Manoj Omprakash Jaiswal
Deedo IDDD-Z8G5Of 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 27 mo late.
Delivery record
2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shree Karu Mata NiwasP52000026633 | Panvel | Certificate Signed | 1 Dec 2022 | 1 Dec 2022 | +47 mo* |
| Shiv SamarthP52000054032 | Wahal | Certificate Signed | 31 May 2026 | 30 Sep 2026 | +6 mo* |
| Shree Shankar PalaceP52000056096 | Pendhar | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | On date |
Manoj Omprakash Jaiswal, in questions
Does Manoj Omprakash Jaiswal finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 1 kept it (33%). The rest ran a median 27 mo late. Across Maharashtra, 73% kept their date.
How many projects has Manoj Omprakash Jaiswal registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 1 completed on MahaRERA.
Does Manoj Omprakash Jaiswal have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.