RegisteredExtendedMahaRERA status: Certificate Signed

P52100032655

Tower - One 52 · Hadapsar, Pune · Anu Constructions

Promised for 20 Dec 2027, extended to 20 Apr 2028, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 20 Dec 2027 to 20 Apr 2028.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate17 Jan 2022View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P52100032655

Is Tower - One 52 delayed?

Its completion moved from 20 Dec 2027 to 20 Apr 2028; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P52100032655. The completion date moved from 20 Dec 2027 to 20 Apr 2028.

Who is the promoter?

MahaRERA records Anu Constructions as the promoter of P52100032655.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100032655.

Answers are generated from the record.

Data through23 Nov 2026, 01:47SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology