Skip to content
Others · 7 buildings · 154 unitsRERA P51700023796

Meera Park

Deedo IDDP-THN-3Q64

MahaRERA shows it completed, after its date was pushed back 1 year; no MahaRERA orders on record; 70% of its units are booked.

Ambarnath (R), Thane 421501 · by Saraswati Homes

DeliveryCompletedCompletion / occupancy certificate on MahaRERA · after a 1 yr extensionRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales70% booked108 of 154 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed, after its date was pushed back 1 year

  • This projectRegistered 6 Jan 2020, completion promised 30 Oct 2022, revised to 30 Oct 2023.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

7 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700023796
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P517000237966 Jan 202030 Oct 202230 Oct 2023M/S. Saraswati HomesProject page
Documents44

3 documents held by Deedo, 41 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardPAN CARD OF FIRM.pdf · uploaded 28 Dec 2019Source

Legal

  • Legal Title reportTITLE CERTIFICATE_compressed.pdf · uploaded 28 Dec 2019Source
  • Declaration Form BShri Munit Girdhari Lulla_compressed.pdf · uploaded 28 Dec 2019Source
  • OtherConsent_compressed.pdf · uploaded 11 Dec 2021Source

Migrated

  • 1 PAN CardPAN CARD OF FIRM.pdf · uploaded 28 Dec 2019Source
Show all 44 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reportTITLE CERTIFICATE_compressed.pdf · uploaded 28 Dec 2019Source
  • 1 Details of encumbrancesNOC.pdf · uploaded 28 Dec 2019Source
  • 1 Copy of Layout Approval (in case of layout)MYSCAN_20191107_0001-converted (1).pdf · uploaded 28 Dec 2019Source
  • 1 Building Plan Approval / NA Order for plotted developmentMYSCAN_20191107_0002.pdf · uploaded 28 Dec 2019Source
  • 2 Building Plan Approval / NA Order for plotted developmentMYSCAN_20191107_0003 (1).pdf · uploaded 28 Dec 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 28 Dec 2019Source
  • 1 Declaration in FORM BShri Munit Girdhari Lulla_compressed.pdf · uploaded 28 Dec 2019Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 (CA's Certificate) Saraswati Homes - Meera Park - Signed.pdf · uploaded 28 Dec 2019Source
  • 1 Proforma of Allotment letter22-11-2019 - Allotment Letter.pdf · uploaded 28 Dec 2019Source
  • 2 Proforma of Allotment letter22-11-2019 - Flat Sale Agreement.pdf · uploaded 28 Dec 2019Source
  • 1 OtherConsent_compressed.pdf · uploaded 11 Dec 2021Source
  • 1 Declaration about Commencement Certificate1 Request For Generation Of Revised Registration Certificate.pdf · uploaded 13 Dec 2021Source
  • 1 CERSAI details1 Details of encumbrances.pdf · uploaded 13 Dec 2021Source
  • 2 CERSAI detailsCERSAI_Search_Report-1.pdf · uploaded 17 Jan 2022Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 (CA's Certificate) Saraswati Homes - Meera Park.pdf · uploaded 17 Jan 2022Source
  • 2 Declaration about Commencement CertificateFormat D - Declaration_071236 pdf (1).pdf · uploaded 10 Feb 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1 compressed.pdf · uploaded 10 Feb 2022Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of Sold-Booked Inventory (Building Wise)_072039 pdf (1).pdf · uploaded 18 Feb 2022Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC.pdf · uploaded 7 Jul 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 5 Audit Report_Saraswati Homes 19-20.pdf · uploaded 20 Sep 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 Audit Report_Saraswati Homes 19-20.pdf · uploaded 20 Sep 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 Audit Report_Saraswati Homes 20-21.pdf · uploaded 20 Sep 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FY 2020-2021 C.pdf · uploaded 20 Oct 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 14 Nov 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FY 2021-2022 C.pdf · uploaded 14 Nov 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 - RERA Audit FY2021-22.pdf · uploaded 6 Mar 2023Source
  • 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentBuilding No 1 Completion_compressed.pdf · uploaded 6 Mar 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)RERA Form 5 Audit Report_Saraswati Homes FY 2022-23.pdf · uploaded 23 Nov 2023Source
  • 3 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentBuilding No 3 - Completion Certificate.pdf · uploaded 23 Nov 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A.pdf · uploaded 29 Nov 2023Source
  • 2 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD-UNSOLD-BOOKED INVENTORY (BUILDING WISE).pdf · uploaded 8 Dec 2023View
  • 12 Architect’s Certificate on Completion of Project (Form 4)Revised FORM 4.pdf · uploaded 8 Dec 2023Source

Technical

  • DocumentMYSCAN_20191107_0002.pdf · uploaded 28 Dec 2019Source
  • DocumentMYSCAN_20191107_0003 (1).pdf · uploaded 28 Dec 2019Source
  • DocumentMYSCAN_20191107_0001-converted (1).pdf · uploaded 28 Dec 2019Source

Technical (Architect)

  • DocumentForm 1.pdf · uploaded 14 Nov 2022Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel CTS NO. 9496, S. NO. 145/2

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, Shop, 1RK154 units in all
Address
S. No. 145/2, Cts No. 9496, S. No. 145/2, Cts No. 9496, AmbernathPIN 421501
Village
Ambarnath(M Cl), Ambarnath taluka
Land area for this project
5,010 sq m (53,927 sq ft)
Permissible built-up area
6,345 sq m (68,297 sq ft)
Sanctioned built-up area
6,345 sq m (68,297 sq ft)
Recreational open space
501 sq m (5,393 sq ft)
Designated bank account
109
Developed in phases
Yes

Survey, CTS, gat or plot numbers

CTS NO. 9496S. NO. 145/2

Land as published on MahaRERA's project page

S. NO. 145/2, CTS NO. 9496

Boundaries

North
Cts No 9495
South
Cts No 9497
East
Cts No 9495
West
Cts No 9494

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking154 units

108 of 154 units booked (70%), as the promoter reported to MahaRERA

1BHK · 82 units2BHK · 31 unitsShop · 40 units1RK · 1 unit
BuildingTypeCarpet areaUnitsBooked
Building 11BHK29.17 sq m · 314 sq ft11
Building 11BHK32.35 sq m · 348 sq ft43
Building 11BHK34.06 sq m · 367 sq ft44
Building 11BHK35.19 sq m · 379 sq ft33
Building 11BHK39.91 sq m · 430 sq ft11
Building 12BHK46.35 sq m · 499 sq ft22
Building 12BHK47.91 sq m · 516 sq ft55
Building 12BHK49.71 sq m · 535 sq ft11
Show all 51 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Building 1Shop9.9 sq m · 107 sq ft11
Building 1Shop11.82 sq m · 127 sq ft11
Building 1Shop12.37 sq m · 133 sq ft11
Building 1Shop12.92 sq m · 139 sq ft11
Building 1Shop13.27 sq m · 143 sq ft11
Building 1Shop16.27 sq m · 175 sq ft22
Building 21BHK31.83 sq m · 343 sq ft1816
Building 2Shop8.92 sq m · 96 sq ft21
Building 2Shop10.18 sq m · 110 sq ft21
Building 2Shop11.96 sq m · 129 sq ft10
Building 2Shop15.61 sq m · 168 sq ft11
Building 31BHK37.09 sq m · 399 sq ft40
Building 31BHK38.06 sq m · 410 sq ft50
Building 31BHK39.88 sq m · 429 sq ft10
Building 31RK22.75 sq m · 245 sq ft10
Building 32BHK46.43 sq m · 500 sq ft40
Building 32BHK52.33 sq m · 563 sq ft40
Building 3Shop8.68 sq m · 93 sq ft10
Building 3Shop10.07 sq m · 108 sq ft10
Building 3Shop10.6 sq m · 114 sq ft10
Building 3Shop11 sq m · 118 sq ft10
Building 3Shop11.52 sq m · 124 sq ft10
Building 3Shop11.6 sq m · 125 sq ft30
Building 3Shop13.92 sq m · 150 sq ft10
Building 3Shop18.41 sq m · 198 sq ft10
Building 51BHK31.83 sq m · 343 sq ft1816
Building 5Shop8.92 sq m · 96 sq ft21
Building 5Shop10.17 sq m · 109 sq ft21
Building 5Shop11.96 sq m · 129 sq ft10
Building 5Shop15.61 sq m · 168 sq ft11
Building 61BHK31.83 sq m · 343 sq ft1816
Building 6Shop8.92 sq m · 96 sq ft21
Building 6Shop10.18 sq m · 110 sq ft22
Building 6Shop11.96 sq m · 129 sq ft10
Building 6Shop15.61 sq m · 168 sq ft11
Building 71BHK32.24 sq m · 347 sq ft55
Building 72BHK42.74 sq m · 460 sq ft108
Building 72BHK45.38 sq m · 488 sq ft55
Building 7Shop8.03 sq m · 86 sq ft11
Building 7Shop20.25 sq m · 218 sq ft11
Building 7Shop25.21 sq m · 271 sq ft11
Building 7Shop25.22 sq m · 271 sq ft11
Building 7Shop27 sq m · 291 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
Architectpramod kamble—
Chartered accountantVrp & Associates—
EngineerRajendra S Kundekar—
OtherKajal Enterprises—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Ambarnath (R)

All 248 projects in Ambarnath (R) · Compare Meera Park with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology