Skip to content
Company or firm · first RERA registration 2018

Vardan Buildcon

Deedo IDDD-P395

Of 2 registrations whose promised date has arrived, 2 kept it (100%).

Projects55 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 5 registrations with dates moved or missed their RERA date · months late against the original promise

5 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Prerna EliteP50500015398Nagpur (M Corp.)Completed30 Oct 2021—On date
Prerna OrbitP50500023320Nagpur (M Corp.)Certificate Signed30 Mar 202430 Mar 2024On date
Prerna IconP50500033603Nagpur (M Corp.)Certificate Signed31 Mar 202731 Mar 2027On date
Prerna HarmonyP50500055895Nagpur (M Corp.)Active31 Mar 2029—On date
Prerna BlissPR1190002600771Nagpur (M Corp.)Certificate Signed31 Dec 203130 Apr 2032+4 mo

Vardan Buildcon, in questions

Does Vardan Buildcon finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 2 kept it (100%). Across Maharashtra, 73% kept their date.

How many projects has Vardan Buildcon registered with MahaRERA?

5 projects under 5 MahaRERA registrations; 3 completed on MahaRERA.

Does Vardan Buildcon have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology