Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P52100000581
Urban Nest Phase1 · Undri, Pune · Vtp Mohite Associates
Promised for 31 Mar 2020, extended once to 30 Mar 2022 — and that date has passed without the project marked complete on MahaRERA.
6 years and 8 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Mar 2020 to 30 Mar 2022 (1 extension certificate on record).
- !Risk: The latest completion date on record, 30 Mar 2022, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P52100000581
Is Urban Nest Phase1 delayed?
Yes. MahaRERA records a promised completion of 31 Mar 2020, revised to 30 Mar 2022, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100000581. The completion date moved from 31 Mar 2020 to 30 Mar 2022.
Who is the promoter?
MahaRERA records Vtp Mohite Associates as the promoter of P52100000581.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100000581.
Answers are generated from the record.