RERA projects in Karad (M Cl)
39 projects under 39 MahaRERA registrations, registered 2017–2026. 41% have a completion date extended beyond the one promised.
Locality
39RERA projects
39Registrations
18Completion still due21 past their completion date
4 monthsMedian extension beyond promised date41% of registrations extended
0Regulatory casesnone on MahaRERA's lists
58Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 3 |
| 2018 | 9 |
| 2019 | 4 |
| 2020 | 4 |
| 2021 | 1 |
| 2022 | 1 |
| 2023 | 6 |
| 2024 | 5 |
| 2025 | 1 |
| 2026 | 5 |
Projects in Karad (M Cl)
39 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Mauli ResidencyM/S Mauli Builders And Developers | P52700019846 | 5 Mar 2019 | 30 Dec 2023 | 30 Dec 2023 | Promised date passed | 0 |
| Jal SrushtiKarad City Enterprise Private Limited | P52700019323 | 23 Jan 2019 | 30 Oct 2023 | 30 Oct 2024 | Extended 12 mo | 0 |
| Sumangal PrideSandeep Sudhakar Kodgule | P52700018807 | 5 Dec 2018 | 30 Apr 2022 | 29 Apr 2023 | Extended 12 mo | 0 |
| Shubhashree PrasadShubhashree Infrastructure | P52700018770 | 4 Dec 2018 | 30 Oct 2022 | 30 Oct 2022 | Promised date passed | 0 |
| SaradaSarada Builders And Developers | P52700018666 | 22 Nov 2018 | 30 Dec 2021 | 30 Dec 2021 | Promised date passed | 0 |
| Devraj HeritageDevraj Developers | P52700018348 | 24 Oct 2018 | 30 Oct 2022 | 30 Oct 2022 | Promised date passed | 0 |
| Sunrise VilleDinesh Vilas Chakke | P52700017048 | 4 Jul 2018 | 30 May 2022 | 30 May 2022 | Promised date passed | 0 |
| Shivtirth HeightsChavan Shinde Developers | P52700015566 | 8 Mar 2018 | 1 Jan 2022 | 1 Jan 2022 | Promised date passed | 0 |
| Laxmi Madhav Tread CenterLaxmi Constructions | P52700015366 | 20 Feb 2018 | 30 Dec 2022 | 30 Dec 2022 | Promised date passed | 0 |
| Pearl ResidencyS J Construction | P52700015283 | 12 Feb 2018 | 30 Dec 2025 | 30 Dec 2025 | Promised date passed | 0 |
| Shubhashree PrideShubhashree Infrastructure | P52700014996 | 22 Jan 2018 | 30 Sep 2018 | 30 Sep 2018 | Promised date passed | 0 |
| M R ComplexM R Construction | P52700011129 | 31 Aug 2017 | 25 May 2019 | 25 May 2019 | Promised date passed | 0 |
| Pandurang SankulDesaibrothers | P52700011348 | 31 Aug 2017 | 31 Dec 2019 | 31 Dec 2019 | Promised date passed | 0 |
| Nirmiti Mundekar PlazaNirmiti Builders | P52700007158 | 17 Aug 2017 | 31 Jan 2021 | 31 Jul 2022 | Extended 18 mo | 0 |
Other localities in Karad
Most active promoters
By projects registered here, as named on MahaRERA.
- Sarada Landmark Private Limited3 projects
- Ajantadevelopers2 projects
- Laxmi Constructions2 projects
- Shubhashree Infrastructure2 projects
- Ashish Ananadrao Thorat1 project
- Bandenawaz Mohamad Mulla1 project
- Belapure Developers1 project
- Brico Builders1 project
- Chavan Shinde Developers1 project
- Desaibrothers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology