Company or firm · first RERA registration 2019

Varad Builders And Promoters

Deedo IDDD-Y5KT

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 17 mo late.

Projects44 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay17 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

4 of 4 registrations with dates moved or missed their RERA date · months late against the original promise

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Siddhali GardenP52700023020Godoli (Ct)Certificate Signed30 Dec 202130 Dec 2021+59 mo*
Sai Prasad ParkP52700025436Godoli (Ct)Certificate Signed30 Jun 202430 Jun 2024+29 mo*
Kirdat ParkP52700048387Karanje Tarf Satara (Ct)Certificate Signed31 Dec 203030 Apr 2031+4 mo
Mane HeightsP52700066521Kodoli (Ct)Certificate Signed31 Dec 202830 Apr 2029+4 mo

Varad Builders And Promoters, in questions

Does Varad Builders And Promoters finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 17 mo late. Across Maharashtra, 73% kept their date.

How many projects has Varad Builders And Promoters registered with MahaRERA?

4 projects under 4 MahaRERA registrations; 0 completed on MahaRERA.

Does Varad Builders And Promoters have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology