Waghere Promoters
Deedo IDDD-ZZG5Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 26 mo late.
Delivery record
2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Rajveer NucleusP52100009974 | Wakad | Certificate Signed | 30 Dec 2025 | 30 Dec 2025 | On date |
| Manikbaug OrchidP52100010235 | Pimpri Chinchawad (M Corp.) | Certificate Signed | 30 Dec 2031 | 30 Apr 2032 | +4 mo |
| Rajveer CreationP52100018448 | Pimpri Chinchawad (M Corp.) | Certificate Signed | 30 Dec 2022 | 31 Mar 2026 | +47 mo* |
Waghere Promoters, in questions
Does Waghere Promoters finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 26 mo late. Across Maharashtra, 73% kept their date.
How many projects has Waghere Promoters registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 1 completed on MahaRERA.
Does Waghere Promoters have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.