RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P52100018448
Rajveer Creation · Pimpri Chinchawad (M Corp.), Pune · Waghere Promoters
Promised for 30 Dec 2022, extended once to 31 Mar 2026 — and that date has passed without the project marked complete on MahaRERA.
3 years and 11 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Dec 2022 to 31 Mar 2026 (1 extension certificate on record).
- !Risk: The latest completion date on record, 31 Mar 2026, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P52100018448
Is Rajveer Creation delayed?
Yes. MahaRERA records a promised completion of 30 Dec 2022, revised to 31 Mar 2026, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100018448. The completion date moved from 30 Dec 2022 to 31 Mar 2026.
Who is the promoter?
MahaRERA records Waghere Promoters as the promoter of P52100018448.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100018448.
Answers are generated from the record.
