Rahul Constructions
Deedo IDDD-ZQ6ZOf 4 registrations whose promised date has arrived, 2 kept it (50%). The rest ran a median 8 mo late — longer than Maharashtra's 4 mo.
Delivery record
2 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Rahul EastviewP52100000845 | Hadapsar | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Rahul EastviewP52100017005 | Hadapsar | Certificate Signed | 30 Oct 2020 | 31 Mar 2021 | +5 mo |
| Rahul Eastview II - Wing D and EP52100031662 | Hadapsar | Completed | 15 Apr 2023 | 31 Mar 2024 | +11 mo |
| Rahul EastviewP52100050478 | Hadapsar | Completed | 31 Dec 2023 | 31 Dec 2023 | On date |
Rahul Constructions, in questions
Does Rahul Constructions finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 2 kept it (50%). The rest ran a median 8 mo late. Across Maharashtra, 73% kept their date.
How many projects has Rahul Constructions registered with MahaRERA?
2 projects under 4 MahaRERA registrations; 4 completed on MahaRERA.
Does Rahul Constructions have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.