Deedo IDDP-SOL-N1SGMahaRERA shows it completed; no MahaRERA orders on record; 0% of its units are booked.
Pandharpur, Solapur 413304 · by Ashwini Facility Creators Llp
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed
- This projectRegistered 1 Apr 2023, completion promised 31 Dec 2025.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52600050305
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52600050305 | 1 Apr 2023 | 31 Dec 2025 | 31 Dec 2025 | Ashwini Facility Creators LLP | Project page |
Documents66
2 documents held by Deedo, 64 filings listed on MahaRERA's project page
Show all 66 documentsShow fewer documents
Migrated
- 1 b Details of encumbrances concerned to Legal04 Encumberances Certificate Financial.pdf · uploaded 21 Feb 2023Source
- 1 Copy of Layout Approval (in case of layout)05 Copy of layout apooval.pdf · uploaded 21 Feb 2023Source
- 1 Building Plan Approval / NA Order for plotted development06 Building plan Aprooval.pdf · uploaded 21 Feb 2023Source
- 1 Commencement Certificates / NA Order for plotted development07 CC- Certificate.pdf · uploaded 21 Feb 2023Source
- 1 Declaration about Commencement Certificate08 Declaration about commencement.pdf · uploaded 21 Feb 2023Source
- 1 Declaration in FORM B09 Form B.pdf · uploaded 21 Feb 2023Source
- 1 CERSAI details18 CERSAI Declaration2_compressed.pdf · uploaded 21 Feb 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of interest.pdf · uploaded 21 Feb 2023Source
- 1 Proforma of Allotment letter15 Allotment Letter.pdf · uploaded 21 Feb 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the same35 Delaration of Separate Bank Account.pdf · uploaded 21 Feb 2023Source
- 2 a Details of encumbrances concerned to Finance03 Encumberances Certificate Leagal.pdf · uploaded 27 Feb 2023Source
- 2 b Details of encumbrances concerned to Legal03 Encumberances Certificate Leagal.pdf · uploaded 27 Feb 2023Source
- 1 Proforma of Agreement for sale16 Model_AFS_in_English.pdf · uploaded 27 Feb 2023Source
- 1 Deviation Report with respect to Allotment letter34 Deviation in Allotment Letter 1.pdf · uploaded 13 Mar 2023Source
- 1 Deviation Report with respect to model copy of Agreement33 Deviation in Agreement to Sale 1.pdf · uploaded 13 Mar 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)19 CA Certificate for RERA 2.pdf · uploaded 24 Mar 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 18 Jan 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 18 Jan 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 18 Jan 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 18 Jan 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 18 Jan 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 18 Jan 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 18 Jan 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 18 Jan 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 18 Jan 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 1 Jun 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 1 Jun 2024Source
- 1 Disclosure of sold/ booked inventoryDisclosure of sold ,Booked Inventory.pdf · uploaded 1 Jun 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 1 Jun 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 20 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 20 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 20 Oct 2024Source
- 1 Disclosure of sold/ booked inventoryDisclosure of Sold or Booked Inventory.pdf · uploaded 20 Oct 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 17 Nov 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 17 Nov 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 17 Nov 2024Source
- 2 Disclosure of sold/ booked inventoryInventory disclosure.pdf · uploaded 17 Nov 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 30 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5 Kothadiya sir and Partner Signature.pdf · uploaded 30 Nov 2024Source
- Occupational CertificateOC.pdf · uploaded 3 Jun 2025Source
- Form 1Form 1.pdf · uploaded 5 Jun 2025Source
- Form 2Form 2.pdf · uploaded 5 Jun 2025Source
- Form 3Form 3.pdf · uploaded 5 Jun 2025Source
- Disclosure of Sold and Booked InventoryInventory Disclosure.pdf · uploaded 5 Jun 2025View
- Self-declaration of Quarterly ProgressSelf_Declaration_Q424-25.pdf · uploaded 5 Jun 2025Source
- Form 1Form 1.pdf · uploaded 5 Jun 2025Source
- Form 2Form 2.pdf · uploaded 5 Jun 2025Source
- Form 3Form 3.pdf · uploaded 5 Jun 2025Source
- Disclosure of Sold and Booked InventoryInventory Disclosure.pdf · uploaded 5 Jun 2025View
- Self-declaration of Quarterly ProgressSelf_Declaration_Q424-25.pdf · uploaded 5 Jun 2025Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 4776/13
As registered with MahaRERA and published on its project page
- Project type
- Commercial
- Status on MahaRERA
- Certificate Signed
- Unit types
- hall, Shop52 units in all
- Address
- 4776/13, Link Road, Near New Karad NakaPIN 413304
- Village
- Pandharpur, Pandharpur taluka
- Location
- 17.65992, 75.90639
- Land area for this project
- 843 sq m (9,074 sq ft)
- Permissible built-up area
- 2,959 sq m (31,850 sq ft)
- Sanctioned built-up area
- 2,109 sq m (22,701 sq ft)
- Designated bank account
- 35
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
4776/13
Boundaries
- North
- 9 meter wide road
- South
- Plot no 4512
- East
- Plot no 14
- West
- 24 meter wide road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking52 units
0 of 52 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| hall | 145.35 sq m · 1,565 sq ft | 1 | 0 |
| Shop | 21.78 sq m · 234 sq ft | 1 | 0 |
| Shop | 22.15 sq m · 238 sq ft | 1 | 0 |
| Shop | 22.15 sq m · 238 sq ft | 3 | 0 |
| Shop | 22.16 sq m · 239 sq ft | 1 | 0 |
| Shop | 22.27 sq m · 240 sq ft | 12 | 0 |
| Shop | 22.27 sq m · 240 sq ft | 4 | 0 |
| Shop | 22.39 sq m · 241 sq ft | 3 | 0 |
Show all 19 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Shop | 22.39 sq m · 241 sq ft | 1 | 0 |
| Shop | 22.46 sq m · 242 sq ft | 2 | 0 |
| Shop | 22.77 sq m · 245 sq ft | 1 | 0 |
| Shop | 22.81 sq m · 246 sq ft | 3 | 0 |
| Shop | 25.08 sq m · 270 sq ft | 3 | 0 |
| Shop | 25.52 sq m · 275 sq ft | 3 | 0 |
| Shop | 25.65 sq m · 276 sq ft | 3 | 0 |
| Shop | 25.78 sq m · 277 sq ft | 3 | 0 |
| Shop | 32.67 sq m · 352 sq ft | 3 | 0 |
| Shop | 40.85 sq m · 440 sq ft | 3 | 0 |
| Shop | 45.96 sq m · 495 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals5
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Sachin Dingare | — |
| Chartered accountant | Sanjieev S Kothadia & company | — |
| Chartered accountant | Vaibhav Narayan Kambale | — |
| Engineer | Satish Nagbhushan Sarfkatte | — |
| Other | Rajkumar Mane | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Pandharpur
- Omkar RegencyRERA PM1320002602281
- Tirupati HarishaRERA PR1320002501713
- Tirupati Puram IIRERA PR1320002501514
- Mahesh ComplexRERA PC1320002500410
- Raghuraj PrideRERA P52600080721
- Unique ResidencyRERA P52600079735
- Construction of 224 LIG Residential T/S on Land Bearing Survey No 25A/1 Pandharpur Dist SolapurRERA P52600076940
- Tirupati PuramRERA P52600055784
All 32 projects in Pandharpur · Compare Jaydev Heights with another project