Skip to content
Promised date passed5 floorsRERA P52700001440

Building B, Ayodhya Park

Deedo IDDP-SAT-6N58-B

MahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.

All of Ayodhya Park
Median saleNot on recordneeds 3 or more sales
Booked100%56 of 56 · MahaRERA
Completion30 Dec 2021as registered
Units & parking in Building B
TypeCarpet areaUnitsBooked
1 BHK36.9 m² (397 sq.ft)44
1 BHK37.3 m² (402 sq.ft)44
1 BHK37.3 m² (402 sq.ft)88
1 BHK37.3 m² (402 sq.ft)44
1 BHK37.4 m² (402 sq.ft)44
1 BHK37.4 m² (402 sq.ft)88
1 BHK37.4 m² (402 sq.ft)44
1 BHK37.4 m² (402 sq.ft)44
1 BHK37.4 m² (403 sq.ft)44
1 BHK37.4 m² (403 sq.ft)44
1 BHK37.5 m² (403 sq.ft)44
1 RK25.3 m² (272 sq.ft)44
As registered with MahaRERA
RERA registration
P52700001440 · registered 28 Jul 2017
Promised completion
30 Dec 2021
Revised completion
30 Dec 2021
Sanctioned habitable floors
5
Sanctioned floors (incl. basement, stilt, podium)
5
Units declared
0
Homes
0
Shops and offices
0
MahaRERA status
Certificate Signed
Deedo ID
DP-SAT-6N58-B
Questions about Building B

When is Building B due for completion?

The MahaRERA registration promises 30 Dec 2021.

How many floors does Building B have?

5 sanctioned habitable floors, as registered with MahaRERA.

Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology