Mane Heights
Deedo IDDP-SAT-X38WCompletion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 32% of its units are booked.
Kodoli (Ct), Satara 415004 · by Varad Builders And Promoters
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2029
- This projectRegistered 11 Jun 2024, completion promised 31 Dec 2028, revised to 30 Apr 2029.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52700066521
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52700066521 | 11 Jun 2024 | 31 Dec 2028 | 30 Apr 2029 | Varad Builders And Promoters | Project page |
Documents88
1 document held by Deedo, 87 filings listed on MahaRERA's project page
Finance
- PAN Card1 PAN Card.pdf · uploaded 22 Mar 2024Source
Legal
Migrated
- 1 PAN Card1 PAN Card.pdf · uploaded 22 Mar 2024Source
- 1 Copy of the legal title reportSEARCH.PDF · uploaded 22 Mar 2024Source
- 1 a Details of encumbrances concerned to FinanceENCUMBRANCE.PDF · uploaded 22 Mar 2024Source
- 1 b Details of encumbrances concerned to LegalENCUMBRANCE.PDF · uploaded 22 Mar 2024Source
Show all 88 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)DRG 1.pdf · uploaded 22 Mar 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentDRG 2.pdf · uploaded 22 Mar 2024Source
- 2 Building Plan Approval / NA Order for plotted developmentDRG 1.pdf · uploaded 22 Mar 2024Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.PDF · uploaded 22 Mar 2024Source
- 1 Declaration in FORM BFORM B PROMOTER.PDF · uploaded 22 Mar 2024Source
- 1 CERSAI detailsCERSAI.PDF · uploaded 22 Mar 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA.pdf · uploaded 22 Mar 2024Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsINTEREST.PDF · uploaded 22 Mar 2024Source
- 1 Proforma of Allotment letterALLOTMENT LETTRE.PDF · uploaded 22 Mar 2024Source
- 1 Proforma of Agreement for salemodel form of agreement jv BLANK.pdf · uploaded 22 Mar 2024Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBANK.PDF · uploaded 22 Mar 2024Source
- 1 Deviation Report with respect to Allotment letterDEV ALLOTMENT.PDF · uploaded 22 Mar 2024Source
- 1 Deviation Report with respect to model copy of AgreementDEV AGREEMENT.PDF · uploaded 22 Mar 2024Source
- 1 Other – TechnicalANNEXTURE A.PDF · uploaded 22 Mar 2024Source
- 2 Commencement Certificates / NA Order for plotted developmentCC MAIL.pdf · uploaded 2 May 2024Source
- 1 Declaration about Commencement CertificateDEC CC.PDF · uploaded 2 May 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 21 Dec 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 FINAL.pdf · uploaded 21 Dec 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 SIGNED.pdf · uploaded 21 Dec 2024Source
- 1 Disclosure of sold/ booked inventorySOLD INVENTORY PDF.pdf · uploaded 21 Dec 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 27 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3_.pdf · uploaded 27 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2.pdf · uploaded 27 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 23 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 23 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 23 Apr 2025Source
- Form 1FORM 1.pdf · uploaded 28 Jul 2025Source
- Form 2FORM 2.pdf · uploaded 28 Jul 2025Source
- Form 3FORM 3.pdf · uploaded 28 Jul 2025Source
- Disclosure of Sold and Booked InventoryDISCLOSURE OF SOLD UNSOLD INVENTORY.pdf · uploaded 28 Jul 2025Source
- Form 1FORM 1.pdf · uploaded 29 Jul 2025Source
- Form 2FORM-2.pdf · uploaded 29 Jul 2025Source
- Form 3FORM 3.pdf · uploaded 29 Jul 2025Source
- Disclosure of Sold and Booked InventoryDISCLOSURE OF SOLD UNSOLD INVENTORY.pdf · uploaded 29 Jul 2025Source
- Form 1FORM 1.pdf · uploaded 29 Jul 2025Source
- Form 2FORM 2.pdf · uploaded 29 Jul 2025Source
- Form 3FORM 3.pdf · uploaded 29 Jul 2025Source
- Disclosure of Sold and Booked InventoryDISCLOSURE OF SOLD UNSOLD INVENTORY.pdf · uploaded 29 Jul 2025Source
- Form 1FORM 1.pdf · uploaded 25 Aug 2025Source
- Form 2FORM 2.pdf · uploaded 25 Aug 2025Source
- Form 3FORM 3.pdf · uploaded 25 Aug 2025Source
- Disclosure of Sold and Booked InventoryDISCLOSURE OF SOLD UNSOLD INVENTORY.pdf · uploaded 25 Aug 2025Source
- Withdrawal Update Form 1FORM 1.pdf · uploaded 17 Sep 2025Source
- Withdrawal Update Form 2FORM 2.pdf · uploaded 17 Sep 2025Source
- Withdrawal Update Form 3Form 3_.pdf · uploaded 17 Sep 2025Source
- Withdrawal Update Form 1FORM 1.pdf · uploaded 6 Nov 2025Source
- Withdrawal Update Form 1FORM 1.pdf · uploaded 6 Nov 2025Source
- Withdrawal Update Form 2FORM 2.pdf · uploaded 6 Nov 2025Source
- Withdrawal Update Form 2FORM 2.pdf · uploaded 6 Nov 2025Source
- Withdrawal Update Form 3Form 3_.pdf · uploaded 6 Nov 2025Source
- Withdrawal Update Form 3Form 3_.pdf · uploaded 6 Nov 2025Source
- Withdrawal Update Form 1FORM 1.pdf · uploaded 19 Nov 2025Source
- Withdrawal Update Form 2FORM 2.pdf · uploaded 19 Nov 2025Source
- Withdrawal Update Form 3FORM 3.pdf · uploaded 19 Nov 2025Source
- Form 5 (FY 2024-2025)Form 5_.pdf · uploaded 3 Jan 2026Source
- Withdrawal Update Form 1FORM 1.pdf · uploaded 13 Feb 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 13 Feb 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 13 Feb 2026Source
- Withdrawal Update Form 11. FORM 1..pdf · uploaded 29 Apr 2026Source
- Withdrawal Update Form 11. FORM 1..pdf · uploaded 29 Apr 2026Source
- Withdrawal Update Form 2FORM 2.pdf · uploaded 29 Apr 2026Source
- Withdrawal Update Form 2FORM 2.pdf · uploaded 29 Apr 2026Source
- Withdrawal Update Form 3FORM 3.pdf · uploaded 29 Apr 2026Source
- Withdrawal Update Form 3FORM 3.pdf · uploaded 29 Apr 2026Source
- Withdrawal Update Form 1FORM 1.pdf · uploaded 5 Aug 2026Source
- Withdrawal Update Form 1FORM 1.pdf · uploaded 5 Aug 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 5 Aug 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 5 Aug 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 5 Aug 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 5 Aug 2026Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 2, PLOT NO 1
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, LAND OWNER 1 BHK, LAND OWNER 1BHK, LAND OWNER 2 BHK, Land owner shop, Shop31 units in all
- Address
- Plot No 1 & 2, S No 339/4/C/3/B, Kodoli, KodoliPIN 415004
- Village
- Kodoli (CT), Satara taluka
- Location
- 17.66951, 74.03377
- Land area for this project
- 883 sq m (9,509 sq ft)
- Permissible built-up area
- 2,177 sq m (23,432 sq ft)
- Sanctioned built-up area
- 1,977 sq m (21,279 sq ft)
- Designated bank account
- 171
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
PLOT NO 1 & 2, S NO 339/4/C/3/B
Boundaries
- North
- By Road
- South
- S No 363 4
- East
- By Road
- West
- Plot No 3
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking31 units
10 of 31 units booked (32%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 36.96 sq m · 398 sq ft | 4 | 2 |
| 1BHK | 38.84 sq m · 418 sq ft | 1 | 1 |
| 1BHK | 39.12 sq m · 421 sq ft | 2 | 0 |
| 1BHK | 41.98 sq m · 452 sq ft | 3 | 3 |
| 1BHK | 47.56 sq m · 512 sq ft | 1 | 1 |
| 2BHK | 48.17 sq m · 518 sq ft | 2 | 2 |
| 2BHK | 50.94 sq m · 548 sq ft | 1 | 0 |
| 2BHK | 52.76 sq m · 568 sq ft | 3 | 1 |
Show all 19 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| LAND OWNER 1 BHK | 36.5 sq m · 393 sq ft | 1 | 0 |
| LAND OWNER 1 BHK | 39.13 sq m · 421 sq ft | 1 | 0 |
| LAND OWNER 1 BHK | 47.2 sq m · 508 sq ft | 1 | 0 |
| LAND OWNER 1 BHK | 50.24 sq m · 541 sq ft | 1 | 0 |
| LAND OWNER 1 BHK | 58.44 sq m · 629 sq ft | 1 | 0 |
| LAND OWNER 1BHK | 41.98 sq m · 452 sq ft | 1 | 0 |
| LAND OWNER 2 BHK | 52.76 sq m · 568 sq ft | 1 | 0 |
| LAND OWNER 2 BHK | 64.91 sq m · 699 sq ft | 1 | 0 |
| Land owner shop | 26.38 sq m · 284 sq ft | 2 | 0 |
| Shop | 24.89 sq m · 268 sq ft | 2 | 0 |
| Shop | 28.93 sq m · 311 sq ft | 2 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals6
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Mr Suhas S Talekar | — |
| Architect | Shankar Kumbhar | — |
| Chartered accountant | Harshvardhan Jaideep Jadhav | — |
| Chartered accountant | Mr Jivan Jagtap | — |
| Engineer | Mr Mangesh Avinash Lawand | — |
| Engineer | Shambhuraj Satish Patil | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Kodoli (Ct)
- Nisarg Residency Phase 1RERA PR1300002602718
- Asian TowerRERA PC1300002602624
- Girishwar ParkRERA PR1300002602514
- Radhakrushna EmpireRERA PR1300002601599
- Viraj ParkRERA PR1300002600540
- Indu EliteRERA PR1300002600068
- ShivsaiRERA PR1300002502841
- Narayan VishwaRERA PR1300002501023
All 42 projects in Kodoli (Ct) · Compare Mane Heights with another project