MahaRERA shows it completed; no MahaRERA orders on record.

Shendurjane, Satara 412803 · by Venus Properties

DeliveryCompletedCompletion / occupancy certificate on MahaRERARegulatoryNo ordersNot in any MahaRERA list or order Deedo has read

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed

  • P52100004984Registered 9 Aug 2017, completion promised 15 Feb 2021.
  • P52700016269Registered 2 May 2018, completion promised 15 Aug 2024.

No extension certificate on record.

2 registrations · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.
Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrations2
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000049849 Aug 201715 Feb 202115 Feb 2021Venus PropertiesProject page
P527000162692 May 201815 Aug 202415 Aug 2024Venus PropertiesProject page
Documents40

2 documents held by Deedo, 38 filings listed on MahaRERA's project page

Registration certificate (2)

  • Registration certificateP52100004984 · 18 May 2020ViewSource
  • Registration certificateP52700016269 · 9 Sep 2021ViewSource

Finance

  • PAN CardP52100004984 · PAN Card.pdf · uploaded 24 Jul 2017Source
  • PAN CardP52700016269 · PAN Card.pdf · uploaded 20 Apr 2018Source

Legal

  • Legal Title reportP52100004984 · TSR Goldmine.pdf · uploaded 24 Jul 2017Source
  • Declaration Form BP52100004984 · Form B Goldmine.pdf · uploaded 29 Jul 2017Source
  • Legal Title reportP52700016269 · TSR Goldmine.pdf · uploaded 20 Apr 2018Source
  • Declaration Form BP52700016269 · Self Declaration II.pdf · uploaded 21 Apr 2018Source
Show all 40 documentsShow fewer documents

Migrated

  • 1 PAN CardP52100004984 · PAN Card.pdf · uploaded 24 Jul 2017Source
  • 1 Copy of the legal title reportP52100004984 · TSR Goldmine.pdf · uploaded 24 Jul 2017Source
  • 1 Details of encumbrancesP52100004984 · Encumbarance Certificate - Goldmine.pdf · uploaded 24 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)P52100004984 · Layout Goldmine.pdf · uploaded 24 Jul 2017Source
  • 1 Proforma of Allotment letterP52100004984 · Draft Agreement.pdf · uploaded 24 Jul 2017Source
  • 1 Building Plan Approval (IOD)P52100004984 · Layout Goldmine.pdf · uploaded 28 Jul 2017Source
  • 1 Declaration in FORM BP52100004984 · Form B Goldmine.pdf · uploaded 29 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100004984 · Architect Certificate Goldmine PH-I.pdf · uploaded 29 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100004984 · Engineers Certificate Goldmine.pdf · uploaded 29 Jul 2017Source
  • 1 Certificates of CA (Form 3)P52100004984 · CA Cert 1MB Goldmine.pdf · uploaded 29 Jul 2017Source
  • 1 PAN CardP52700016269 · PAN Card.pdf · uploaded 20 Apr 2018Source
  • 1 Copy of the legal title reportP52700016269 · TSR Goldmine.pdf · uploaded 20 Apr 2018Source
  • 1 Details of encumbrancesP52700016269 · Encumbarance Certificate - Goldmine.pdf · uploaded 20 Apr 2018Source
  • 1 Proforma of Allotment letterP52700016269 · Draft Agreement.pdf · uploaded 20 Apr 2018Source
  • 1 Declaration in FORM BP52700016269 · Self Declaration II.pdf · uploaded 21 Apr 2018Source
  • 1 Certificates of CA (Form 3)P52700016269 · CA Certificate - Goldmine II .pdf · uploaded 23 Apr 2018Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100004984 · NA Order - Goldmine Wai.pdf · uploaded 26 Apr 2018Source
  • 1 Copy of Layout Approval (in case of layout)P52700016269 · Layout - Goldmine b2 .pdf · uploaded 26 Apr 2018Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52700016269 · NA Order - Goldmine Wai.pdf · uploaded 26 Apr 2018Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)P52100004984 · Society Registration Cert - Goldmine.pdf · uploaded 25 Jul 2019Source
  • 1 Building Plan Approval (IOD)P52700016269 · Layout - Goldmine b2 .pdf · uploaded 25 Jul 2019Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)P52700016269 · Society Registration Cert - Goldmine.pdf · uploaded 25 Jul 2019Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100004984 · Form 1 Goldmine .pdf · uploaded 14 Aug 2020Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)P52100004984 · Form 4 Goldmine .pdf · uploaded 14 Aug 2020Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52700016269 · Form 1 Goldmine 2.pdf · uploaded 14 Aug 2020Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)P52700016269 · Form 4 Goldmine 2.pdf · uploaded 14 Aug 2020Source

Technical

  • DocumentP52100004984 · Layout Goldmine.pdf · uploaded 24 Jul 2017Source
  • DocumentP52100004984 · Layout Goldmine.pdf · uploaded 28 Jul 2017Source
  • DocumentP52700016269 · Layout - Goldmine b2 .pdf · uploaded 26 Apr 2018Source
  • DocumentP52700016269 · Layout - Goldmine b2 .pdf · uploaded 25 Jul 2019Source

Technical (Architect)

  • DocumentP52100004984 · Architect Certificate Goldmine PH-I.pdf · uploaded 29 Jul 2017Source

Technical (Engineer)

  • DocumentP52100004984 · Engineers Certificate Goldmine.pdf · uploaded 29 Jul 2017Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 593/B, 593/C

As registered with MahaRERA and published on its project page

Project type
Plotted
Status on MahaRERA
Certificate Signed
Phases
2
Address
Gat No. 593/A, 593/B and 593/C, Village Shendurjane, Tal. Wai Dist SataraPIN 412803
Village
Shendurjane, Wai taluka
Land area for this project
19,341 sq m (2,08,189 sq ft)
Permissible built-up area
0 sq m (0 sq ft)
Sanctioned built-up area
0 sq m (0 sq ft)
Designated bank account
220
Developed in phases
No
Also registered as
Goldmine II

Survey, CTS, gat or plot numbers

593/B593/CGat No. 593/A

Land as published on MahaRERA's project page

Gat No. 593/A, 593/B and 593/C, Village Shendurjane, Tal. Wai Dist Satara

Boundaries

North
Gat No 599 600 601
South
30 Mt Road
East
Gat No 592 591 590 589 588
West
30 Mt Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals2

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.RERA
ArchitectMr Shrikant Anpat—P52700016269
ArchitectStudio Collaborative—P52100004984

Source: MahaRERA project page. Contact details are not shown.