Nirmaan Realty
Deedo IDDD-VTCROf 3 registrations whose promised date has arrived, 2 kept it (67%). The rest ran a median 6 mo late.
Delivery record
2 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Aaraadhy ImperialP51700047256 | Dombivli | Certificate Signed | 15 Aug 2024 | 15 Aug 2024 | On date |
| Saket ImperialP51700050395 | Dombivli | Certificate Signed | 7 Aug 2025 | 7 Aug 2025 | On date |
| Ayodhya ImperialP51700054104 | Dombivli | Certificate Signed | 19 Apr 2026 | 19 Aug 2026 | +7 mo* |
| Shree Datta ImperialP51700080107 | Chole | Certificate Signed | 31 May 2027 | 30 Sep 2027 | +4 mo |
Nirmaan Realty, in questions
Does Nirmaan Realty finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 2 kept it (67%). The rest ran a median 6 mo late. Across Maharashtra, 73% kept their date.
How many projects has Nirmaan Realty registered with MahaRERA?
4 projects under 4 MahaRERA registrations; 2 completed on MahaRERA.
Does Nirmaan Realty have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.