Vtp Mohite Associates
Company or firm · 4 projects · 4 MahaRERA registrations
4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
25%Kept RERA date1 of 4 past their proposed date, not extended
+14 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Trade Park Phase1P52100000518 | Undri | 2017 | Certificate Signed | 30 Dec 2019 | 29 Dec 2021 | +24 months |
| Urban Nest Phase1P52100000581 | Undri | 2017 | Certificate Signed | 31 Mar 2020 | 30 Mar 2022 | +24 months |
| Market PlaceP52100000587 | Undri | 2017 | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| tradeparkbP52100019796 | Undri | 2019 | Certificate Signed | 30 Jun 2026 | 30 Oct 2026 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 4 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 24 months, for Trade Park Phase1 (P52100000518).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology