Residential / Group Housing · 3 buildings · 147 unitsRERA P51700046891

Ekdant Pooja Chsl

Deedo IDDP-THN-88V2

Completion was pushed back 4 months, to Nov 2026; no MahaRERA orders on record; 82% of its units are booked.

Badlapur (M Cl), Thane 421503 · by Landmark Infra

DeliveryExtended 4 moPromised Jul 2026 · now due Nov 2026RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales82% booked121 of 147 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Nov 2026

  • This projectRegistered 16 Sep 2022, completion promised 31 Jul 2026, revised to 30 Nov 2026.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

3 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700046891
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170004689116 Sep 202231 Jul 202630 Nov 2026Landmark InfraProject page
Documents86

1 document held by Deedo, 85 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Cardcompany PAN.pdf · uploaded 16 Jul 2022Source

Legal

  • Legal Title reportTITLE REPORT.pdf · uploaded 16 Jul 2022Source
  • Declaration Form BFORM B BUILDER.pdf · uploaded 16 Jul 2022Source

Migrated

  • 1 PAN Cardcompany PAN.pdf · uploaded 16 Jul 2022Source
  • 1 Copy of the legal title reportTITLE REPORT.pdf · uploaded 16 Jul 2022Source
  • 1 Copy of Layout Approval (in case of layout)LAYOUT PLAN-2.pdf · uploaded 16 Jul 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentPLAN-1.pdf · uploaded 16 Jul 2022Source
Show all 86 documentsShow fewer documents

Migrated

  • 1 Commencement Certificates / NA Order for plotted developmentCommencement certificate.pdf · uploaded 16 Jul 2022Source
  • 1 Declaration about Commencement CertificateDeclaration About Commencement certificate.pdf · uploaded 16 Jul 2022Source
  • 1 Declaration in FORM BFORM B BUILDER.pdf · uploaded 16 Jul 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE.pdf · uploaded 16 Jul 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE.pdf · uploaded 16 Jul 2022Source
  • 1 CERSAI detailsCERSAI_Search_Report_200243306888_For_Asset_Based_Search_27_07_2022_19_21_56_548.pdf · uploaded 27 Jul 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE_11zon.pdf · uploaded 27 Jul 2022Source
  • 1 a Details of encumbrances concerned to FinanceFINANCIAL ENCRUMBANCES.pdf · uploaded 23 Aug 2022Source
  • 1 b Details of encumbrances concerned to LegalLEGAL ENCRUMBANECS.pdf · uploaded 23 Aug 2022Source
  • 1 Proforma of Allotment letterAllotment letter format_11zon.pdf · uploaded 23 Aug 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFORMAT A.pdf · uploaded 23 Aug 2022Source
  • 1 Deviation Report with respect to Allotment letterDEVIATION REPORT TO ALLOTMENT LETTER.pdf · uploaded 23 Aug 2022Source
  • 2 Proforma of Allotment letterNew_draft-Ekdant_Pooja.pdf · uploaded 6 Sep 2022Source
  • 1 Deviation Report with respect to model copy of AgreementDEVIATION LETTER-AFS.pdf · uploaded 6 Sep 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect's Certificate- Landmark Infra 3_11zon.pdf · uploaded 12 May 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's Certificate- Landmark Infra_11zon.pdf · uploaded 12 May 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate- Landmark Infra (3)_11zon.pdf · uploaded 12 May 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Rera Architect Certificate_11zon.pdf · uploaded 20 Oct 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architecture certificate Landmark Infra.pdf · uploaded 20 Oct 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE JUN 23_11zon.pdf · uploaded 20 Oct 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate Landmark Infra.pdf · uploaded 20 Oct 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Landmark Infra-11zon.pdf · uploaded 20 Oct 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)RERA AUDIT FORM 5 MAR23.pdf · uploaded 20 Oct 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA certificate landmark infra.pdf · uploaded 21 Oct 2023Source
  • 1 Disclosure of sold/ booked inventoryDisclosure Mar 23 landmark .pdf · uploaded 31 Jan 2024Source
  • 2 Disclosure of sold/ booked inventoryDisclosure Jun 23 Landmark .pdf · uploaded 31 Jan 2024Source
  • 3 Disclosure of sold/ booked inventoryDisclosure Sept 23 Landmark .pdf · uploaded 31 Jan 2024Source
  • 4 Disclosure of sold/ booked inventoryDisclosure Dec 23 Landmark .pdf · uploaded 31 Jan 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate dec23_11zon.pdf · uploaded 3 Feb 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate dec23 .pdf · uploaded 3 Feb 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3_11zon.pdf · uploaded 3 Feb 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate_11zon.pdf · uploaded 2 May 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate .pdf · uploaded 23 May 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Quality Assurance Certificate landmark .pdf · uploaded 23 May 2024Source
  • 5 Disclosure of sold/ booked inventorySold Unsold inventory .pdf · uploaded 23 May 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate - Landmark Infra_11zon.pdf · uploaded 23 May 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Rera.pdf · uploaded 8 Nov 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Rera.pdf · uploaded 8 Nov 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 landmark_11zon (1).pdf · uploaded 9 Nov 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)LANDMARK INFRA FORM 5.pdf · uploaded 9 Nov 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 11 Nov 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 11 Nov 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 11 Nov 2024Source
  • 2 Disclosure of sold/ booked inventoryDISCLOSURE.pdf · uploaded 11 Nov 2024Source
  • 3 Disclosure of sold/ booked inventoryDISCLOSURE.pdf · uploaded 11 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 23 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 23 Jan 2025Source
  • 1 Disclosure of sold/ booked inventoryDISCLOSURE- Q3.pdf · uploaded 23 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 28 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect certificate.pdf · uploaded 5 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers certificate.pdf · uploaded 5 May 2025Source
  • 1 Disclosure of sold/ booked inventoryDisclosure sold - unsold Land Mark Infra.pdf · uploaded 5 May 2025Source
  • Form 1FORM 1.pdf · uploaded 8 Aug 2025Source
  • Form 2FORM 2.pdf · uploaded 8 Aug 2025Source
  • Form 3Form 3 Landmark Infra.pdf · uploaded 8 Aug 2025Source
  • Disclosure of Sold and Booked InventoryDisclosure.pdf · uploaded 8 Aug 2025Source
  • Form 5 (FY 2024-2025)Form 5 Landmark Infra.pdf · uploaded 17 Sep 2025Source
  • Withdrawal Update Form 1FORM 1.pdf · uploaded 29 Nov 2025Source
  • Withdrawal Update Form 2FORM 2_11zon.pdf · uploaded 29 Nov 2025Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 29 Nov 2025Source
  • Withdrawal Update Form 1FORM 1.pdf · uploaded 5 Feb 2026Source
  • Withdrawal Update Form 2FORM 2.pdf · uploaded 5 Feb 2026Source
  • Withdrawal Update Form 3FORM 3.pdf · uploaded 5 Feb 2026Source
  • Form 2A (FY 2024-2025)FORM 2A.pdf · uploaded 27 Feb 2026Source
  • Form 5 (FY 2025-2026)FORM 5.pdf · uploaded 28 Sep 2026Source
  • Form 2A (FY 2025-2026)FORM 2A.pdf · uploaded 30 Sep 2026Source

Technical

  • DocumentLAYOUT PLAN-2.pdf · uploaded 16 Jul 2022Source
  • DocumentPLAN-1.pdf · uploaded 16 Jul 2022Source

Technical (Architect)

  • DocumentArchitect Certificate Rera.pdf · uploaded 8 Nov 2024Source
  • DocumentArchitect Certificate.pdf · uploaded 11 Nov 2024Source
  • DocumentFORM 1.pdf · uploaded 23 Jan 2025Source
  • DocumentArchitect certificate.pdf · uploaded 5 May 2025Source
  • DocumentFORM 1.pdf · uploaded 5 Feb 2026Source

Technical (Engineer)

  • DocumentEngineer Certificate Rera.pdf · uploaded 8 Nov 2024Source
  • DocumentEngineer Certificate.pdf · uploaded 11 Nov 2024Source
  • DocumentFORM 2.pdf · uploaded 23 Jan 2025Source
  • DocumentEngineers certificate.pdf · uploaded 5 May 2025Source
  • DocumentFORM 2.pdf · uploaded 5 Feb 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 2 S NO 40 H NO 13 PLOT NO 1, S NO 40 H NO 11 PLOT NO 3 S NO 40 H NO 12 PLOT NO 1

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, 1RK, 3BHK147 units in all
Address
S No 40 H No 11 Plot No 3 S No 40 H No 12 Plot No 1 & 2 S No 40 H No 13 Plot No 1, Kulgaon, Badlapur EastPIN 421503
Village
Badlapur (M Cl), Ambarnath taluka
Land area for this project
2,620 sq m (28,206 sq ft)
Permissible built-up area
7,127 sq m (76,719 sq ft)
Sanctioned built-up area
7,127 sq m (76,719 sq ft)
Recreational open space
2,620 sq m (28,206 sq ft)
Designated bank account
203
Developed in phases
Yes

Survey, CTS, gat or plot numbers

2 S NO 40 H NO 13 PLOT NO 1S NO 40 H NO 11 PLOT NO 3 S NO 40 H NO 12 PLOT NO 1

Land as published on MahaRERA's project page

S NO 40 H NO 11 PLOT NO 3 S NO 40 H NO 12 PLOT NO 1 & 2 S NO 40 H NO 13 PLOT NO 1

Boundaries

North
New English School
South
Ambika Jyot Chsl
East
Road And Vivekanand Society
West
Adarsh Vidya Mandir Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking147 units

121 of 147 units booked (82%), as the promoter reported to MahaRERA

1BHK · 89 units2BHK · 50 units1RK · 1 unit3BHK · 7 units
BuildingTypeCarpet areaUnitsBooked
Ekdant Pooja Chsl A Wing1BHK34.31 sq m · 369 sq ft76
Ekdant Pooja Chsl A Wing1BHK35.54 sq m · 383 sq ft149
Ekdant Pooja Chsl A Wing2BHK44.75 sq m · 482 sq ft77
Ekdant Pooja Chsl A Wing2BHK45.62 sq m · 491 sq ft75
Ekdant Pooja Chsl A Wing2BHK45.99 sq m · 495 sq ft77
Ekdant Pooja Chsl B Wing1BHK34.88 sq m · 375 sq ft75
Ekdant Pooja Chsl B Wing1BHK35.35 sq m · 381 sq ft63
Ekdant Pooja Chsl B Wing1BHK35.54 sq m · 383 sq ft1411
Show all 19 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Ekdant Pooja Chsl B Wing1BHK36.59 sq m · 394 sq ft1311
Ekdant Pooja Chsl B Wing1RK25.27 sq m · 272 sq ft11
Ekdant Pooja Chsl B Wing2BHK46.85 sq m · 504 sq ft11
Ekdant Pooja Chsl B Wing2BHK50.04 sq m · 539 sq ft77
Ekdant Pooja Chsl C Wing1BHK32.84 sq m · 353 sq ft76
Ekdant Pooja Chsl C Wing1BHK37.09 sq m · 399 sq ft73
Ekdant Pooja Chsl C Wing1BHK38.53 sq m · 415 sq ft1413
Ekdant Pooja Chsl C Wing2BHK43.92 sq m · 473 sq ft77
Ekdant Pooja Chsl C Wing2BHK46.25 sq m · 498 sq ft76
Ekdant Pooja Chsl C Wing2BHK48.74 sq m · 525 sq ft77
Ekdant Pooja Chsl C Wing3BHK70.94 sq m · 764 sq ft76

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSpace Designers—
Chartered accountantM N Jain & Co—
Chartered accountantRaviraj B Dange And Associates—
EngineerDarshan A Kasture—
EngineerSaad Consultant—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology