Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

Completed

P51700008943

Arham Vatika · Badlapur (M Cl), Thane · Arham Enterprises

Promised for 31 Jul 2018; MahaRERA reports the project completed.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: 1 other MahaRERA order names this registration.

Documents 13

Title report30 Jul 2017View
Encumbrance details30 Jul 2017View
Form B30 Jul 2017View
Form 130 Jul 2017View
Form 230 Jul 2017View
Registration certificate19 Aug 2017View
Occupancy / completion certificate20 Jan 2020View
OtherView
Show all 13 documents
OtherView
Layout planView
Building planView
Allotment letterView
OtherView

Orders 1

Suo motu order

Suo motu order: Secretary, MahaRERA Versus Arham Enterprises (Suo Motu Case No. 44 of 2020) dated 10th February 2020

11 Feb 2020 · matched by RERA number

View on MahaRERA

Questions about P51700008943

Is Arham Vatika delayed?

MahaRERA reports it completed. Its promised completion date was 31 Jul 2018.

How many extensions has it had?

Deedo holds 0 extension certificates for P51700008943.

Who is the promoter?

MahaRERA records Arham Enterprises as the promoter of P51700008943.

Is it on any MahaRERA regulatory list?

1 MahaRERA order or list names P51700008943.

Answers are generated from the record.

Data through22 Oct 2026, 01:46SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology