Vtp Mohite Associates

Company or firm · 4 projects · 4 MahaRERA registrations

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
25%Kept RERA date1 of 4 past their proposed date, not extended
+14 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Trade Park Phase1P52100000518Undri2017Certificate Signed30 Dec 201929 Dec 2021+24 months
Urban Nest Phase1P52100000581Undri2017Certificate Signed31 Mar 202030 Mar 2022+24 months
Market PlaceP52100000587Undri2017Certificate Signed30 Dec 202130 Dec 2021On date
tradeparkbP52100019796Undri2019Certificate Signed30 Jun 202630 Oct 2026+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Trade Park Phase1+24 mo
  • Urban Nest Phase1+24 mo
  • Market PlaceOn date
  • tradeparkb+4 mo

Track record notes

  • 1 of 4 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 24 months, for Trade Park Phase1 (P52100000518).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology