Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Certificate Signed

P51700047256

Aaraadhy Imperial · Dombivli, Thane · Nirmaan Realty

Promised for 15 Aug 2024 — that date has passed and MahaRERA does not mark the project complete.

2 years and 3 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 15 Aug 2024, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate13 Oct 2022View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51700047256

Is Aaraadhy Imperial delayed?

Yes. MahaRERA records a promised completion of 15 Aug 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51700047256.

Who is the promoter?

MahaRERA records Nirmaan Realty as the promoter of P51700047256.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700047256.