Residential / Group Housing · 2 buildingsRERA P51700008943

Arham Vatika

MahaRERA shows it completed; 1 listing or order with MahaRERA on record.

Badlapur (M Cl), Thane 421503 · Promoter: Arham Enterprises

DeliveryCompletedAs MahaRERA showsRegulatory1 listing or orderLatest: Suo motu order, 2020
Arham Vatika project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

MahaRERA shows it completed

  • This projectRegistered 19 Aug 2017, completion promised 31 Jul 2018.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page. Construction % is the average of the developer's own declared activity progress to MahaRERA, not an inspection.

Regulatory record1

What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.

  • Suo motu order11 Feb 2020Matched by RERA number

    Suo motu order: Secretary, MahaRERA Versus Arham Enterprises (Suo Motu Case No. 44 of 2020) dated 10th February 2020

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700008943
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170000894319 Aug 201731 Jul 2018—Arham EnterprisesProject page
Documents27

13 documents held by Deedo, 14 filings listed on MahaRERA's project page

Title report

Encumbrance details

Form B

Form 1

Form 2

Registration certificate

Occupancy / completion certificate

  • Occupancy / completion certificate20 Jan 2020ViewSource

Other (3)

Show all 27 documentsShow fewer documents

Other (3)

Layout plan

Building plan

Allotment letter

Document library

  • Declaration in FORM BFrom -B-min.pdf · uploaded 30 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architec Certif.pdf · uploaded 30 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg Certif.pdf · uploaded 30 Jul 2017View
  • Details of encumbrancesEncumbrances Certfi.PDF · uploaded 30 Jul 2017View
  • Copy of the legal title reporttitle.pdf · uploaded 30 Jul 2017View
  • Copy of Layout Approval (in case of layout)plan copy.pdf · uploaded 30 Jul 2017View
  • Proforma of Allotment lettersales draft.pdf · uploaded 30 Jul 2017View
  • Building Plan Approval (IOD)CC.pdf · uploaded 30 Jul 2017View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCERTIFICATE OF COM.pdf · uploaded 20 Jan 2020View

Promoter documents

  • Declaration Form BFrom -B-min.pdf · uploaded 30 Jul 2017View
  • Legal Title reporttitle.pdf · uploaded 30 Jul 2017View

Technical documents

  • Building Plan ApprovalCC.pdfView
  • Layout Approvalplan copy.pdfView

Proforma allotment letter

  • Proforma allotment lettersales draft.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsS No.140 H. NO. 8A

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Address
S No.140 H. NO. 8APIN 421503
Village
Badlapur (M Cl), Ambarnath taluka
Land area for this project
1,600 sq m (17,222 sq ft)
Permissible built-up area
1,600 sq m (17,222 sq ft)
Sanctioned built-up area
1,600 sq m (17,222 sq ft)
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Survey, CTS, gat or plot numbers

S No.140 H. NO. 8A

Land as published on MahaRERA's project page

S No.140 H. NO. 8A

Boundaries

North
9 m w road
South
play ground
East
S No 8
West
kokan village

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking0 parking spaces

0 units registered

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
Arham Vatika R 1Closed/Covered00000
Arham Vatika R 1Open Space00000
Arham Vatika R 2Closed/Covered00000
Arham Vatika R 2Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress3 buildings and areas

Work completed, as the promoter reported it to MahaRERA (Form 1)

Arham Vatika R 1

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises20%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Arham Vatika R 2

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyIn Progress after Completion0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)In Progress no STP Only Septic Tank Provided0%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingIn Progress80%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsFinished100%
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Professionals1

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPramod V Patil—

Source: MahaRERA project page. Contact details are not shown.

Data through11 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project page · MahaRERA regulatory lists and ordersData through is when MahaRERA's project page was last read.Methodology