Promised date passed7 floorsRERA P51700014690
Wing - D, Deep Enclave
Deedo IDDP-THN-X6F4-DMahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked0%0 of 18 · MahaRERA
Completion30 Jun 2019as registered
Units & parking in Wing - D
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK | 28 m² (301 sq.ft) | 4 | 0 |
| 1 BHK | 28.1 m² (302 sq.ft) | 4 | 0 |
| 1 BHK | 28.6 m² (308 sq.ft) | 4 | 0 |
| SHOP | 6.1 m² (65 sq.ft) | 1 | 0 |
| SHOP | 9 m² (97 sq.ft) | 1 | 0 |
| SHOP | 9.1 m² (98 sq.ft) | 1 | 0 |
| SHOP | 9.6 m² (103 sq.ft) | 1 | 0 |
| SHOP | 10.1 m² (109 sq.ft) | 1 | 0 |
| SHOP | 12.2 m² (131 sq.ft) | 1 | 0 |
As registered with MahaRERA
- RERA registration
- P51700014690 · registered 26 Dec 2017
- Promised completion
- 30 Jun 2019
- Revised completion
- 30 Jun 2019
- Sanctioned habitable floors
- 7
- Sanctioned floors (incl. basement, stilt, podium)
- 7
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-THN-X6F4-D
Questions about Wing - D
When is Wing - D due for completion?
The MahaRERA registration promises 30 Jun 2019.
How many floors does Wing - D have?
7 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology