Abdulnayeem Fatekhan
Deedo IDDD-TMDFOf 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 23 mo late.
Delivery record
2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| An SunriseP52000022057 | Ulawe | Certificate Signed | 8 Feb 2021 | 8 Feb 2022 | +12 mo |
| A.n. BlueberryP52000025144 | Ulawe | Certificate Signed | 9 Sep 2022 | 9 Sep 2022 | On date |
| A N FloraP52000050542 | Ulawe | Certificate Signed | 5 Jan 2024 | 5 Jan 2024 | +34 mo* |
Abdulnayeem Fatekhan, in questions
Does Abdulnayeem Fatekhan finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 1 kept it (33%). The rest ran a median 23 mo late. Across Maharashtra, 73% kept their date.
How many projects has Abdulnayeem Fatekhan registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 2 completed on MahaRERA.
Does Abdulnayeem Fatekhan have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.