Company or firm · 2 projects · 2 MahaRERA registrations · 1 reported completed

2Projects2 RERA registrations
1Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Yashraj AnganP51500014780Aurangabad (M Corp.)2018Completed25 Dec 2021—On date
Rutuviraj ApartmentP51500028674Aurangabad (M Corp.)2021Certificate Signed1 Jul 20251 Jul 2025On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Yashraj AnganOn date
  • Rutuviraj ApartmentOn date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology