Rahul Constructions
Company or firm · 2 projects · 4 MahaRERA registrations
2Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date2 of 4 past their proposed date, not extended
+3 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Rahul EastviewP52100000845 | Hadapsar | 2017 | Not reported | 31 Dec 2018 | — | On date |
| Rahul EastviewP52100017005 | Hadapsar | 2018 | Not reported | 30 Oct 2020 | 31 Mar 2021 | +5 months |
| Rahul Eastview II - Wing D and EP52100031662 | Hadapsar | 2021 | Not reported | 15 Apr 2023 | 31 Mar 2024 | +11 months |
| Rahul EastviewP52100050478 | Hadapsar | 2023 | Not reported | 31 Dec 2023 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 11 months, for Rahul Eastview II - Wing D and E (P52100031662).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology