Completion was pushed back 1 year to Jun 2022, and that date has passed too; no MahaRERA orders on record; 0% of its units are booked.

Wahal, Raigarh 410206 · by Millennium Group

Delivery5 yrs 5 mo latePromised Jun 2021 · revised Jun 2022 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 18 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 1 year to Jun 2022, and that date has passed too

  • This projectRegistered 9 Aug 2020, completion promised 30 Jun 2021, revised to 30 Jun 2022, and still not shown completed today.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000026013
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P520000260139 Aug 202030 Jun 202130 Jun 2022Millennium GroupProject page
Documents30

3 documents held by Deedo, 27 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardPAN.pdf · uploaded 17 Mar 2020Source

Legal

  • Legal Title reportCopy of the legal title report.pdf · uploaded 17 Mar 2020Source
  • Declaration Form BFORM B Promoter_compressed.pdf · uploaded 18 Mar 2020Source
  • OtherLetter to Maha Rera.pdf · uploaded 15 Jul 2021Source

Migrated

  • 1 PAN CardPAN.pdf · uploaded 17 Mar 2020Source
Show all 30 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reportCopy of the legal title report.pdf · uploaded 17 Mar 2020Source
  • 1 Copy of Layout Approval (in case of layout)Copy of Layout Approval (in case of layout).pdf · uploaded 17 Mar 2020Source
  • 1 Building Plan Approval / NA Order for plotted developmentCopy of Layout Approval (in case of layout).pdf · uploaded 17 Mar 2020Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificates NA Order for plotted development.pdf · uploaded 17 Mar 2020Source
  • 1 Proforma of Allotment letterRera Act - Agreement For Sale New - Millenium ICON (1)-converted.pdf · uploaded 17 Mar 2020Source
  • 2 Proforma of Allotment letterAllotment Letter.pdf · uploaded 17 Mar 2020Source
  • 1 Declaration in FORM BFORM B Promoter_compressed.pdf · uploaded 18 Mar 2020Source
  • 1 Details of encumbrancesCERTIFICATE of Encumbrances.pdf · uploaded 1 Aug 2020Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 From CA.pdf · uploaded 1 Aug 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Millennium Icon.pdf · uploaded 7 Apr 2021Source
  • 1 Declaration about Commencement CertificateForm D.pdf · uploaded 8 Jul 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A.pdf · uploaded 8 Jul 2021Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of sold.pdf · uploaded 8 Jul 2021View
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_compressed.pdf · uploaded 8 Jul 2021Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_compressed.pdf · uploaded 8 Jul 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5.PDF · uploaded 8 Jul 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)Letter to Maha Rera.pdf · uploaded 15 Jul 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Letter to Maha Rera.pdf · uploaded 15 Jul 2021Source
  • 1 OtherLetter to Maha Rera.pdf · uploaded 15 Jul 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form - 5 - Icon.pdf · uploaded 10 Feb 2023Source

Technical

  • DocumentCopy of Layout Approval (in case of layout).pdf · uploaded 17 Mar 2020Source
  • DocumentCopy of Layout Approval (in case of layout).pdf · uploaded 17 Mar 2020Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Plot No 308, Sector 24

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1RK, Shop18 units in all
Address
Plot No 308, Sector 24, na, Village PushpakPIN 410206
Village
Wahal, Panvel taluka
Land area for this project
280 sq m (3,014 sq ft)
Permissible built-up area
419 sq m (4,509 sq ft)
Sanctioned built-up area
419 sq m (4,509 sq ft)
Designated bank account
85
Developed in phases
No

Survey, CTS, gat or plot numbers

Plot No 308Sector 24

Land as published on MahaRERA's project page

Plot No 308, Sector 24

Boundaries

North
Plot No 366
South
Plot No 217
East
Plot No 309
West
Plot No 307

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking18 units

0 of 18 units booked (0%), as the promoter reported to MahaRERA

1BHK · 11 units1RK · 3 unitsShop · 4 units
TypeCarpet areaUnitsBooked
1BHK21.49 sq m · 231 sq ft30
1BHK22.84 sq m · 246 sq ft30
1BHK27.91 sq m · 300 sq ft10
1BHK28.63 sq m · 308 sq ft30
1BHK36.07 sq m · 388 sq ft10
1RK19.01 sq m · 205 sq ft30
Shop8.3 sq m · 89 sq ft10
Shop9.61 sq m · 103 sq ft10
Shop9.62 sq m · 104 sq ft10
Shop11.48 sq m · 124 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDestination Architecture Interior Designs—
Chartered accountantGanpath Jain—
EngineerM/s. Agharkar Consulting Engineers Pvt. Ltd—
OtherBablu Enterprises—
Registered real estate agentSanjay Madanlal Jain—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Wahal

All 301 projects in Wahal · Compare Millennium Icon with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology