Rahul Constructions

Company or firm · 2 projects · 4 MahaRERA registrations

2Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date2 of 4 past their proposed date, not extended
+3 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Rahul EastviewP52100000845Hadapsar2017Not reported31 Dec 2018—On date
Rahul EastviewP52100017005Hadapsar2018Not reported30 Oct 202031 Mar 2021+5 months
Rahul Eastview II - Wing D and EP52100031662Hadapsar2021Not reported15 Apr 202331 Mar 2024+11 months
Rahul EastviewP52100050478Hadapsar2023Not reported31 Dec 2023—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Rahul EastviewOn date
  • Rahul Eastview+5 mo
  • Rahul Eastview II - Wing D and E+11 mo
  • Rahul EastviewOn date

Track record notes

  • 2 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 11 months, for Rahul Eastview II - Wing D and E (P52100031662).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology