Extended 25 mo7 floorsRERA P51700005580
Main building, Aruna Ulhas
Deedo IDDP-THN-T83R-AUMahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked100%30 of 30 · MahaRERA
Completion30 Sep 202031 Aug 2018 · revised
Units & parking in Main building
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 18.6 m² (200 sq.ft) | 4 | 4 |
| 1BHK | 23.8 m² (256 sq.ft) | 4 | 4 |
| 1BHK | 24.2 m² (260 sq.ft) | 4 | 4 |
| 1RK | 16.5 m² (177 sq.ft) | 4 | 4 |
| 1RK | 17.9 m² (193 sq.ft) | 4 | 4 |
| OFFICE | 30.5 m² (329 sq.ft) | 1 | 1 |
| SHOP | 4.6 m² (49 sq.ft) | 1 | 1 |
| SHOP | 5.3 m² (57 sq.ft) | 1 | 1 |
| SHOP | 8.3 m² (89 sq.ft) | 1 | 1 |
| SHOP | 9.3 m² (100 sq.ft) | 1 | 1 |
| SHOP | 9.4 m² (101 sq.ft) | 2 | 2 |
| SHOP | 9.6 m² (103 sq.ft) | 1 | 1 |
| SHOP | 15.2 m² (163 sq.ft) | 1 | 1 |
| SHOP | 16.1 m² (173 sq.ft) | 1 | 1 |
As registered with MahaRERA
- RERA registration
- P51700005580 · registered 11 Aug 2017
- Promised completion
- 31 Aug 2018
- Revised completion
- 30 Sep 2020
- Sanctioned habitable floors
- 7
- Building
- ARUNA ULHAS
- Sanctioned floors (incl. basement, stilt, podium)
- 7
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-THN-T83R-AU
Questions about Main building
When is Main building due for completion?
The MahaRERA registration promises 31 Aug 2018, revised to 30 Sep 2020.
How many floors does Main building have?
7 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology