Millennium Group
Deedo IDDD-J4EROf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 58 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Millennium IconP52000026013 | Wahal | Certificate Signed | 30 Jun 2021 | 30 Jun 2022 | +65 mo* |
| Millennium KunjP52000030430 | Wahal | Certificate Signed | 30 Sep 2022 | 30 Sep 2022 | +50 mo* |
Millennium Group, in questions
Does Millennium Group finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 58 mo late. Across Maharashtra, 73% kept their date.
How many projects has Millennium Group registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Millennium Group have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.