Completed

P51500014780

Yashraj Angan · Aurangabad (M Corp.), Aurangabad · Rutuja Developers

Promised for 25 Dec 2021; MahaRERA reports the project completed.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 17

Title report26 Dec 2017View
Form B26 Dec 2017View
Commencement certificate11 Apr 2018View
Form 513 Oct 2018View
Form 530 Sep 2019View
Form 430 Sep 2019View
Occupancy / completion certificate23 Jan 2020View
Form 423 Jan 2020View
Show all 17 documents
Registration certificate9 Sep 2021View
Occupancy / completion certificate29 Apr 2023View
OtherView
Layout planView
Building planView
Allotment letterView
OtherView
OtherView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51500014780

Is Yashraj Angan delayed?

MahaRERA reports it completed. Its promised completion date was 25 Dec 2021.

How many extensions has it had?

Deedo holds 0 extension certificates for P51500014780.

Who is the promoter?

MahaRERA records Rutuja Developers as the promoter of P51500014780.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51500014780.

Answers are generated from the record.

Data through23 Nov 2026, 01:36SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology