Its promised completion date, Mar 2023, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.

Uran Islampur (M Cl), Sangli 415409 · by Megha Manohar Kamerikar

Delivery3 yrs 8 mo past duePromised Mar 2023 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 14 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Mar 2023, has passed and MahaRERA does not show it completed

  • This projectRegistered 3 Feb 2022, completion promised 30 Mar 2023, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP53100033018
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P531000330183 Feb 202230 Mar 202330 Mar 2023Megha Manohar KamerikarProject page
Documents17

1 document held by Deedo, 16 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Cardpan card.pdf · uploaded 28 Jan 2022Source

Legal

  • Legal Title reportsearch title report.pdf · uploaded 28 Jan 2022Source
  • Declaration Form Bform b affidavit cum declaration.pdf · uploaded 28 Jan 2022Source

Migrated

  • 1 PAN Cardpan card.pdf · uploaded 28 Jan 2022Source
  • 1 Copy of the legal title reportsearch title report.pdf · uploaded 28 Jan 2022Source
  • 1 Details of encumbrancescertificate.pdf · uploaded 28 Jan 2022Source
  • 1 Copy of Layout Approval (in case of layout)nakashta11.pdf · uploaded 28 Jan 2022Source
Show all 17 documentsShow fewer documents

Migrated

  • 1 Building Plan Approval / NA Order for plotted developmentdwg.pdf · uploaded 28 Jan 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentsanction of building permission certificate.pdf · uploaded 28 Jan 2022Source
  • 1 Declaration about Commencement CertificateDCC.pdf · uploaded 28 Jan 2022Source
  • 1 Declaration in FORM Bform b affidavit cum declaration.pdf · uploaded 28 Jan 2022Source
  • 1 CERSAI detailsCERSAI.pdf · uploaded 28 Jan 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)c a certificate.pdf · uploaded 28 Jan 2022Source
  • 1 Proforma of Allotment letteragreement of sale of residential flat premises on ownership basis.pdf · uploaded 28 Jan 2022Source

Technical

  • Documentdwg.pdf · uploaded 28 Jan 2022Source
  • Documentnakashta11.pdf · uploaded 28 Jan 2022Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel S. NO. 98 P. NO. 7 B

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1RK, Office space, Shop14 units in all
Address
S. No. 98 P. No. 7 B, Peth Sangli Road, Near Pertol PumpPIN 415409
Village
Uran Islampur (M Cl), Walwa taluka
Land area for this project
402 sq m (4,322 sq ft)
Permissible built-up area
469 sq m (5,046 sq ft)
Sanctioned built-up area
469 sq m (5,046 sq ft)
Designated bank account
116
Developed in phases
No

Survey, CTS, gat or plot numbers

S. NO. 98 P. NO. 7 B

Land as published on MahaRERA's project page

S. NO. 98 P. NO. 7 B

Boundaries

North
S No 98 Land
South
Peth Sangli Road
East
30m Wide Dp Road
West
Plot No 7a

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking14 units

0 of 14 units booked (0%), as the promoter reported to MahaRERA

1BHK · 1 unit1RK · 1 unitOffice space · 2 unitsShop · 10 units
TypeCarpet areaUnitsBooked
1BHK46.98 sq m · 506 sq ft10
1RK44.47 sq m · 479 sq ft10
Office space49.65 sq m · 534 sq ft10
Office space51.24 sq m · 552 sq ft10
Shop10.91 sq m · 117 sq ft10
Shop11.53 sq m · 124 sq ft10
Shop12.58 sq m · 135 sq ft10
Shop13.1 sq m · 141 sq ft20
Show all 11 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Shop13.2 sq m · 142 sq ft30
Shop13.85 sq m · 149 sq ft10
Shop13.92 sq m · 150 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectRanjit Deepak Nerlekar—
Chartered accountantNityanand Kulkarni—
EngineerKunal Nejdar—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology