 units

140 of 218 units booked (64%), as the promoter reported to MahaRERA

1BHK · 109 units1RK · 76 units1.5BHK · 22 units2BHK · 11 units
BuildingTypeCarpet areaUnitsBooked
Wing B1BHK32.85 sq m · 354 sq ft3327
Wing B1BHK35 sq m · 377 sq ft3325
Wing B1BHK35.92 sq m · 387 sq ft117
Wing B1RK21.24 sq m · 229 sq ft3224
Wing B1RK23.39 sq m · 252 sq ft4421
Wing C1.5BHK42.21 sq m · 454 sq ft112
Wing C1.5BHK44.61 sq m · 480 sq ft117
Wing C1BHK34 sq m · 366 sq ft118
Wing C1BHK34.9 sq m · 376 sq ft2114
Wing C2BHK51.45 sq m · 554 sq ft115

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectVISHAL VILAS DALal—
Chartered accountantMangesh Ghanekarr—
EngineerSwapnil Jadhav—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology