Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

Completed1 extension

P52100031662

Rahul Eastview II - Wing D and E · Hadapsar, Pune · Rahul Constructions

Promised for 15 Apr 2023; MahaRERA reports the project completed.

The revised date is 11 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 15 Apr 2023 to 31 Mar 2024 (1 extension certificate on record).
  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 11

Title report28 Oct 2021View
Registration certificate3 Nov 2021View
Other28 Sep 2022View
Form 228 Jan 2023View
Form B24 Feb 2023View
Extension certificate18 Apr 2023View
Occupancy / completion certificate22 Sep 2023View
Allotment letter29 Sep 2023View
Show all 11 documents
OtherView
OtherView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P52100031662

Is Rahul Eastview II - Wing D and E delayed?

MahaRERA reports it completed. Its promised completion date was 15 Apr 2023.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100031662. The completion date moved from 15 Apr 2023 to 31 Mar 2024.

Who is the promoter?

MahaRERA records Rahul Constructions as the promoter of P52100031662.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100031662.

Answers are generated from the record.

Data through23 Nov 2026, 01:46SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology