Others · 1 building · 19 unitsRERA P52000054032

Shiv Samarth

Deedo IDDP-RAI-GT1N

Completion was pushed back 4 months to Sep 2026, and that date has passed too; no MahaRERA orders on record; 21% of its units are booked.

Wahal, Raigarh 410206 · by Manoj Omprakash Jaiswal · 33% of its projects kept the RERA date

Delivery6 mo latePromised May 2026 · revised Sep 2026 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales21% booked4 of 19 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months to Sep 2026, and that date has passed too

  • This projectRegistered 19 Dec 2023, completion promised 31 May 2026, revised to 30 Sep 2026, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000054032
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200005403219 Dec 202331 May 202630 Sep 2026Manoj Omprakash JaiswalProject page
Documents63

1 document held by Deedo, 62 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN.pdf · uploaded 11 Jul 2023Source

Legal

  • Legal Title reportTitle Report (2).pdf · uploaded 9 Jul 2023Source
  • Declaration Form BForm B.pdf · uploaded 11 Jul 2023Source

Migrated

  • 1 Copy of the legal title reportTitle Report (2).pdf · uploaded 9 Jul 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentPLAN.pdf · uploaded 9 Jul 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentcc.pdf · uploaded 9 Jul 2023Source
  • 1 a Details of encumbrances concerned to Financeno encumbrances certificate.pdf · uploaded 10 Jul 2023Source
Show all 63 documentsShow fewer documents

Migrated

  • 1 b Details of encumbrances concerned to Legalno encumbrances certificate.pdf · uploaded 10 Jul 2023Source
  • 1 Copy of Layout Approval (in case of layout)PLAN.pdf · uploaded 10 Jul 2023Source
  • 1 Declaration about Commencement CertificateDecleration abt cc.pdf · uploaded 10 Jul 2023Source
  • 1 Proforma of Allotment letterALLOTMENT DRAFT NEW.pdf · uploaded 10 Jul 2023Source
  • 1 Deviation Report with respect to Allotment letterDeviation allotment.pdf · uploaded 10 Jul 2023Source
  • 1 Deviation Report with respect to model copy of Agreementdeviation-draft sale.pdf · uploaded 10 Jul 2023Source
  • 1 PAN CardPAN.pdf · uploaded 11 Jul 2023Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 11 Jul 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 new.pdf · uploaded 13 Jul 2023Source
  • 1 CERSAI detailsCERSAI Search Report.pdf · uploaded 13 Jul 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDecleration in other project.pdf · uploaded 13 Jul 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A bank account decla.pdf · uploaded 13 Jul 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Manoj Jaiswal Form 3 New.pdf · uploaded 25 Jul 2023Source
  • 1 Other – TechnicalOther technical.pdf · uploaded 25 Jul 2023Source
  • 1 Proforma of Agreement for sale1 Proforma of Agreement for sale (9)_01 (16 files merged) (2).pdf · uploaded 1 Aug 2023Source
  • 2 Proforma of Agreement for sale2 Proforma of Agreement for sale.pdf · uploaded 1 Aug 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)REVISED FORM 2 MANOJ_1 (4 files merged).pdf · uploaded 8 Aug 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentPlinth CC.pdf · uploaded 13 Nov 2023Source
  • 2 Other – TechnicalPlinth CC.pdf · uploaded 13 Nov 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 11 May 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 11 Jul 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 SIGNED.pdf · uploaded 11 Jul 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Signed.pdf · uploaded 11 Jul 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 25 Dec 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 signed - converted.pdf · uploaded 25 Dec 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 25 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - converted.pdf · uploaded 22 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 SIGNED - converted.pdf · uploaded 22 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 22 Feb 2025Source
  • Form 1Form 1 30-06-2025.pdf · uploaded 8 Jun 2026Source
  • Form 2Form 2 Shiv Samarth 30-06-25 new.pdf · uploaded 8 Jun 2026Source
  • Form 3Form 3 30-06-2025 SHIV SAMARTH.pdf · uploaded 8 Jun 2026Source
  • Disclosure of Sold and Booked InventoryDisclosure of sold_ booked 30-06-2025.pdf · uploaded 8 Jun 2026Source
  • Form 1Form 1 30-09-2025.pdf · uploaded 8 Jun 2026Source
  • Form 2Form 2 Shiv Samarth 30-09-2025 new.pdf · uploaded 8 Jun 2026Source
  • Form 3Form 3 30-09-2025 SHIV SAMARTH.pdf · uploaded 8 Jun 2026Source
  • Disclosure of Sold and Booked InventoryDisclosure of sold_ booked 30-09-2025.pdf · uploaded 8 Jun 2026Source
  • Form 1Form 1 31-12-2025.pdf · uploaded 8 Jun 2026Source
  • Form 2Form 2.pdf · uploaded 8 Jun 2026Source
  • Form 3Form 3 31-12-2025 SHIV SAMARTH.pdf · uploaded 8 Jun 2026Source
  • Disclosure of Sold and Booked InventoryDisclosure of sold_ booked 31-12-2025.pdf · uploaded 8 Jun 2026Source
  • Form 1Form 1 31-12-2025.pdf · uploaded 8 Jun 2026Source
  • Form 2Form 2.pdf · uploaded 8 Jun 2026Source
  • Form 3Form 3 31-12-2025 SHIV SAMARTH.pdf · uploaded 8 Jun 2026Source
  • Disclosure of Sold and Booked InventoryDisclosure of sold_ booked 31-12-2025.pdf · uploaded 8 Jun 2026Source

Technical

  • DocumentPLAN.pdf · uploaded 9 Jul 2023Source
  • DocumentPLAN.pdf · uploaded 10 Jul 2023Source
  • Other – TechnicalOther technical.pdf · uploaded 25 Jul 2023Source
  • Other – TechnicalPlinth CC.pdf · uploaded 13 Nov 2023Source

Technical (Architect)

  • DocumentForm 1.pdf · uploaded 11 Jul 2024Source
  • DocumentForm 1.pdf · uploaded 25 Dec 2024Source
  • DocumentForm 1 - converted.pdf · uploaded 22 Feb 2025Source

Technical (Engineer)

  • DocumentFORM 2 SIGNED.pdf · uploaded 11 Jul 2024Source
  • DocumentForm 2.pdf · uploaded 25 Dec 2024Source
  • DocumentForm 2.pdf · uploaded 22 Feb 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Plot No 443 Sector 25A

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1RK, Shop19 units in all
Address
Plot No 443 Sector 25A, Sector 25A, PushpakPIN 410206
Village
Wahal, Panvel taluka
Land area for this project
250 sq m (2,690 sq ft)
Permissible built-up area
375 sq m (4,035 sq ft)
Sanctioned built-up area
375 sq m (4,035 sq ft)
Designated bank account
28
Developed in phases
No

Survey, CTS, gat or plot numbers

Plot No 443 Sector 25A

Land as published on MahaRERA's project page

Plot No 443 Sector 25A

Boundaries

North
Plot No 444
South
Plot No 442
East
Plot No 439 And 440
West
11 Mtr Wide Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking19 units

4 of 19 units booked (21%), as the promoter reported to MahaRERA

1BHK · 6 units1RK · 10 unitsShop · 3 units
TypeCarpet areaUnitsBooked
1BHK24.25 sq m · 261 sq ft62
1RK13.88 sq m · 149 sq ft62
1RK14.68 sq m · 158 sq ft20
1RK16.38 sq m · 176 sq ft20
Shop10.17 sq m · 109 sq ft20
Shop10.19 sq m · 110 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAtul Patel—
Chartered accountantD P Shejwal And Associates—
EngineerB S Sukthankar& Associates—
EngineerShahaji R Tanpure—

Source: MahaRERA project page. Contact details are not shown.