Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52000022057

An Sunrise · Ulawe, Raigarh · Abdulnayeem Fatekhan

Promised for 8 Feb 2021, extended once to 8 Feb 2022 — and that date has passed without the project marked complete on MahaRERA.

5 years and 9 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 8 Feb 2021 to 8 Feb 2022 (1 extension certificate on record).
  • Risk: The latest completion date on record, 8 Feb 2022, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Registration certificate18 May 2020View
Extension certificate9 Sep 2021View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P52000022057

Is An Sunrise delayed?

Yes. MahaRERA records a promised completion of 8 Feb 2021, revised to 8 Feb 2022, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52000022057. The completion date moved from 8 Feb 2021 to 8 Feb 2022.

Who is the promoter?

MahaRERA records Abdulnayeem Fatekhan as the promoter of P52000022057.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52000022057.

Answers are generated from the record.

Data through30 Nov 2026, 01:55SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology