Varad Builders And Promoters
Deedo IDDD-Y5KTOf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 17 mo late.
Delivery record
4 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Siddhali GardenP52700023020 | Godoli (Ct) | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | +59 mo* |
| Sai Prasad ParkP52700025436 | Godoli (Ct) | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | +29 mo* |
| Kirdat ParkP52700048387 | Karanje Tarf Satara (Ct) | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 mo |
| Mane HeightsP52700066521 | Kodoli (Ct) | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
Varad Builders And Promoters, in questions
Does Varad Builders And Promoters finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 17 mo late. Across Maharashtra, 73% kept their date.
How many projects has Varad Builders And Promoters registered with MahaRERA?
4 projects under 4 MahaRERA registrations; 0 completed on MahaRERA.
Does Varad Builders And Promoters have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.