RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
Completed
P50500015398
Prerna Elite · Nagpur (M Corp.), Nagpur · Vardan Buildcon
Promised for 30 Oct 2021; MahaRERA reports the project completed.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- ✓Clear: MahaRERA reports the project as completed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 3
Orders 0
No MahaRERA order or list names this number.
Questions about P50500015398
Is Prerna Elite delayed?
MahaRERA reports it completed. Its promised completion date was 30 Oct 2021.
How many extensions has it had?
Deedo holds 0 extension certificates for P50500015398.
Who is the promoter?
MahaRERA records Vardan Buildcon as the promoter of P50500015398.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P50500015398.
Answers are generated from the record.
Data through23 Nov 2026, 01:36SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology